American Bridge Co. of New York v. Camden Interstate Ry. Co.

135 F. 323, 68 C.C.A. 131, 1904 U.S. App. LEXIS 4556
CourtCourt of Appeals for the Fourth Circuit
DecidedNovember 15, 1904
DocketNo. 519
StatusPublished
Cited by7 cases

This text of 135 F. 323 (American Bridge Co. of New York v. Camden Interstate Ry. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Bridge Co. of New York v. Camden Interstate Ry. Co., 135 F. 323, 68 C.C.A. 131, 1904 U.S. App. LEXIS 4556 (4th Cir. 1904).

Opinion

GOFF, Circuit Judge.

This writ of error was prosecuted from a judgment rendered by the Circuit Court of the United States for the Southern District of West Virginia in an action of assumpsit. The declaration contains the usual indebitatus assumpsit counts. The case is sufficiently stated by the facts as found by the court below. By stipulation in writing the parties waived a jury, and submitted all matters of law and fact involved in the issues to the court for its decision. The assignments of error relating to the action of the court below concerning the pleadings are without merit, and it will not be profitable to consider them here. In fact, they are not insisted upon by counsel for plaintiff in error. The facts found by the court below are as follows:

I find that the American Bridge Company, plaintiff, is the assignee of the Pittsburgh Bridge Company of a certain contract with the defendant dated May 26, 1900, for the erection of a bridge over Twelve Pole creek on or before August 1, 1900, for the sum of $4,000, and was also the assignee of the American Bridge Company of New Jersey of a certain contract with the defendant dated September 25, 1900, providing for the erection of a steel bridge over the Big Sandy river on or before January 1, 1901, for the sum of $24,500. Both of these contracts were made with the Ohio Valley Electric Railway Company, and said corporation afterwards changed its name to the Camden Interstate Railway Company, the present name of the defendant. I further find that the contract dated September 25, 1900, was signed by “J. N. Camden,” but was made for and on béhalf of the defendant corporation, and no question of authority to make such contract was raised at the trial.
I find from the evidence that the bridges over Twelve Pole creek and Big Sandy river were constructed in accordance with the plans and specifications set forth in the contracts therefor. I further find that the Twelve Pole Bridge was completed on or about March 1, 1901, and the Big Sandy Bridge on or about June 23, 1901, and that the cause of delay was not among those specified in the contract as excusing the contractor from liability for failure to complete said work at the time prescribed in its agreements.
I further find from the evidence that at and before the contract for the Big Sandy Bridge was entered into Mr. Broumbaugh, the agent of the American Bridge Company of New Jersey, assignor of the contract for said bridge to the plaintiff, was advised of the fact that it was the intention of the defendant to connect the Huntington, Ashland and Catlettsburg Street Rail [325]*325ways into a continuous system, and that it was the intention of the defendant to push their work on this construction, and that, in consequence, the contract for the erection of the Big Sandy Bridge would be a time contract But I do not find from the evidence that Mr. Broumbaugh was advised of the fact that the Ironton Street Railway was to be a part of the contemplated connected system.
I find that one-half of the contract price of each bridge, to wit $2,000 on the Twelve Pole Bridge and $12,250 on the Big Sandy Bridge, was paid by the defendant when due, and that the balance upon each contract has not as yet been paid. I further find that the plaintiff did extra work on the Twelve Pole Bridge amounting to $1,175, for which it is entitled to be paid, with interest from November 1, 1900; and that it also furnished piles, etc., to the value of $127.95, to which it is entitled, with interest from August 1, 1901.
I further find that the plaintiff is entitled to recover the balance on the Twelve Pole Bridge, as aforesaid, of $2,000, with interest from March 1, 1901, and the balance on the Big Sandy Bridge of $12,250, with interest from June 23, 1901.
I find from the evidence that the set-off claimed by the defendant in its plea and statement of set-off, which amounts to $644.42, was not authorized to be expended and incurred by plaintiff or its agent, and the same cannot be allowed.
I find from the evidence that the defendant, the Camden Interstate Railway Company, expended for construction upon its lines and plants the following sums:
Construction.
Previous to January 1, 1901.............................. $328,913 51
During January ” 29,169 39
” February ” 46,152 09
” March ” 37,086 05
” April ” 49.273 44
” May ” 44,530 78
—And I further find that by reason of the failure of the plaintiff to complete the Big Sandy Bridge at the time specified in the contract (i. e., January 1, 1901) the defendant was deprived of the use of the aforesaid sums of money, and that they are entitled to recoupment by way of interest at 6 per cent, from the several dates to June 23, 1901, the date of the completion of the said bridge, as per the following statement:
Recoupment by Way of Interest.
Int. on $328,913.51 from Jan. 1 to June 23, 1901............$ 9,483 57
Int. on 29,169.39 from Feb. 1 to June 23, 1901............' 695 18
Int. on 46,152.09 from Mch. 1 to June 23, 1901......... 884 60
Int on 37,086.05 from Apr. 1 to June 23, 1901............ 520 20
Int. on 49,273.44 from May 1 to June 23, 1901............ 443 45
Int. on 44,530.78 from Jun. 1 to June 23, 1901............ 170 68
Total ............................................... $12,197 68
Summary: I therefore find that the plaintiff is entitled to recover of the defendant as follows:
$1,175.00, with interest from Nov. 1, 1900, to June 23, 1901... $ 1,220 62 $2,000 balance due on Twelve Pole Bridge, with interest from
Mar. 1, 1901, to June 23, 1901.......... .■.................. 2,037 33
$12,250, balance due on Big Sandy Bridge as of June 23, 1901.. 12,250 00
Total ................................................. $15,507 95
—And that the defendant is entitled to recoupment to the amount of $12,-197.68, being interest at 6 per cent, upon amounts invested as shown in finding above. I therefore find that the plaintiff is entitled to recover of the defendant the sum of $3,310.27, balance due as of June 23, 1901, which, with interest from said June 23, 1901, to the date of this finding, April 10, 1903, amounts to $3,667.22, and the further sum of $127.95, the value of piles, etc., [326]*326furnished defendants, with interest from August 1, 1901, to the date of this finding, April 10, 1903, amounting to $140.94.
I therefore find that the plaintiff is entitled to recover of the defendant the sum of $3,808.16, with interest thereon from this date, April 10, 1903, until paid, and its costs by it about its suit in this behalf expended, including an attorney’s fee of $10, as allowed by law. An order may go in accordance with this finding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L & S Construction Co. v. Bradbury Homes, Inc.
118 A.2d 681 (Court of Appeals of Maryland, 1955)
Sanford Coal Co. v. Wisconsin Bridge & Iron Co.
293 F. 735 (Seventh Circuit, 1923)
Coal & Iron Ry. Co. v. Reherd
204 F. 859 (Fourth Circuit, 1913)
Friedman v. Murphey
124 P. 654 (Arizona Supreme Court, 1912)
United States v. Davies, Turner & Co.
177 F. 371 (First Circuit, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
135 F. 323, 68 C.C.A. 131, 1904 U.S. App. LEXIS 4556, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-bridge-co-of-new-york-v-camden-interstate-ry-co-ca4-1904.