American Municipal Power, Inc. v. Voith Hydro, Inc.

CourtDistrict Court, S.D. Ohio
DecidedFebruary 1, 2022
Docket2:17-cv-00708
StatusUnknown

This text of American Municipal Power, Inc. v. Voith Hydro, Inc. (American Municipal Power, Inc. v. Voith Hydro, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Municipal Power, Inc. v. Voith Hydro, Inc., (S.D. Ohio 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF OHIO EASTERN DIVISION

AMERICAN MUNICIPAL POWER, INC.

Plaintiff, Case No. 2:17-cv-708

vs. Chief Judge Algenon L. Marbley

Magistrate Judge Elizabeth P. Deavers

VOITH HYDRO, INC.,

Defendant.

OPINION AND ORDER

This matter is before the Court to consider the Motion for Additional Deposition Time filed by Defendant Voith Hydro, Inc. (“Voith”). (ECF No. 211.) Plaintiff American Municipal Power, Inc. (“AMP”) filed a Response (ECF No. 212) and Voith filed a Reply (ECF No. 219). For the following reasons, Voith’s Motion is GRANTED, in part. I. The issue here is whether Voith has demonstrated that additional deposition time is necessary to fairly examine Pete Crusse as contemplated by the Federal Rules of Civil Procedure. Specifically, Voith requests two additional seven-hour days for the completion of his fact deposition. As far as relevant background, the parties, acknowledging the specific nature of the case, had agreed to a default limit of two seven-hour days for fact witness depositions of all AMP and Voith employees. While there is some apparent disagreement as to whether this default limit was set in stone as to Mr. Crusse or remained open to revisitation, there is no debate that the additional time Voith requests here would both exceed the default limit as applied to other deponents and be in addition to Mr. Crusse’s 14-hour Rule 30(b)(6) deposition. Accordingly, the current dispute is straightforward and Voith argues that the following reasons justify an extension of the deposition. This case, involving the construction of four separate hydroelectric power plants, is remarkable in length, breadth and dollar value. Mr.

Crusse had and continues to have unparalleled responsibility with respect to the construction projects and the claims arising from those projects such that other deponents including AMP’s expert, have consistently deferred to him. Given the singular nature of his involvement, Voith asserts that it requires additional deposition time to address three remaining matters: (1) installation contractor claims; (2) Voith equipment alignment and powerhouse foundation settlement issues; and (3) submittal milestone liquidated damages. This need remains, according to Voith, despite the numerous topics it already has explored with Mr. Crusse in his individual deposition, including, inter alia, AMP’s discharge ring claim, the circumstances surrounding the 2012 Memorandum of Understanding, and AMP’s assessment of equipment delivery milestone

liquidated damages, all topics involving significant dollar amount claims. Voith also details that, given Mr. Crusse’s documented and comprehensive involvement in this litigation, this additional deposition time will not present any undue burden. To counter, AMP contends that the 14-hour default time period already recognizes and accounts for the complex nature of this case. As AMP sees it, it was able to complete its depositions within the default time period and it is both Voith’s demonstrated inefficiency and failed prioritization strategy that prevented it from timely completing Mr. Crusse’s deposition. According to AMP, this fact, as well as the nature of the remaining deposition topics, do not justify Voith’s request for additional time. Further, AMP asserts that the burden presented by an additional fourteen hours of deposition time on top of the 28 hours Mr. Crusse already has undergone amounts to harassment, especially because testimony already has been offered on these three topics by other witnesses. Finally, AMP suggests that if the Court finds additional discovery to be warranted, less burdensome alternatives exist. II.

Federal Rule of Civil Procedure 30(d)(1) provides as follows: Unless otherwise stipulated or ordered by the court, a deposition is limited to one day of 7 hours. The court must allow additional time consistent with Rule 26(b)(1) and (2) if needed to fairly examine the deponent or if the deponent, another person, or any other circumstance impedes or delays the examination.

The Advisory Committee Notes to the 2000 amendments to the Rules of Civil Procedure state that the party seeking a deposition longer than the Rules permit “is expected to show good cause to justify such an order.” The Notes indicate that the limit had been imposed in order to reduce cost and delay in the discovery process. But the Committee also recognize that in some situations an extension will be needed, especially if the events to be inquired about took place over a lengthy period of time, or if the witness is provided documents in advance but fails to review them, thus prolonging the deposition with activity which should have taken place before the deposition began. The cases are generally consistent with these principles, but also place a burden on the requesting party to show that he or she acted diligently in attempting to complete the deposition within the time allotted by Rule 30(d)(1). Jones-McNamara v. Holzer Health Sys., No. 2:13-CV-616, 2014 WL 4202496, at *1 (S.D. Ohio Aug. 22, 2014) (citing Beneville v. Pileggi, 2004 WL 1631358 (D. Del. July 19, 2004) (the moving party has the burden to demonstrate that additional time is necessary)). III.

At the outset, the Court offers two observations. First, many points raised by the parties are simultaneously true. Further, the Court’s ongoing discovery management provides critical context for the current motion. As to the first observation, yes, this case is complex and high stakes involving events occurring over a long period of time; yes, the parties generally have accounted for these circumstances with respect to deposition length; yes, AMP completed its depositions in a timely manner; yes, by all accounts Mr. Crusse appears uniquely situated among witnesses; yes, despite this, he is not the only witness with relevant information on these topics and Voith has deposed or will depose several other witnesses; yes, AMP ignores the distinction between Mr. Crusse’s fact and Rule 30(b)(6) depositions; yes, a 28-hour fact deposition would be four times the limit set forth in Rule 30(b)(1); yes, Voith’s motion is tinged with a tone of entitlement; and yes, AMP’s counter argument is not focused on the relevance of the remaining topics. As to the matter of context, the Court is familiar with tendencies toward leaving not even

the tiniest pebble unturned, sometimes to questionable avail. The parties’ motions practice frequently has amounted to little more than a critique of the other party’s litigation strategy masquerading as substantive objection. Petulant stalemates have not been uncommon and the current motion presents no exception - Voith believes fourteen hours of additional time is necessary and, therefore, it is entitled to it; AMP asserts that it said no and meant it. Finally, an admonition is worthy of a reminder: the issues at stake, amount in controversy, and the parties’ resources, while certainly Rule 26(b)(1) considerations, are not to be construed as justification for either limitless discovery or the monopolization of judicial resources. As to this final point of context, notably in this particular instance, Voith’s request for additional deposition time is limited to Mr. Crusse. Presumably, this reflects both Voith’s awareness of the magnitude of this particular request and an appreciation that, under the circumstances here, it is not one to be made lightly. With all of the above in mind, the Court turns first to the issue of diligence. Voith explains its method for deposition topic evaluation and ranking as evidence of its diligence.

AMP challenges the wisdom of Voith’s efforts.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
American Municipal Power, Inc. v. Voith Hydro, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-municipal-power-inc-v-voith-hydro-inc-ohsd-2022.