American Pipe & Steel Corp. v. Firestone Tire & Rubber Co.

186 F. Supp. 904, 1960 U.S. Dist. LEXIS 4074
CourtDistrict Court, S.D. California
DecidedJuly 19, 1960
DocketNo. 459/57
StatusPublished
Cited by2 cases

This text of 186 F. Supp. 904 (American Pipe & Steel Corp. v. Firestone Tire & Rubber Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Pipe & Steel Corp. v. Firestone Tire & Rubber Co., 186 F. Supp. 904, 1960 U.S. Dist. LEXIS 4074 (S.D. Cal. 1960).

Opinion

WESTOVER, District Judge.

The United States Government gave to Firestone Tire & Rubber Company, defendant herein (hereinafter referred to as Firestone), a contract for the fabrication and construction of Corporal Missiles. At the same time the Government gave to Firestone a contract for the manufacture of shipping containers for the missiles.

The original contract .covering the missile containers provided they were to be made of wood, but after a number had been so constructed it was decided by the Government that metal containers would be superior. Redesigned plans and specifications for metal containers were given Firestone. In the redesigned plans and specifications torsion bar lever arms were designed, the purpose of which was to hold the missile in place and keep it from moving around within the container while in transit. The plans and specifications furnished Firestone by the Government called for torsion bar lever arms five inches in diameter at the widest point.

After Firestone received the original contract for wooden containers, it sublet to other contractors the work of manufacturing the containers. Among the subcontractors was Hammond Manufacturing Company. Hammond originally manufactured wood containers. After the design of the containers had been changed from wood to metal, Hammond manufactured ten of the metal containers. 4

Although Firestone’s plans and specifications from the Government indicated the torsion bar lever arms were to be five inches in diameter at the widest point, nevertheless, Firestone, in its preparation of drawings for metal containers to be used by Hammond and subsequently by the plaintiff herein, reduced the metal torsion bar lever arm from five inches to four inches. When the metal containers with the four-inch torsion bar lever arms were delivered by Hammond and put into use by the Government, it was discovered the four-inch torsion bar lever arms bent under stress and use and distorted and were unsatisfactory. Firestone attempted to obtain authority from the Government for use of the four-inch torsion bar lever arm but never received such authority. Firestone also attempted to rectify the defect by placing along the side of the torsion bar lever arm a steel plate. Firestone attempted to obtain authorization from the Government for use of the steel plate, but no authorization was ever received from the government.

As hereinabove stated, when Firestone entered into the contracts with plaintiff for fabrication of metal containers it gave plaintiff plans and specifications for the containers. The plans and specifications called for four-inch torsion bar lever arms. Firestone knew, prior to execution of the contracts with plaintiff, that the torsion bar lever arms bent and distorted under stress and strain; that use of four-inch torsion bar lever arms had not been authorized by the Government, and that its attempt to rectify the fault by use of a steel plate had also hot been authorized.1 Nevertheless, with this. [906]*906knowledge at hand, Firestone went ahead, entered into the contracts with plaintiff and gave to plaintiff plans and specifications which included four-inch torsion bar lever arms.2

Upon execution of the contracts plaintiff immediately commenced work upon the metal containers and was progressing thereon when it received notice from Firestone to cease installation of the torsion bar lever arm until a new bar could be designed, tested and approved by the Government.2 3 Upon receipt of the notice, plaintiff at once stopped all work upon the containers.

The entire facilities of plaintiff in Alhambra, California, had been given over to performance of the contract, and at the time of the stop order the containers in various stages of completion were scattered over the floor of plaintiff’s manufacturing plant. Plaintiff contends that inasmuch as it did not know whether the stop order in question would remain in effect for days, weeks or months, it was unable to use its premises for any other purpose.

Some thirty-odd days after receipt of the stop order, defendant gave plaintiff new plans and specifications covering a [907]*907redesigned torsion bar lever arm; whereupon plaintiff completed its contract satisfactorily, delivered the containers and was paid by Firestone the price as set forth in the contract.

The contracts between plaintiff and defendant provided, in part, as follows:

“The Firestone Tire & Rubber Company may at any time by written order, make changes in any of the drawings, designs, specifications, method of shipments or packing and place of delivery.
“If any such change causes an increase or decrease in the cost of the unit price of the articles ordered, an equitable adjustment shall be made in the contract price by amendment thereto.”
“(A) If any change materially affects the estimated cost of, or time required for the performance of the work, an equitable adjustment shall be made in the fixed price or time of performance or both.”

Inasmuch as the change in the torsion bar lever arm caused an increase in the estimated cost and in the unit price of the containers, an equitable adjustment was made between the parties by which defendant paid plaintiff $46,259.88 in addition to the contract price. However, plaintiff contends the change in design of the torsion bar lever arm caused a delay of approximately thirty days in performance of the contract, during which period plaintiff’s manufacturing plant had remained idle and overhead accumulated, and that consequently not only was plaintiff entitled to an equitable adjustment as to the unit price but also to an equitable adjustment for overhead resulting from the time lost by reason of the stop order.

Defendant admitted liability for direct cost occasioned by the stop order but denied liability for all indirect cost. As a result of the controversy this action was filed.

The first question to be resolved by the Court is whether the contracts between plaintiff and defendant were Government contracts. The contracts between defendant and the United States of America were Government contracts, having as their subject the construction and manufacture of missiles and missile containers for the United States of America. Plaintiff contends that as the contracts now before the Court were entered into by and between two private corporations they were not Government contracts but private contracts.

When defendant proposed to enter into the contracts herein involved with plaintiff, notice of the proposed contracts was given to the Government, as provided in the contract between the Government and Firestone. Plaintiff knew Firestone had the prime contract with the Government and that plaintiff’s subcontract was a part of the prime contract. No merit is found in the contention that the contracts herein (between plaintiff and defendant) were not Government contracts.

The next question confronting the Court is the meaning of the words “equitable adjustment” as used in- the contracts. Defendant- contends this term has been defined by the United States Supreme Court in United States v. Rice, 317 U.S. 61, 63 S.Ct. 120, 87 L.Ed. 53, and that, according to the definition as promulgated by the Supreme Court, plaintiff cannot recover indirect costs. The Supreme Court said, 317 U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ruhlen v. Montgomery (In Re Montgomery)
310 B.R. 169 (C.D. California, 2004)
Dobson v. Rutgers, State University
384 A.2d 1121 (New Jersey Superior Court App Division, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
186 F. Supp. 904, 1960 U.S. Dist. LEXIS 4074, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-pipe-steel-corp-v-firestone-tire-rubber-co-casd-1960.