American Metal Products Co. v. A. Geo. Schultz Co.

267 N.W. 19, 221 Wis. 291, 1936 Wisc. LEXIS 352
CourtWisconsin Supreme Court
DecidedApril 28, 1936
StatusPublished
Cited by4 cases

This text of 267 N.W. 19 (American Metal Products Co. v. A. Geo. Schultz Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Metal Products Co. v. A. Geo. Schultz Co., 267 N.W. 19, 221 Wis. 291, 1936 Wisc. LEXIS 352 (Wis. 1936).

Opinion

Fairchild, J.

Respondent made the agreement with appellant set out in the statement of facts. Under the stipulations of that agreement an easement over respondent’s land was provided for, and a sidetrack bringing switching facilities to the boundary of appellant’s land was to be constructed by respondent. The appellant is entitled to specific performance of the contract on respondent’s part: (1) If the time has arrived for the performance of this covenant; that is, if the clause “at such time as it [respondent] will begin building operations” can fairly be construed to refer to the time of building the sidetrack, and not to constitute a condition that the sidetrack will be built only if the respondent determines to improve its property; (2) if the contract is not too indefinite and uncertain, with respect to location of the sidetrack, to' be capable of specific performance; (3) unless the inconvenience and expense to respondent is so great compared to the benefits to be derived by appellant from the [296]*296building of the track as to make it inequitable to compel' specific performance.

As to time of performance, the trial court was persuaded that following literally the language of the contract, respondent was not bound to furnish the sidetrack until after the commencement of building operations by it upon the land secured through appellant, and that “neither the actual construction nor the preliminary planning and location of the sidetrack could possibly be commenced until the defendant had determined the location of its own proposed new buildings, which the sidetrack was clearly intended mutually to serve, along with the building of the plaintiff.” The time for performance of the covenant to build a sidetrack is expressed in the contract as being “at such time as it [respondent] will begin building operations.” These words alone do not constitute an expression of a definite time for performance of the agreement to build a sidetrack, but they do express a definite intention to “begin building operations.” After a consideration of the contract before us in its entirety, we are of the opinion that it was designed to and does express the intentions of the parties to arrange between themselves a plan under which each would meet what were then considered immediate and existing needs. That portion of the contract which states:

“As a further consideration, the said A. Geo. Schultz Company, party of the second part agrees that it will give the Chicago, Milwaukee & St. Paul Railway Company and Chicago & Northwestern Railway Company an easement for a sidetrack on its own land and over tracts Number One and Two up to the east line thereof, and agrees to construct said track on such easement to' the said east line of said property at its own cost and expense, at such time as it will begin building operations and it does hereby grant to said party of the first part, its successors and assigns, the right to connect or extend the said track at the cost and expense of said party of the first part on its own property just east, as well as the [297]*297right to use and enjoy the said sidetrack for such switching purposes as may be necessary to meet the needs of said party of the first part,”—

together with such phrases as: “Whereas, The A. Geo. Schultz Company . . . desires this tract of land to enlarge its own holdings to meet its needs, ...” and the words: “Whereas, The said American Metal Products Company ... to meet its needs, ...” too clearly evidence a then present purpose to proceed with the plans referred to, to permit the conclusion that the parties were arranging for contingencies to arise in the distant future. The word “needs,” as here used, unaccompanied by any suggestion that future developments were being considered, carries a meaning of preparation to encounter conditions at hand. As an inducement to appellant to give up its option on tract Number One and move to the land described as tract Number Three, respondent was agreeing to pay cash to cover the value of the option, some of the expense incidental to the preparing of tract Number Three, and to provide appellant with a sidetrack and switching facilities. In fact, the switching facilities were practically the inducing cause. Other arrangements made did not more than approximate in value the disadvantage suffered by appellant in the exchange of property. There was considerable of an element of accommodation in the transaction if the value to the appellant of the sidetrack is to be determined entirely by the respondent. There is no doubt of appellant’s intention to act immediately, and the considerations offered by respondent in cash and the agreement to build the sidetrack must be weighed with the relation in mind, of things incident to the accomplishment of the things stipulated for, and the expense incurred by appellant by releasing his interest in tract Number One, and building on tract Number Three.

That prompt action was contemplated by both parties is further evidenced by the contents of letters which were writ[298]*298ten on June 14, 1920, and June 16, 1920. In the letter from appellant to respondent, dated June 14, 1920, we find these words: “So in asking you $5,500 there is very little more cost involved and if you grant it, and build the sidetrack as previously agreed, we on our part are ready to close the matter.” Later in the same letter there are these words (referring to' the building of the sidetrack) : “But not later than one year from date.” Those words, upon objection of respondent, were stricken out. The objection to those words was in a letter from respondent to appellant dated June 16, 1920, and after agreeing to pay the $5,500, it wrote: “For the purpose of placing land that you intend to purchase east of the above-mentioned four hundred feet, in the same condition as the property upon which you hold an option. We also agree to allow you the privilege of using our private sidetrack that may be built on our property. We cannot guarantee any .set time or place as to when or where this sidetrack will be built, but at the present time indications are that the same will be built approximately as shown on blueprints.” After the words “but not later than one year from date” were stricken, the appellant’s letter of June 14th, in this respect, then read: “We are not unmindful, however, of the savings effected us by having the privilege of using the sidetrack you propose to- install, which we understand, you will do as soon as convenient.” With these facts at hand, the only conclusion fairly to be drawn is that the appellant was to have that sidetrack within a reasonable time. “If a reasonable time of performance is contemplated, failure to- fix a definite time does not render the contract indefinite.” 6 Page, Contracts, § 3283. Citing, Penney v. Norton, 202 Ala. 690, 81. So. 666; Ullsperger v. Meyer, 217 Ill. 262, 75 N. E. 482; Dingman v. Hilberry, 159 Wis. 170, 149 N. W. 761; Boyington v. Sweeney, 77 Wis. 55, 45 N. W. 938. In addition to the authorities just cited, the following cases support the proposition that if the respondent had agreed to pay appellant [299]*299$5,500 “at such time as it will begin building operations,” such an agreement would fix the time of payment within a reasonable time. Valley Fruit Co. v. Swash, 134 Wash. 697, 236 Pac. 273; Nunes v. Dautel, 19 Wall. 560; Noland v. Bull, 24 Or. 479, 33 Pac. 983; Voight v. Voight, 96 Neb. 465, 148 N. W. 83; Greenstreet v. Cheatum, 99 Kan. 290, 161 Pac. 596; Randall v. Johnson, 59 Miss. 317; Button v. Higgins, 5 Colo. App. 167, 38 Pac. 390.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B&D Contractors, Inc. v. Arwin Window Systems, Inc.
2006 WI App 123 (Court of Appeals of Wisconsin, 2006)
Praefke v. Sentry Insurance
2005 WI App 50 (Court of Appeals of Wisconsin, 2004)
Chevron Chemical Co. v. Deloitte & Touche
483 N.W.2d 314 (Court of Appeals of Wisconsin, 1992)
Brevig v. Webster
277 N.W.2d 321 (Court of Appeals of Wisconsin, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
267 N.W. 19, 221 Wis. 291, 1936 Wisc. LEXIS 352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-metal-products-co-v-a-geo-schultz-co-wis-1936.