This text of 15 App. D.C. 397 (American Bonding & Trust Co. v. United States ex. rel. Lincoln) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Bonding & Trust Co. v. United States ex. rel. Lincoln, 15 App. D.C. 397, 1899 U.S. App. LEXIS 3525 (D.C. Cir. 1899).

Opinion

Mr. Justice Morris

delivered the opinion of the Court:

This is an action of debt on a bond given to the United States of America by Henry T. Douglas and George Snow-den Andrews, partners, composing a firm of Douglas & Andrews, with the appellant, the American Bonding and Trust Company of Baltimore City, a corporation of the State of Maryland, as surety, in the penal sum of $30,000, conditioned for the due performance by said firm of all the covenants, conditions and agreements contained in a certain contract entered into by them with the United States, under date of December 16, 1896, for the construction of a wharf and gun emplacements at a place known as Sheridan’s Point, in the State of Virginia; and conditioned, also, as required by the Act of Congress of August 13, 1894, (28 Stat. 278), entitled “An act for the protection of persons furnishing materials and labor for the construction of public works,” that said firm should promptly make full payments to all persons supplying to them labor or materials in the prosecution of the work provided for in said contract. Douglas & Andrews entered into an agreement with S. Dana Lincoln, who was doing business, it seems, under the name and title of the National Mortar Company, under date of March 29, 1897, whereby it was provided that Lincoln should deliver to Douglas & Andrews, in barges alongside the dock at Sheridan’s Point, all the river sand and pebbles required to be used by Douglas & Andrews in their contract with the United States, and that payments should be made therefor by Douglass & Andrews to Lincoln on or about the 15th day of each month, at a certain specified price, to the amount of eighty (80) per centum of the value of the sand and pebbles delivered and accepted in the previous month, and the remaining twenty (20) per centum to be [399]*399paid when all the material contracted for should be delivered and accepted.

It is claimed that Douglas & Andrews violated the contract by failure to pay as stipulated; and thereupon Lincoln refused to proceed to deliver any more materials, and instituted this suit to recover the money due to him for the amount of'material actually delivered, including not only the 80 per centum specifically payable on or about the 15th day of each month, but also the 20 per centum agreed to be retained or l’eserved to the completion of the contract. Lincoln sued on the bond given by Douglas & Andrews to the United States, as he was authorized to do by the Act of Congress, to which reference has been made; and proceeded against the surety without joining the principals in the suit.

In the declaration filed on May 18, 1898, it is alleged that, to the end of November, 1897, Lincoln had furnished and delivered sand and pebbles under the contract to the value of $1,991.06 ; that he had received payments to the amount of $1,314.32 ; that there yet remained due to him on that account $676.74; that he had fully complied with his contract up to the time of alleged default by Douglas & Andrews; that these latter did not pay on or about December 15, 1897, or at any time thereafter, the 80 per centum due for the sand and pebbles delivered and accepted in the previous November, or any other sum whatever; and that Douglas & Andrews have failed and refused to pay the amount so stipulated to be paid, notwithstanding that the plaintiff, Lincoln, has tendered himself ready and willing to go on with the contract. And the declaration is supported by affidavit, and is accompanied by a copy of the contract between Lincoln and the firm of Douglas & Andrews, and also by a copy of the bond, with the appellant as surety, given by the firm of Douglas & Andrews to the United States.

The defendant company demurred to the declaration on [400]*400the ground that a certain requirement of the statute in regard to an affidavit had not been complied with, and also on the ground that the principals had not been joined in the suit; but the dumurrer was overruled, and leave was given to the defendant to plead. The defendant then filed a plea to the effect that Lincoln had not performed the covenants of the contract on his part to be performed; and this plea was supported by an affidavit of its general agent, somewhat vague and indefinite in several of its averments, but of which the substantial part in defense of the action was that the firm of Douglas & Andrews had paid everything that was due and payable up to November 30, 1897; and that, for the materials delivered and accepted in the month of November, they had, on or about the 10th day of December, 1897, submitted a statement to Lincoln, which they requested him to verify, at the same time offering to pay the amount shown by that statement to be due from them, but that Lincoln had never complied with their request. It was also stated in this affidavit that, on February 15, 1898, Douglas & Andrews again called the attention of Lincoln to their previous statement, and notified him that shipments of sand and gravel, to a certain specified amount, would be required beginning with March 10, 1898 ; but that Lincoln thereupon notified Douglas & Andrews that he would make no further shipments either of sand or of gravel, upon which notification, as they say, they had to go into the market and purchase sand and gravel at great expense to go on with their contract with the United States.

’This affidavit was deemed insufficient .by counsel for Lincoln, and motion was made for judgment under the Seventy-third Rule of the Supreme Court of the District of Columbia. This motion was overruled with leave to the defendant to file an additional plea and affidavit. An additional plea and affidavit were accordingly filed. The plea alleged failure of Lincoln to deliver any material after November 30, 1897, and that Douglas & Andrews had to [401]*401pay to one Lord for the sand and gravel which they were required to procure $716.58 more than they would have been compelled to pay to Lincoln under their contract with him. The affidavit, which showed that work on the contract between the contractors and the United States was compelled to be suspended on account of the weather from December 1, 1897, to March of 1898, merely elaborated the plea and the refusal of Lincoln to proceed with his contract in March of 1898.

There were now two pleas on the record for this defendant. The plaintiff demurred to both on the ground that, in consequence of the failure of Douglas & Andrews to make payments as stipulated, Lincoln was under no obligation to go on with the contract. This demurrer the court sustained, but again gave the defendant leave to plead, and the time to plead was extended twice. The defendant then filed another or further plea, which was no more than a reiteration of the second plea, with a notice of recoupment attached to it, and without affidavit.

The plaintiff thereupon again moved for judgment under the Seventy-third Rule; and the court allowed the motion, and entered judgment for $30,000, the penal sum of the bond, but to be released on the payment of $676.74, the amount of the claim in the declaration.

From this judgment the defendant company has appealed. We have been thus careful to state at some length the condition of the pleadings in this case, as disclosed by the record before us, for the reason that they show that there is practically nothing before us for review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips & Colby Construction Co. v. Seymour
91 U.S. 646 (Supreme Court, 1876)

Cite This Page — Counsel Stack

Bluebook (online)
15 App. D.C. 397, 1899 U.S. App. LEXIS 3525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-bonding-trust-co-v-united-states-ex-rel-lincoln-cadc-1899.