American Bridge Co. v. Providence Place Group Ltd. Partnership

263 F. Supp. 2d 330, 2003 U.S. Dist. LEXIS 8667, 2003 WL 21190991
CourtDistrict Court, D. Rhode Island
DecidedMay 12, 2003
DocketC.A. 02-377S
StatusPublished
Cited by1 cases

This text of 263 F. Supp. 2d 330 (American Bridge Co. v. Providence Place Group Ltd. Partnership) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Bridge Co. v. Providence Place Group Ltd. Partnership, 263 F. Supp. 2d 330, 2003 U.S. Dist. LEXIS 8667, 2003 WL 21190991 (D.R.I. 2003).

Opinion

DECISION AND ORDER

SMITH, District Judge.

Defendant Providence Place Group Limited Partnership (“Defendant” or “PPGLP”) moves to dismiss the Complaint of Plaintiff American Bridge Company (“Plaintiff’ or “ABC”), or in the alternative for summary judgment. Oral argument on the motion was held on March 13, 2003. Having assessed the parties’ arguments and submissions, the Court rules in favor of PPGLP and grants summary judgment to Defendant on all counts of the Complaint.

I. Facts

This case relates to the construction of the Providence Place Mall (“the Project”) between 1997 and 1999. PPGLP is the owner and developer of the mall, and contracted with Morse Diesel International, Inc. (“Morse”) for construction management services on the Project. Morse subcontracted with SMI-Owen Steel Company (“SMI-Owen”) for structural steel fabrication and erection of the building. SMI-Owen in turn subcontracted with ABC for the erection of structural steel.

ABC began work in April 1998. ABC alleges that it worked overtime hours on the Project from August 1998 through January 1999, and submitted its invoices to SMI-Owen. In January 1999, ABC alleges that SMI-Owen informed ABC that SMI-Owen would no longer pay ABC for overtime work on the Project. ABC thereafter informed SMI-Owen that it would no longer work any overtime hours.

In order to resolve this situation, Morse Diesel arranged a meeting between ABC’s representative, Richard Conte, and the mall’s owner and developer, J. Daniel Lu-gosch, III. ABC alleges that at that meeting, Conte and Lugoseh entered into an oral contract by which ABC would continue to work overtime on the Project, and would be paid for such overtime directly by Morse Diesel.

ABC alleges that after it entered into this oral contract, it invoiced overtime to Morse Diesel, but that it was paid only a fraction of what it claims was due for the overtime work. ABC also contends that *332 PPGLP issued “change orders” to Morse Diesel for overtime work done by ABC, but that ABC was never paid for such “change order” work. All in all, ABC claims that it is owed $605,693 for overtime work on the Project for the months of March — August 1999. In addition, ABC claims that it was underpaid by $5,491 for its invoiced overtime work in February 1999. Thus, ABC brings this diversity action against PPGLP, asserting claims for (1) breach of contract; (2) quantum meru-it; and (3) promissory estoppel, each of which seek damages in the amount of $611,184.

During construction of the mall, SMI-Owen sued Morse Diesel and PPGLP in Rhode Island federal district court (the “SMI-Owen Litigation”). On February 25, 2000, while that litigation was pending, ABC, through its attorney, submitted its claim against SMI-Owen in a letter addressed to the lawyers for SMI-Owen. Consolidated Appendix of Defendant Providence Place Group Limited Partnership in Connection with Its Motion to Dismiss or, in the Alternative, for Summary Judgment (“Def.App.”), Ex. C. The letter sets forth that it is a “Communication Provided Pursuant to Fed.R.Evid. 408,” and that it “is inadmissible in any judicial or arbitration proceeding.” It also states, “I have enclosed information related to the calculation of [ABC’s] claim against SMI-Owen.” Appended to the letter is a spreadsheet indicating the unpaid overtime charges for the months of February — August 1999. The amount claimed by ABC against SMI-Owen in the spreadsheet for unpaid overtime work is $611,184, the same figure that ABC demands in this case.

After ABC stated its “preliminary” claim against SMI-Owen (totaling $8,992,360), SMI-Owen merged the entire ABC claim, including the $611,184, into the SMI-Owen Litigation, by amending its Complaint against Morse Diesel and PPGLP to reflect additional allegations and an increased damages figure. Moreover, SMI-Owen attached ABC’s demand letter to the Amended Complaint in the SMI-Owen Litigation.

The SMI-Owen Litigation settled, see Def.App., Ex. B, and on July 26, 2000, SMI-Owen signed a release, on behalf of itself and its agents, setting forth SMI-Owen’s obligation to indemnify PPGLP against any claims asserted against PPGLP in the SMI-Owen Litigation. See DefiApp., Ex. A.

On March 15, 2001, ABC entered into a settlement agreement with SMI-Owen, wherein ABC specifically released PPGLP “with respect to any claim previously asserted or which could have been asserted against SMI-Owen” that relates to the Project. DefiApp., Ex. F.

Defendant claims that ABC now reasserts the same overtime claims against PPGLP that it already settled and released with SMI-Owen. Defendant therefore moves to dismiss or for summary judgment based on (1) the doctrine of res judicata or claim preclusion; and (2) the fact that the claims asserted by ABC have been released. Plaintiff disputes that the overtime claims are the same, arguing that ABC should be permitted to bring its overtime claims directly against PPGLP pursuant to the alleged oral contract between Conte and Lugosch.

II. Analysis

1. Standard of Review

The parties request that the Court examine various affidavits and exhibits that do not form part of and were not attached to the Complaint. As authorized by Fed *333 eral Rule of Civil Procedure 12(b), 1 the Court will therefore treat Defendant’s motion as one for summary judgment.

Federal Rule of Civil Procedure 56(c) states that a party shall be entitled to summary judgment

if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.

Fed.R.Civ.P. 56(c). When determining a motion for summary judgment, this Court must review the evidence in the light most favorable to the nonmoving party and must draw all reasonable inferences in the nonmoving party’s favor. Rochester Ford Sales, Inc. v. Ford Motor Co., 287 F.3d 32, 38 (1st Cir.2002); Mesnick v. General Electric Co., 950 F.2d 816, 820 (1st Cir.1991); Griggs-Ryan v. Smith, 904 F.2d 112, 115 (1st Cir.1990).

To oppose the motion successfully, the nonmoving party “may not rest upon mere allegation or denials of his pleading.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 256, 106 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ayoub v. CitiMortgage, Inc.
D. Massachusetts, 2018

Cite This Page — Counsel Stack

Bluebook (online)
263 F. Supp. 2d 330, 2003 U.S. Dist. LEXIS 8667, 2003 WL 21190991, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-bridge-co-v-providence-place-group-ltd-partnership-rid-2003.