American & Foreign Insurance v. Bolt

106 F.3d 155, 1997 WL 57361
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 13, 1997
DocketNo. 95-2273
StatusPublished
Cited by1 cases

This text of 106 F.3d 155 (American & Foreign Insurance v. Bolt) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American & Foreign Insurance v. Bolt, 106 F.3d 155, 1997 WL 57361 (6th Cir. 1997).

Opinions

KEITH, J., delivered the opinion of the court. MERRITT, J. (p. 161), delivered a separate concurring opinion. SUHRHEINRICH, J. (pp. 161-62), delivered a separate dissenting opinion.

KEITH, Circuit Judge.

Plaintiffs appeal from a decision of the district court which granted judgment as a matter of law in favor of the defendant on a negligence claim. For the reasons stated below, we REVERSE and order that the jury’s verdict on that issue be reinstated.

BACKGROUND

This case is an action for damages based on theories of breach of contract, breach of implied warranty of good workmanship and negligence arising from the collapse of a warehouse roof under a large accumulation of snow and ice. In 1988, ALTL, Inc., plaintiff’s subrogor, elected to build additional warehouse space by placing a pre-engineered metal building adjacent to an existing, shorter building. It is undisputed that the first set of plans drawn up for the project failed to note that the disparity in height created a potential “Canadian snow load” problem. The term “Canadian snow load” refers to the fact that the higher roofline of the new budding would result in a heavier load of snow and ice accumulating on the lower roof, especially at the joint between the buildings. There is some dispute about which of the consultants whom ALTL employed brought this issue to the attention of The Architectural Group (“TAG”), the firm drawing up the plans, but regardless, a note was added to the plans indicating that this problem required that the lower roof be strengthened. The notation reads: “[rjeinforce existing roof in this area w/additional purlins1 between existing to support extra snow load.” Joint Appendix (“Jt.App.”) at 224. .

These plans, with the snow load notation, were sent to William Bolt (“Bolt”), the defendant-appellee, who bid on the project and contracted to construct the building. The parties dispute whether further instructions on the roof strengthening project were ever issued to Bolt. Bolt claims that he requested and received further oral instructions about the installation of the purlins from TAG, but TAG denies that such instructions were given. Regardless, Bolt proceeded according to the oral instructions that he claims to have received, while admitting that he knew that these instructions dictated an improper manner of installing the additional purlins. William Bolt, Trial Transcript (“Trial Tr.”) at 135, 152, Vol. II, 8/8/95. The new purlins were placed between the original purlins and bolted to the existing frame of the building utilizing a “gusset plate”, rather than being bolted to the roof deck as the original purlins had been. Yet, despite Bolt’s statement that he improperly installed the additional pur-[157]*157lins, Robert Johnson, plaintiffs expert and the person who made the notation on the plans regarding the additional support necessary for the lower roof, acknowledged at trial that the manner in which Bolt affixed the purlins complied with his snow load notation. He stated that “[i]n a general sense, that’s what you would have expected them to do.” Robert Johnson, Trial Tr. at 75, Vol. Ill, 8/10/95.

In early 1994, inclement weather resulted in a large accumulation of snow/iee/slush on the roof of the lower building, culminating in its collapse. The collapse resulted in property damage in the amount of $210,980.89. American and Foreign Insurance Co. (“American”) indemnified ALTL for losses relating to the roof collapse pursuant to ALTL’s insurance policy. American then commenced the instant suit against Bolt in the United States District Court for the Western District of Michigan, Southern Division on May 26, 1994 seeking to recover the amount by which it had indemnified ALTL.

At the close of American’s case, Bolt moved for a directed verdict. The court took the motion under advisement and the trial continued until the jury rendered a verdict. The jury found that Bolt had breached neither the contract nor the implied warranty of good workmanship. However, the jury did find that Bolt had been negligent, and that his negligence was the proximate cause of the roof collapse. Following the jury decision, Bolt renewed his earlier motion for a directed verdict, which the district court treated as a motion for judgment as a matter of law pursuant to Fed.R.Civ.P. 50(b). On October 19, 1995, the district court2 entered a judgment for Bolt on the negligence claim holding that no cause of action for negligence lay against him. American now appeals this decision and asserts that the district court’s decision was erroneous.

DISCUSSION

- The Magistrate’s decision to grant judgment notwithstanding the verdict (“JNOV”)3 was predicated on two independent theories. However, this Court finds nothing in the opinion below indicating which ground was dispositive, and further finds that neither theory was sufficient to support the district court’s decision to grant JNOV.

A .Standard of Review

A circuit court reviewing a district court’s decision to grant judgment as a matter of law must utilize .the same standard applied by the district court, i.e., the circuit court must conduct a de novo review. Monette v. AM-7-7 Baking Co., 929 F.2d 276, 280 (6th Cir.1991). The standard for granting JNOV requires a finding that “viewing the admissible evidence most favorable to the party opposing the motion, a reasonable trier of fact could draw only one conclusion.” Hill v. Spiegel, Inc., 708 F.2d 233, 237 (6th Cir.1983). Another formulation of this standard states that sufficient evidence for submission to the jury will be found “unless, when viewed in the light of those inferences most favorable to the non-movant, there is either a complete absence of proof on-the issues or no controverted issue of fact upon which a reasonable person could differ.” Monette, 929 F.2d at 280.

B. Adoption of Illinois Law

One basis of the Magistrate’s decision to grant JNOV was the decision of an Illinois appellate court in Georgetown Township High School v. Hardy, 38 Ill.App.3d 722, 725, 349 N.E.2d 88, 91 (1976). The Magistrate erred in adopting Illinois law as dispositive precedent on the negligence issue. The Georgetown Township decision held that a contractor cannot be held liable for negli[158]*158gence if he fulfilled his duty in completing the work as specified by the plans or designs given to him. The Magistrate concluded, without explanation, that a Michigan court would adopt this rule. However, a review of Michigan law on contractor negligence demonstrates that Michigan law affords American a cause of action for negligence against Bolt.

This Court has laid out the analysis a judge must perform before adopting a standard derived from the caselaw of another jurisdiction:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American and Foreign Insurance Company v. Bolt
106 F.3d 155 (Sixth Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
106 F.3d 155, 1997 WL 57361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-foreign-insurance-v-bolt-ca6-1997.