American-Hawaiian S. S. Co. v. Morse Dry Dock & Repair Co.

169 F. 678, 1909 U.S. Dist. LEXIS 315
CourtDistrict Court, S.D. New York
DecidedMarch 2, 1909
StatusPublished

This text of 169 F. 678 (American-Hawaiian S. S. Co. v. Morse Dry Dock & Repair Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American-Hawaiian S. S. Co. v. Morse Dry Dock & Repair Co., 169 F. 678, 1909 U.S. Dist. LEXIS 315 (S.D.N.Y. 1909).

Opinion

ADAMS, District Judge.

This action was brought by the American-Hawaiian Steamship Company to recover from the Morse Dry Dock & Repair Company and the Merritt & Chapman Derrick & Wrecking Company the value of the time of the stéamship American during'certain repairs made in the latter part of August, 1906, said in the libel to amount t’o $3,921.87. It arose out of a state of affairs fully described in the action of Morse Company v. Merritt Company (D. C.) 157 Fed. 274, where it was determined that the Morse Company was entitled t’o recover its damages, caused by the falling of the low pressure piston of the steamer, from the Merritt Company by reason of its negligence in removing the piston. This action was tried with that action and it was held:

“There will also be a decree in favor of the American Company against the Morse Company, with an order of reference. The latter decree to be satisfied in the first instance by the Merritt Company, but this provision is without prejudice to the right of the American Company to recover from the Morse Company should satisfaction from the Merritt Company fail.”

Upon this decision an interlocutory decree was entered as follows:

“American Hawaiian Steamship Company against Morse Dry Dock & Repair . Company, and the Merritt & Chapman Derrick & Wrecking Company, Brought in by Petition.
The above entitled cause having come on to be heard on the pleadings and proofs adduced by the respective parties, and having been argued and submitted by the proctors for the respective parties, and due deliberation having been had.
Now on motion of Wheeler, Cortis & Haight, proctors for the libellant, it is
Ordered that the libellant herein recover its damages suffered by reason of the matters complained of in the libel, and that it be referred to Herbert Green, Esq., United States Commissioner, to ascertain and report the amount of such damages to the court with all convenient speed.”

[679]*679The claim in the libel was:

“Fifth. By reason of the premises it became necessary to put, in new parts and to repair the injury done to the said vessel as above stated. The respondent herein has made said repairs and has restored the said steamship to her proper condition, but in making the said repairs, the said respondent detained the steamer for a period of five days and one half hours longer than would have been required had the repairs contracted for been performed with due care.
Sixth. The value of the said steamship to the libellant at the time that she was delayed was about $750 per day, and the libellant, therefore, lost the sum of $3,921.87 through its inability to use the said steamship for the said period, and the said sum of $3,921.87 is now due the libellant from the respondent.”

On the reference, it was stated:

“Mr. Haight: I claim the vessel was worth $750 a day, and I claimed in my libel only 5y2 days, but I shall have to ask for an amendment to the ad damnum, which I believe is allowed up to the amendment” (entry) “of the Decree, to increase the number of days as I get my information now.”
* ***********
“Mr. Haight: Yes. I claim, in accordance with the testimony given by
Mr. Blackford, that if the steamer had arrived at the dock on the night of August 29th, when she was expected, her loading would have been completed on the afternoon of September 7th, and that the steamer would have sailed on September Sth, and that the American Hawaiian Steamship Company is entitled to nine days demurrage, at the rate of $530.55 per day, which is the actual net earnings of the steamer on the voyage from New York to Seattle.
Mr. Putnam: I still ask you to give us the days that you claim that we should pay for.
Mr. Haight: I have done so.
Mr. Putnam: I don’t think you have.
Mr. Haight: That she should have sailed on the 8th and did not sail until the 17th; a total of nine days.”

Thereafter the commissioner made a full report. In concluding he said:

“Libellant’s whole case consists of little more than assertions that if the accident had not happened, the other necessary work would have been rushed, some of the work actually done would not have been undertaken, the ship would have sailed leaving other portions uncompleted, the inspection would have been hastened, and the ship would have been loaded and despatched with a speed unusual in libellant’s business. I regard all this as too vague, doubtful and conjectural to found a decree upon. No claim was made for damages for detention while the ship was repairing, and apparently no intimation was given that such a claim might be made. Mr. Mills admits that he did not request Morse to hurry the accident work, or complain that it was delaying the ship. If the Morse Co. had been under a time limit by its original contract, with a per diem penalty clause, it is very doubtful that libellant could have recovered penalties in view of all the additional work it ordered, both originally and from time to time as the repairs proceeded up to the very end, without a suggestion that it would claim damages for delay. If libellant’s silence and orders for additional work would not have operated as a waiver, it would seem that they would at least have been regarded as an implied extension of the time on its part.. Under the facts here, I do not see why the Morse Co. is not in a position at least as good as that, nor do I see why the Merritt & Chapman Co. should occupy a worse position. The liability of the one is no broader than that of the other, although primarily it rests upon the Merritt & Chapman Go. My conclusion is that libellant has failed to prove that the ship was detained by reason of the accident.
To enable the court to dispose of the case finally in the event of the above conclusion not being sustained, it is proper that I should find the rate of damages which libellant would be entitled to recover. Computations were [680]*680submitted purporting to show that the net daily earnings of the ship on her west bound voyage, the one in question, were $530.55 per day, and upon a demand of the respondent, similar computations were presented as to the return of east bound voyage, and these showed net daily earnings of $394.84. The accuracy of these computations has not been questioned. The daily u average for the two voyages was $426.28. Upon the reference it was contended that the last mentioned rate would apply, but the question has not been discussed in respondent’s brief. I 'do not see why the east bound voyage should be considered, any more than the next following, or successive voyages subsequently made. Each voyage was separate and distinct. If the ship was detained, I think that she would be entitled to recover the net earnings which she would have made during the days of detention. I therefore find the rate to be $530.55.”

On the 8th of February, 1909, the libellant duly excepted to the report, pointing out in detail the errors relied upon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Actiesselskabet Albis v. Munson
130 F. 32 (S.D. New York, 1904)
Albis Co. v. Munson
139 F. 234 (Second Circuit, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
169 F. 678, 1909 U.S. Dist. LEXIS 315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-hawaiian-s-s-co-v-morse-dry-dock-repair-co-nysd-1909.