American Excavators, LLC. v. RCR Building Corporation

CourtCourt of Appeals of Tennessee
DecidedDecember 4, 2003
DocketM2002-01757-COA-R3-CV
StatusPublished

This text of American Excavators, LLC. v. RCR Building Corporation (American Excavators, LLC. v. RCR Building Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Excavators, LLC. v. RCR Building Corporation, (Tenn. Ct. App. 2003).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE August 5, 2003 Session

AMERICAN EXCAVATORS, LLC v. RCR BUILDING CORPORATION, ET AL.

Appeal from the Chancery Court for Williamson County No. 27213 R.E. Lee Davies, Chancellor

No. M2002-01757-COA-R3-CV - Filed December 4, 2003

American Excavators, LLC (“Plaintiff”) entered into a subcontract agreement with RCR Building Corporation (“Defendant”) which required Plaintiff to perform excavation and utilities work for the Williamson County community services building.1 The subcontract agreement provided for certain excavation work to be done for a lump sum and states that “[a]ny additional undercutting and refilling of areas due to unsuitable soils will be done for a unit price of $12.50 per cubic yard.” Plaintiff claims that while performing the work, it encountered a large amount of unsuitable soil that it removed and replaced. Plaintiff later submitted change orders to Defendant requesting to be paid for the removal of the alleged unsuitable soil. Defendant paid a portion of the change orders, but refused to pay the entire amount. Plaintiff sued for breach of contract. After a bench trial, the Trial Court dismissed Plaintiff’s claims against Defendant. Plaintiff appeals. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded.

D. MICHAEL SWINEY , J., delivered the opinion of the court, in which HOUSTON M. GODDARD , P.J., and HERSCHEL P. FRANKS, J., joined.

Todd E. Panther, Nashville, Tennessee, for the Appellant, American Excavators, LLC.

Gregory L. Cashion and S. Joseph Welborn, Nashville, Tennessee, for the Appellee, RCR Building Corporation.

1 The factual situation of this case is more involved than we discuss in this Opinion. For purposes of simplicity, we discuss only the facts directly relevant to the issues on appeal. OPINION

Background

Defendant contracted with the owner, Williamson County (“County”), to construct the Williamson County community services building (“Project”). Defendant then solicited subcontract bids for portions of the work.

Plaintiff submitted a subcontract bid proposing to install the utilities such as water and sewer and perform site work for the Project. Plaintiff’s contractual responsibilities on the job were to include excavating the site to subgrade, which is the elevation necessary for construction. In order to reach subgrade, the topsoil would be stripped and then portions of land with a natural grade above subgrade level would be removed. This process is known as cutting. The portions of the property below subgrade level would need to be filled appropriately. If the soils below subgrade were unsuitable to build upon, those areas would need to be undercut and filled with suitable soil. Basically, unsuitable soil is soil that is not sufficiently compactable.

In preparing Plaintiff’s bid, Harley Ezell, Plaintiff’s estimator and project manager, referred to a soils report prepared for the County by a geotechnical engineer, Goodrich Testing & Engineering, Inc. (“GT&E”). The soils report showed that the material in the cut section would be suitable for use as fill. This meant that Plaintiff could move the material from the cut area to the fill area and less material would need to be imported onto the site for fill. The soils report indicated that there were two areas, the garden area and the gymnasium area, with potentially adverse soil conditions. However, the report indicated that the remainder of the material on site was suitable for building. The contract between Defendant and the County states that the soils report was provided for informational purposes only. Plaintiff prepared its bid estimating that approximately six inches of topsoil would be stripped from the site. The county provided fill at no cost for the Project.

Plaintiff’s bid was accepted and Plaintiff and Defendant entered into a subcontract agreement. The subcontract agreement between Plaintiff and Defendant provides that “[a]ny additional undercutting and refilling of areas due to unsuitable soils will be done for a unit price of $12.50 per cubic yard.” Plaintiff claims that the $12.50 per yard provision applies to unsuitable material both below subgrade and above subgrade. However, Mr. Ezell admits that neither the county, nor the architect, ever told Mr. Ezell that Plaintiff would be paid for unsuitable materials above subgrade. The subcontract agreement also provides “If there shall be any inconsistency between any provision of the Contract Documents between the OWNER and the CONTRACTOR and this Subcontract Agreement, then this Subcontract Agreement shall govern.”

Once work on the project began, several problems were encountered. The survey did not match the plans and one of the four boundaries appeared to be off. As a result, Plaintiff had to “remove some additional trees, refrigerators, car bumpers and stuff like that. . . .” A problem was also encountered when some concrete pipe with a diameter of 18 or 24 inches was discovered in the ground running through the entire length of the property. Plaintiff had to excavate, remove and

-2- dispose of the pipe and then fill in the area where the pipe had been. Mr. Ezell and Anthony Orange, Defendant’s project superintendent, discussed the pipe and agreed that Plaintiff would be paid extra to remove the pipe and fill that area.

Ricky Tipper acted as Plaintiff’s field superintendent for the Project. Mr. Ezell instructed Mr. Tipper to strip the topsoil on the site. However, Mr. Ezell did not tell Mr. Tipper to strip the topsoil to a specific depth. Rather, he assumed that Mr. Tipper had been in the construction business long enough to know what to do. When Mr. Ezell visited the site several days after the stripping began, he discovered that Mr. Tipper had “taken out approximately two and a half, three and a half feet of dirt,” rather than the six inches provided for in the subcontract agreement. Mr. Ezell stopped his crew from stripping “[b]ecause this was a fill section. Anything that was unsuitable below the six inches was extra compensation. We couldn’t go in and get out because every inch they took out over and above the six inches was material that we had to import back in to replace.”

Mr. Ezell then called it to Mr. Orange’s attention that there was a problem with the soil in the parking lot area. Mr. Ezell dug some test pits and he and Mr. Orange walked the site. The test pits revealed different strata of material, some of which appeared to be unsuitable. The test pits did not appear to be consistent with the original boring logs prepared by GT&E. A representative from GT&E was called out to the site. The GT&E representative stated that the soil thought to be unsuitable was brown silty clay that would be compactable under optimum moisture conditions and suitable for use as fill. Mr. Ezell disagreed, but told Mr. Orange that they would go ahead and leave the soil in if Defendant so instructed. Mr. Ezell claims that Mr. Orange instructed him to remove the soil. Plaintiff then called in their own geotechnical engineer, Southern Consulting (“Southern”), to get an opinion. Southern came out and stated that the soils were not compactable and not suitable for use as fill.

As a result of the disagreement between GT&E and Southern regarding the soil conditions, a third geotechnical engineering firm, PSI, was called to the site and a meeting was held on June 30, 1999, with representatives of Plaintiff, Defendant, the County, and PSI to discuss the condition of the site. It was decided at this meeting that both GT&E and Southern would be dismissed and Defendant would hire PSI to take over the soils testing. Under the subcontract agreement, Plaintiff had been responsible for paying the geotechnical engineer’s fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bogan v. Bogan
60 S.W.3d 721 (Tennessee Supreme Court, 2001)
Southern Constructors, Inc. v. Loudon County Board of Education
58 S.W.3d 706 (Tennessee Supreme Court, 2001)
Seals v. England/Corsair Upholstery Manufacturing Co.
984 S.W.2d 912 (Tennessee Supreme Court, 1999)
Collins v. Howmet Corp.
970 S.W.2d 941 (Tennessee Supreme Court, 1998)
Jaffe v. Bolton
817 S.W.2d 19 (Court of Appeals of Tennessee, 1991)
Waste Conversion Systems, Inc. v. Greenstone Industries, Inc.
33 S.W.3d 779 (Tennessee Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
American Excavators, LLC. v. RCR Building Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-excavators-llc-v-rcr-building-corporation-tennctapp-2003.