American Federation of Government Employees, Local 2119 v. Rumsfeld

262 F.3d 649
CourtCourt of Appeals for the Seventh Circuit
DecidedAugust 21, 2001
Docket00-3512
StatusPublished
Cited by1 cases

This text of 262 F.3d 649 (American Federation of Government Employees, Local 2119 v. Rumsfeld) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Federation of Government Employees, Local 2119 v. Rumsfeld, 262 F.3d 649 (7th Cir. 2001).

Opinion

RIPPLE, Circuit Judge.

The individual plaintiffs in this case are present or former civilian employees of the Department of the Army employed at the Rock Island Arsenal (“Rock Island”) in Rock Island, Illinois. They, along with their labor union, American Federation of Government Employees, Local 2119, brought this action against the federal defendants, 1 who are officials and officers of the United States Government. The plaintiffs contend that the Army violated the provisions of the Arsenal Act, 10 U.S.C. § 4532, with regard to two defense programs: (1) the production of tank gun mounts for the upgraded M1A2 Abrams tank and (2) the development of the Lightweight 155mm (“LW155”) Towed Howit *652 zer. The plaintiffs allege that the Army violated the Act by allowing these items to be produced by private contractors without first undertaking a cost analysis, required by the Act (“Arsenal Act cost analysis”), to demonstrate that production of those items could not instead be performed at a government-owned facility on an economical basis. The district court granted summary judgment to the defendants. For the reasons set forth in the following opinion, we affirm the judgment of the district court.

I

BACKGROUND

A. Facts

1.

Rock Island is a government-owned weapons manufacturing facility, one of only two remaining manufacturing arsenals operated by the Army today. It has produced a number of different forms of weaponry for many years, including both of the items at issue in this case — gun mounts and howitzers. However, in recent years the number of manufacturing projects performed at Rock Island has declined. As a result, the number of civilian workers employed at Rock Island has been reduced continually, and some employees have been placed involuntarily in lower-graded positions.

Since 1976, the Army has acquired and upgraded the Ml Abrams series of tanks from Chrysler Defense, Inc. and its corporate successor General Dynamics Land Systems (“GDLS”). One component of this tank and its upgraded versions is a gun mount. Prior to 1982, all of the gun mounts for the Abrams tank system were produced at the Detroit Army Tank Plant (“DATP”) by the contractor. 2 In 1982, due to increased demand for the tank, the Army and GDLS amended their contract to provide that one half of the gun mounts needed for the tank would be provided separately to GDLS as government-furnished material, while the other half would continue to be made by GDLS personnel at the DATP (“the DATP gun mounts”). Since that time, the gun mounts produced by the government have been manufactured at Rock Island. The contract for the M1A2 tank upgrade program, at issue in this case, provides that GDLS is responsible for delivering the tank system in its entirety and for determining where it will produce the various components of the system. It also states that the gun mounts needed for the M1A2 upgrade will be produced in the manner described above-half by the government at Rock Island and half by GDLS at the DATP.

In 1995, pursuant to the Defense Base Closure and Realignment Act of 1990, 10 U.S.C. § 2687, a base closure commission recommended to Congress that the DATP be closed. At this time, the Army discussed the possibility of having all gun mount production for the M1A2 upgrade program transferred to a GDLS-owned- and-operated facility. Ultimately, in 1996, the Army and GDLS amended their contract to allow for the transfer of equipment used to produce the DATP gun mounts to a GDLS owned-and-operated facility in Muskegon, Michigan. Production of those gun mounts began at the Muskegon site in March 1997. In effecting this site change, the Army determined that a decision to transfer production on this half of the gun *653 mounts was not subject to an Arsenal Act cost analysis. It took the view that the Act applied only to the manufacture of the “end-item” of a contract and not to the production of each component of that end-item. Because the end-item of the contract for the upgraded M1A2 tank system (the tanks themselves) was being made at a government factory, the Lima Army Tank Plant, the Army determined that a cost analysis was not required. 3

Production of the other half of the gun mounts was not shifted from Rock Island to a GDLS facility. Because those items were acquired by the Army directly from a government-run arsenal as a separate item of supply, the government determined that any decision to remove them from Rock Island would require an Arsenal Act cost analysis. After a cost analysis showed that it would be eighteen percent cheaper to continue to produce these gun mounts at Rock Island, as opposed to at a GDLS facility, the Army did not shift their production.

2.

In December 1994, the Marine Corps and the Army collaborated to begin work on the LW155 Towed Howitzer program. This program was to produce a new design for the LW155 Towed Howitzer to replace the previous model, which had tactical and physical shortcomings. Private contractors had been developing prototypes of a lighter-weight howitzer for a number of years at their own expense. With the LW155 howitzer program, the Marine Corps and the Army hoped to take advantage of the technology being developed by these private contractors in order to save money and time on research and development. As a result, the Army’s Armament Research, Development and Engineering Center announced a market survey to identify a source for the new LW155 howitzers and later issued draft solicitations to obtain comments from industry on future production of the howitzers.

A formal request for proposals to obtain the LW155 howitzer contract was issued in April 1996. It was contemplated that this contract would be awarded after a two-step process. First, prospective offerors would deliver a prototype howitzer for initial screening and technical documentation, with each eligible offeror to receive a fixed-price contract to support further development and testing. Second, the government would hold a “shoot-off’ between all of the offerors’ howitzers; the winner of this shoot-off would receive a contract for the engineering and development phase of the program and, after that phase was successfully completed, a full-scale production contract. 4 This process went forward, *654 and following the shoot-off, the government entered into an engineering and manufacturing contract with Cadillac Gage Textron, Inc. (“Textron”). 5

It was anticipated that a total of 869 howitzers would be produced under the contract. Funding for the howitzer program initially was provided by the Marine Corps, although both services will contribute financially to its budget. The Army is also developing a “Towed Artillery Digital-ization” (“TAD”) system, a location and targeting system that will be included as part of the LW165 howitzer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
262 F.3d 649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-federation-of-government-employees-local-2119-v-rumsfeld-ca7-2001.