American Indemnity Co. v. Peak

255 P. 975, 123 Kan. 502, 1927 Kan. LEXIS 280
CourtSupreme Court of Kansas
DecidedMay 7, 1927
DocketNo. 27,347
StatusPublished

This text of 255 P. 975 (American Indemnity Co. v. Peak) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Indemnity Co. v. Peak, 255 P. 975, 123 Kan. 502, 1927 Kan. LEXIS 280 (kan 1927).

Opinion

The opinion of the court was delivered by

Hopkins, J.:

The plaintiff as surety for the National Paving Company of Oklahoma City executed a maintenance bond guaranteeing certain paving. The bond was executed on the application of the defendants, who were the officers and chief stockholders of the [503]*503paving company. Having been compelled to pay the city because of defects in the paving, plaintiff brought this action to recoup its damages from defendants. Plaintiff was defeated and appeals.

The plaintiff alleged, in substance, that it was a Texas corporation engaged in the general business of acting as surety for persons and corporations engaged in constructing paving and similar work; that the defendants were officers and principal stockholders of the National Paving Company, an Oklahoma corporation; Stingley, president, and Peak, vice president; that the paving company, under the active management of the defendants, became and was the successful bidder for certain paving in Oklahoma City, requiring a bond of $38,758, conditioned upon its paying for all work and materials used in the performance of its contract; that plaintiff at the especial instance and request of the paving company and as a result of the personal solicitation of the defendants became the surety upon such bond; that as a further condition pertaining to the letting of the paving contract, the paving company was required to execute a maintenance bond guaranteeing the maintenance of the paving for a'period of five years after completion and acceptance of the work; that defendants being fully conversant with all the requirements of the city, after extensive negotiations procured the plaintiff to execute a maintenance bond in the sum of $38,758, guaranteeing the maintenance of the paving for a period of five years; that such bond was eventually executed by plaintiff upon a formal written application by defendants; that the application for such maintenance bond was executed by the paving company and by the defendants as sureties; that thereafter, as additional security to plaintiff for the execution of the maintenance bond and other bonds, the plaintiff required the paving company to' deposit $3,000 in the American National Bank, and a certificate thereof to be assigned to the plaintiff. Provisions of the application and bond are set out in the petition in much detail. It is alleged that the paving company duly entered upon the work of constructing the paving, which was completed and accepted by the city August 21, 1917; that the paving company failed to pay for material and labor provided in its contract in accordance with the terms of the bond first mentioned, as a result of which plaintiff was compelled to pay a judgment for the paving company of $10,588; that thereafter, for the purpose of reimbursement, the plaintiff brought suit against the paving company and the [504]*504American National Bank to recover the value of the certificate of deposit; that the paving company joined in the prayer of plaintiff, as a result o'f which the certificate of deposit was collected in the sum of $4,050 and applied by plaintiff upon the indebtedness of the paving company. It was further alleged that within less than 18 months after completion of the paving it became badly cracked, which condition increased to crumbling until by January, 1921, the entire pavement, with some, exceptions, became and was impassable and useless; that thereafter the city of Oklahoma City commenced an action against the paving company and plaintiff to recover the sum of $38,758; that defendants were notified of such suit and importuned to defend it, but failed to do so; that plaintiff defended the action but was compelled to respond in satisfaction of a judgment against it of $8,500; that attorney’s fees and other expenses of such litigation brought the amount in all to $13,300, for which amount plaintiff prayed judgment. Copies of the various instruments, including the application and bond, were attached as exhibits to plaintiffs petition.

The defendants answered denying generally the allegations of the petition. They pleaded also the five-year statute of limitations, and the three-year statute of limitations. For a further defense, they alleged that plaintiff took possession of a plant used in the laying of hard-surface roads, of wagons, motors, etc., of a total .value of $19,500, which more than satisfied the claims, if any, of plaintiff against the defendants and the National Paving Company. They also alleged that plaintiff had recovered the sum of $4,050 on the certificate of deposit mentioned in plaintiff’s petition.

The plaintiff in reply denied the allegations of new matter set up in the answer of the defendants and further alleged that in a certain attachment action brought by the plaintiff against the National Paving Company, the paving plant and equipment referred to by the defendant in its answer had been seized, appraised and sold and that there was realized therefrom approximately the sum of only $250.

Trial was to the court; evidence to sustain the allegations of both parties; general judgment for defendants; no special findings.

The plaintiff contends that the judgment was contrary to the evidence. Defendants contend that the action is barred by the five- and three-year statutes of limitations; that there was a variation [505]*505between the application signed by them and the bond executed by plaintiff; that plaintiff received credits (money and property) from defendants in excess of the amounts claimed.

In support of the contention that the action was barred by the statute of limitations, the defendants say that the paving was completed Thanksgiving day in November, 1916; that the city made no demands for repairs under the bond until December 8, 1921, more than five years after completion of the work. The petition alleged and there was evidence in support of the allegation that the paving began to crack within eighteen months after it was completed, and continued to grow worse until; with some exceptions, the entire pavement had become useless within five years after its completion. The city made due demand upon the plaintiff within time to compel compliance with the provisions of the bond. Plaintiff’s cause of action against the defendants accrued when it paid the judgment in favor of the city, April 21, 1924. Action was filed against defendants in August, 1924. Neither the five- nor the three-year statute of limitations had. run against plaintiff’s cause of action, and defendants’ contention in this regard, therefore, cannot be sustained.

With respect to variations between the application and the bond it is contended:

“That the application did not specify the amount of indemnity to be named in the bond and that when a bond of 100 per cent of the contract price was executed, it therefore was not'in accordance with the application; that the application called for a maintenance bond for five years from the completion of the paving while the bond itself called for five years from completion and acceptance; that the application in no way contemplated the provision in the bond itself, whereby the city engineer and commissioners possessed the power of determining the amount necessary to place the pavement in proper condition to stand up.”

It may be noted that the city, in its requirements expressed in the advertisement for bidders, required a maintenance bond for the full amount of the contract price for five years from the date of the completion and acceptance of the improvements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McClure v. Freeborn Engineering & Construction Co.
156 P. 692 (Supreme Court of Kansas, 1916)
Standard Asphalt & Rubber Co. v. Texas Building Co.
99 Kan. 567 (Supreme Court of Kansas, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
255 P. 975, 123 Kan. 502, 1927 Kan. LEXIS 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-indemnity-co-v-peak-kan-1927.