American Pipe & Construction Co. v. State

159 N.E. 892, 247 N.Y. 150, 1928 N.Y. LEXIS 1051
CourtNew York Court of Appeals
DecidedJanuary 10, 1928
StatusPublished
Cited by3 cases

This text of 159 N.E. 892 (American Pipe & Construction Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Pipe & Construction Co. v. State, 159 N.E. 892, 247 N.Y. 150, 1928 N.Y. LEXIS 1051 (N.Y. 1928).

Opinion

Kellogg, J.

The Bellew and Merritt Co. and the State of New York entered into a written contract, known as Barge Canal Contract No. 49.. The former thereby agreed to construct, in accordance with plans and specifications annexed, a section of the Barge canal in Wayne county having a length of about six miles. The latter agreed to pay, for the work and materials furnished, the unit prices specified in an agreed schedule. The Bellew and Merritt Co. sublet a large part of the work *153 to a subcontractor, which in turn sublet a part of the work undertaken by it. Subsequently the corporate name of the Bellew and Merritt Co. was changed by order of court to the Merritt Construction Company.” The Merritt Construction Company thereafter assigned Barge Canal Contract No. 49, with the consent of the State, to the claimant, the American Pipe and Construction Co. The contract work was carried to completion by the two subcontractors and the claimant, and was accepted by the State. Thereafter the claimant filed this claim for additional compensation, asserting that it had performed work and furnished materials for which it had not been paid, and that it was entitled to payment therefor. The claim set forth a large number of items, but, owing to a stipulation entered into between the parties, we need consider here, none other than the items 47, 42, 43, 40 and 39, as the same were numbered in Schedule A ” attached to the claim. The Court of Claims, after a trial, made findings in reference to these items, determining all issues of fact in favor of the claimant. As to items 47, 42, 40 and 39, it dismissed the claim on the ground that the services performed or materials furnished were performed or furnished by subcontractors and not by claimant, and that the latter had suffered no damage.. As to item 43, it found that the claimant furnished materials and labor of the value of $1,055.32 and made an award in its favor for that amount. As to materials and labor constituting the balance of the item, it dismissed the claim on the ground that they were furnished by the subcontractors and not by the claimant. The claim, as to all other items, was dismissed. Judgment was directed in favor of the claimant for $1,055.32. The claimant took an appeal, stipulating that it would bring up for review the decision of the Court of Claims in respect to the five numbered items only, and that it would rest upon the findings of fact made by the Court of Claims in reference to such items. Accordingly, the *154 record upon appeal was made up to contain the decision of the Court of Claims, the findings proposed by the claimant and the State, with the court’s rulings thereupon, the original contract between the Bellew and Merritt Co. and the State, the plans and specifications, and other proof of a purely documentary character. No testimony given upon the trial was incorporated in the record. The State did not appeal. Upon the record so made the Appellate Division reversed the judgment below and directed judgment for the claimant upon each of the five items. The State appealed from the decision thus made and upon the facts found by the Court of Claims, considered in the light of the documentary proof set forth in the record, asks for a reversal. We will deal separately with the five disputed items.

Item 47. The essential facts found were these: That part of the Barge canal prism which the claimant’s assignor agreed to construct incorporated within its boundaries, for a certain distance, a portion of the old Erie canal. In the improvement of that canal the State had used, at various points, timbers and sheet piling to hold the banks in place. This construction consisted of driven piles, timbers extending to cover the spaces between the piles, and sheet piling covering the timber work. The structure had become covered with dirt and silt and was not visible when contract No. 49 was executed. The claimant’s assignor was not aware of the presence of the piling when it signed- the contract. The State, having erected the piling, was chargeable with knowledge of its presence within the limits of the Barge canal prism. No reference was made to the piling in contract No. 49 or the plans and specifications annexed thereto. Its removal was not specifically called for thereby. However, the claimant does not assert, and the Court of Claims has not found, that the State made any misrepresentation of fact in regard to the presence of the piling. The sheet piling construction was removed by one of the subcon *155 tractors in the course of its work of excavation. The piling removed extended- through a distance of 1,658 feet, and the fair and reasonable value of removing the same was $3,863.14.

The essential thing which the Beílew and Merritt Co., under contract No. 49, promised to construct was a canal prism of a certain width and depth as shown upon plans annexed to the contract. To this end it necessarily agreed to remove all material within the lines of the prism of whatever name or kind. It particularly promised to make approximately 1,543,600 cubic yards of excavation ” for twenty-three cents per cubic yard. The nature of the material to be excavated was not specified. Excavation ” was the thing agreed to be made. The word is defined by the contract specifications as follows: Excavation shall consist of the loosening, loading, transporting and depositing of all material, whether wet or dry, of every name and nature necessary to be removed, for the purpose of forming the canal prism, ditches, pits for structures, for obtaining material from borrow pits, or for any other purpose necessary to complete the works under contract * * *.” In removing the piling construction, therefore, the subcontractor merely performed the contract duty of the Bellew and Merritt Co. to make excavation for the canal prism. The contractor was entitled to receive therefor the sum of twenty-three cents per cubic yard and no more. It has been paid that sum. Therefore, the claimant, under item 47, may have no recovery.

Item 42. The facts found are these: The contract called for the construction in the new channel of the Barge canal of a lock known as lock 30. The old channel of the Erie canal was to the south of the new channel. A portion thereof was to be utilized as a ditch for" the purpose of passing water around lock 30, as in time of flood. In this portion of the old canal was lock 61 of the old Erie canal. To construct the by-passing ditch it *156 became necessary to remove about ten cubic yards of masonry from lock 61. This was done by one of the subcontractors. The reasonable value of such work was 1204.

As in the case of item 47, the work performed was work of excavation, within the terms of the contract, for which the contractor was to receive twenty-three cents per cubic yard. The specifications, in the clause heretofore quoted, define excavation to include “ material of every name and nature necessary to be removed ” whether for the purpose of forming the canal prism ” or necessary “ ditches.’ Moreover,'they seem otherwise particularly to provide for the condition here found, for they specify that stones in existing structures removed by the contractor shall remain the property of the State

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valdez v. Gonzales
176 P.2d 173 (New Mexico Supreme Court, 1946)
J. Harry McNally, Inc. v. State
170 Misc. 914 (New York State Court of Claims, 1939)
Phoenix Title & Trust Co. v. Continental Oil Co.
29 P.2d 1065 (Arizona Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
159 N.E. 892, 247 N.Y. 150, 1928 N.Y. LEXIS 1051, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-pipe-construction-co-v-state-ny-1928.