American Home Assurance Co. v. Gemma Construction Co.

275 A.D.2d 616, 713 N.Y.S.2d 48, 2000 N.Y. App. Div. LEXIS 9158
CourtAppellate Division of the Supreme Court of the State of New York
DecidedSeptember 14, 2000
StatusPublished
Cited by13 cases

This text of 275 A.D.2d 616 (American Home Assurance Co. v. Gemma Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Home Assurance Co. v. Gemma Construction Co., 275 A.D.2d 616, 713 N.Y.S.2d 48, 2000 N.Y. App. Div. LEXIS 9158 (N.Y. Ct. App. 2000).

Opinion

—Order, Supreme Court, New York County (Barry Cozier, J.), entered April 6, 1999, which denied the motion of plaintiff American Home Assurance Company (American Home) pursuant to CPLR 3212 for partial summary judgment, and pursuant to CPLR 3211 (a) (7) and 3212 to dismiss the counterclaims asserted against it, unanimously reversed, on the law, with costs, plaintiffs motion granted and the matter remanded for further proceedings, including the calculation of interest.

American Home commenced this action for breach of indemnity agreements by Gemma Construction Company, Inc. (Gemma), IVS Construction Company (IVS), and various individuals affiliated with these companies. American Home had agreed to act as surety for Gemma on a number of public projects, some of which were connected with the School Construction Authority, including the Margaretville sewage treatment plant, the P.S. 171-Early Childhood Center 2 project, the Liberty High School project, the P.S. 721/Hewlitt-Woodmere project, the P.S. 54 project, and the P.S. 121/225 project. Defendant TVS was Gemma’s subcontractor on several of these projects and also separately contracted to perform work on the Enid Haupt Pavilion at the New York Botanical Gardens. As surety, American Home issued performance bonds, labor and material payment bonds and discharge of lien bonds, naming Gemma and/or TVS as principal and the project owners and other entities as obligees. In June of 1994 Gemma and its principals (the Carchiettas) executed a General Agreement of Indemnity with American Home. In July of 1994 Gemma, IVS and its sole employee, defendant Sargeant, signed a second agreement containing identical terms and conditions. As relevant, both agreements provide:

“this agreement is made by the Undersigned in favor of the American International Companies for the purpose of indemnifying them from all loss and expense in connection with any Bonds of any Principal defined below, for which any of the American International Companies now is or hereafter becomes Surety.

[617]*617“In consideration of the execution of any such Bonds for Principal and as an inducement to such execution or continuation of suretyship by Surety, the Undersigned, jointly and severally, agree as follows:

“definitions: Where they appear in this agreement, the following terms shall be defined in this paragraph:

“Principal: Any one, combination of, or all of the Undersigned, or any present or future subsidiary or any subsidiary of a subsidiary of the Undersigned, whether alone or in joint venture with others not named herein, and any corporation, partnership or person upon written request of any of the Undersigned.

“Bond: Any and all bonds, undertakings or instruments of guarantee and any renewals or extensions thereof by Surety.

“Surety: American Home Assurance Company * * *.

“indemnity to surety: Undersigned agree to pay to Surety upon demand any premium due and all loss and expense, including attorney fees, incurred by Surety by reason of having executed any Bond. An itemized statement of loss and expense incurred by Surety, sworn to by an officer of Surety, shall be prima facie evidence of the fact and extent of liability of Undersigned to Surety in any claim or suit by Surety against Undersigned. Separate suits may be brought under this agreement as causes of action accrue, and the pendency or termination of any such suit shall not bar any subsequent action by Surety.

“general provisions:

“1. Assent by Surety to changes in any Bond or refusal so to assent shall not release or affect the obligations of Undersigned to Surety.

“2. Surety shall have the right to decline to execute any Bond.”

On December 23, 1996, the New York City Department of Environmental Protection (DEP), the owner of the Margaretville project, notified Gemma that it intended to declare the contractor in default for lack of progress in completing the job. Gemma requested to assign the remaining work to another contractor, but DEP found that Gemma’s proposed assignee lacked the necessary experience. However, the agency suggested that a default could be avoided by Gemma’s transfer of the project to a qualified contractor. Thereafter, Gemma’s president, Fred Carchietta, advised American Home, by letter dated [618]*618January 19, 1997, that it was experiencing cash flow problems and requested funding to complete its construction projects. Consequently, at the suggestion of DEP, plaintiff entered into a written agreement with Gemma, the Carchiettas, the DEP and Parsippany Construction Co., Inc., whereby the contract for the Margaretville project was assigned from Gemma to Parsippany.

On March 26, 1997, Gemma and the Carchiettas entered into another contract with plaintiff under which American Home was to supply Gemma with up to $100,000 in financing to finish the Liberty High School project and $400,000 to complete the P.S. 171 project, both of which were near completion. Because the P.S. 54 and P.S. 121 projects were only in the early stages of construction, Gemma agreed to assign those contracts to other contractors. American Home agreed to provide Gemma with up to $175,000 per month to cover its overhead on the foregoing four projects, along with the P.S. 721 project and another project, the Newburgh project. Plaintiff also offered a financial incentive to the Gemma defendants to limit or reduce their obligation to American Home.1

Gemma agreed to supply American Home with assignments of proceeds on the other bonded projects except for the New-burgh project, which proceeds were to be placed in a separate trust fund account in the name of American Home and used to pay for the labor and materials that had been expended on the various undertakings.

Gemma was unable to complete the Liberty or P.S. 171 projects with the level of financing that it had claimed to be adequate2 and it did not assign the P.S. 54 and P.S. 121/225 proj[619]*619ects by the agreed-upon date of May 15,1997.3 American Home’s suit for breach of the indemnity agreements alleges that it has sustained a loss of $7,129,638.96 on the bonded projects, for which the defendants are jointly and severally liable. In support, American Home submitted copies of the payment drafts from the trust account, lists referencing each of the checks paid on the projects, and monies recovered on each project.

Defendants Gemma and the Carchiettas admitted execution of the agreements and issuance of the bonds, but interposed the following affirmative defenses: (1) failure to state a cause of action; (2) neglecting to annex an itemized and sworn statement of loss and expenses; (3) breach by plaintiff of its duty to mitigate losses and perform its contractual obligations in good faith; (4) estoppel arising out of American Home’s conduct; (5) unmitigable losses less than $3,750,000; (6) gross negligence by plaintiff in paying claims under the bonds; and (7) unreasonable refusal to allow Gemma to substitute another surety on the P.S. 54 and P.S. 121/225 projects, plus one other project, thereby preventing the contractor from substantially limiting its losses on those jobs and ultimately forcing it out of business.

The last affirmative defense raised by Gemma and the Carchiettas was also denominated as a first counterclaim. The second counterclaim stated that because of the alleged improper actions of plaintiff, defendants were unable to meet certain construction loan payments to European American Bank (EAB).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TRAVELERS CASUALTY & SURETY COMPANY v. COSTANZA, NICHOLAS
Appellate Division of the Supreme Court of New York, 2015
Travelers Casualty & Surety Co. of America v. Costanza
125 A.D.3d 1358 (Appellate Division of the Supreme Court of New York, 2015)
International Fidelity Insurance v. Kulka Construction Corp.
100 A.D.3d 967 (Appellate Division of the Supreme Court of New York, 2012)
Adames v. Velasquez
19 Misc. 3d 881 (New York Supreme Court, 2008)
Prestige Decorating & Wallcovering, Inc. v. United States Fire Insurance
49 A.D.3d 406 (Appellate Division of the Supreme Court of New York, 2008)
Kennerson v. LaBARBERA
536 F. Supp. 2d 305 (W.D. New York, 2008)
Lee v. T.F. DeMilo Corp.
29 A.D.3d 867 (Appellate Division of the Supreme Court of New York, 2006)
Superintendent of Insurance v. Spira
289 A.D.2d 173 (Appellate Division of the Supreme Court of New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
275 A.D.2d 616, 713 N.Y.S.2d 48, 2000 N.Y. App. Div. LEXIS 9158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-home-assurance-co-v-gemma-construction-co-nyappdiv-2000.