American Construction MacHinery & Equipment Corp. v. Mechanised Construction of Pakistan Ltd.

659 F. Supp. 426, 1987 U.S. Dist. LEXIS 2148
CourtDistrict Court, S.D. New York
DecidedMarch 23, 1987
Docket85 Civ. 3765 (JFK)
StatusPublished
Cited by11 cases

This text of 659 F. Supp. 426 (American Construction MacHinery & Equipment Corp. v. Mechanised Construction of Pakistan Ltd.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Construction MacHinery & Equipment Corp. v. Mechanised Construction of Pakistan Ltd., 659 F. Supp. 426, 1987 U.S. Dist. LEXIS 2148 (S.D.N.Y. 1987).

Opinion

KEENAN, District Judge:

Background

Petitioner, American Construction Machinery & Equipment Corporation, Ltd. (“ACME”), brings this instant motion to confirm a foreign arbitration award it obtained against the respondent, Mechanised Construction of Pakistan Ltd. (“MCP”). ACME is a Cayman Islands corporation with a Westchester County office. During the relevant activities, the office was located in Tarrytown. MCP is a wholly-owned enterprise of the Pakistan government.

On January 6,1977, the parties entered a contract that called for ACME to supply MCP with goods and services to be used in MCP’s Iraq construction project. The contract included an arbitration clause which stated,

[a]ny dispute or difference arising between the parties concerning the interpretation of any provision of this agreement or performance or any action taken there-under shall be settled in the first instance directly between the parties and if no such settlement is possible by referring to the International Chamber of Commerce [ICC] at Paris/Geneva for arbitration.

Petition, Exh. A, H 9. The parties entered a Supplementary Agreement dated May 22, 1978, which stated the governing law would be that of Pakistan.

Almost one year later, on May 1, 1979, ACME filed a claim with the ICC. On June 24, 1979, MCP participated in the arbitration proceedings by filing a reply and a counterclaim for $1 million. See Connolly Affidavit, Exh. 1, 2. The ICC Court of Arbitration selected Geneva as the site for the arbitration and Max W. Abrahamson, Q.C., was chosen as the sole arbitrator. Petition, Exh. C, ¶¶ 3, 13. After designating authorized representatives, on March 19, 1980 the parties signed the Terms of Reference for the arbitration. Petition, Exh. C, ¶ 2. One of the issues the parties agreed to have arbitrated was what effect, if any, the Supplementary Agreement would have on the original January 6, 1977 Agreement. Id., Exh. C, ¶ 2(d)(i). A hearing was scheduled for June 1 and 2, 1981. *428 Despite receiving proper notice of the hearing, MCP elected not to attend. Id., Exh. C, MI 14, 15.

By signing the Terms of Reference, MCP had accepted the Arbitrator’s jurisdiction, Geneva as the location of the arbitration, and the use of Geneva’s procedural rules. MCP, however, decided to pursue another strategy. In July, 1980, MCP stated that it viewed the arbitration as invalid under the law of Pakistan. It proceeded to petition a court in Lahore, Pakistan for a declaration invalidating both the arbitration and the arbitration clause. In that action, ACME and Arbitrator Abrahamson were named as defendants. Id., Exh. C, ¶ 6. MCP’s petition, which according to the Arbitrator contained “omissions and positive misstatements,” id., Exh. C, 118, was granted on January 13, 1981. Id., Exh. C, II6.

The Arbitrator reached his decision in this case on May 24, 1982. Id., Exh. C. He found in favor of ACME on its claim, and against MCP on its counterclaim. In addition, he determined that even if Pakistani law were applicable, MCP’s objections were meritless. Id., Exh. C, MI 8-12. New York law was found to govern the January 6, 1977 Agreement, id., Exh. C, ¶ 28, and the Supplementary Agreement was held invalid. Id., Exh. C, MI 20-22. ACME timely filed a petition in this Court on May 17, 1985 to confirm the arbitral award pursuant to the Convention on the Recognition and Enforcement of Foreign Arbitral Awards (“Convention”), which is given the force of United States law at 9 U.S.C. § 201.

In this Court, MCP has previously moved to dismiss the petition to confirm the award on grounds of lack of personal and subject matter jurisdiction and improper venue. The Court rejected these positions, and briefs were filed on the motion to confirm the arbitration award. For the reasons set forth below, the Court confirms the award which directed MCP to pay ACME, (a) $1,402,924.00 including interest up to December 21, 1981; (b) interest at the rate of 17% on that sum from December 22, 1981 until the date of payment; (c) arbitration costs of $45,057.57; and (d) ACME’s legal costs calculated at $87,500.00. Id., Exh. C, If 31.

DISCUSSION

On a motion to confirm an arbitral award entered pursuant to the Convention, a federal court “shall confirm the award unless it finds one of the grounds for refusal or deferral of recognition or enforcement of the award specified in the said Convention.” 9 U.S.C. § 207. Respondent raises several of the defenses set forth in Article V of the Convention. First, it is asserted that the arbitration agreement “is not valid under the law to which the parties have subjected it.” See 9 U.S.C. § 201, note, Article V, 1(a). Second, respondent argues that the award contains decisions on matters beyond the scope of the arbitration agreement. See id., Article V, 1(c). Third, respondent states that “the arbitral authority of the arbitral procedure was not in accordance with the agreement of the parties----” Answer, II18. Finally, respondent claims that the award has been set aside “by a competent authority of the country in which, or under the law of which, that award was made.” See Article V, 1(e). Two defenses not found within Article V(l) are also presented: the arbitration agreement should be vacated as contrary to United States public policy and the award was in “manifest disregard” of the applicable law. The Court rejects each of these defenses.

As a preliminary matter, the Court notes that there is a “general pro-enforcement bias” manifested in the Convention. See Parsons & Whittemore Overseas Co. v. Societe Generate de I’Industrie du Papier (RAKTA), 508 F.2d 969, 973 (2d Cir.1974). The party opposing confirmation of the award bears the burden of proof. La Societe Nationale v. Shaheen Natural Resources Co., Inc., 585 F.Supp. 57, 61 (S.D.N.Y.1983), aff' d, 733 F.2d 260 (2d Cir.), cert. denied, 469 U.S. 883, 105 S.Ct. 251, 83 L.Ed.2d 188 (1984). MCP has failed to meet this burden.

MCP first argues that the award should not be confirmed because it is invalid under the laws of Pakistan. This argu *429 ment is unavailing because it assumes that the laws of Pakistan were designated by the parties to apply to their agreement. While it is true that the Supplementary Agreement contained a choice of law clause selecting Pakistani law, the Arbitrator ruled that the Supplementary Agreement was invalid under both Pakistani and New York law. See Petition, Exh. C, ¶¶ 21-26. Thus, to accept MCP’s Article V(l)(a) defense would require this Court to reverse one of the Arbitrator’s express findings of law. This can only be done if the findings were made in “manifest disregard” of the law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
659 F. Supp. 426, 1987 U.S. Dist. LEXIS 2148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-construction-machinery-equipment-corp-v-mechanised-nysd-1987.