Ameren Illinois Co v. Illinois Commerce Commission

CourtAppellate Court of Illinois
DecidedMay 26, 2026
Docket5-24-0164
StatusUnpublished

This text of Ameren Illinois Co v. Illinois Commerce Commission (Ameren Illinois Co v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ameren Illinois Co v. Illinois Commerce Commission, (Ill. Ct. App. 2026).

Opinion

2026 IL App (5th) 240164-U NOTICE NOTICE Decision filed 05/26/26. This order was filed The text of this decision NOS. 5-24-0164, 5-24-0165, 5-24-0853, 5-24-0968, 5-25-0172 cons. under Supreme Court may be changed or Rule 23 and is not corrected prior to the IN THE precedent except in the filing of a Petition for limited circumstances Rehearing or the allowed under Rule disposition of the same. APPELLATE COURT OF ILLINOIS 23(e)(1).

FIFTH DISTRICT ______________________________________________________________________________

AMEREN ILLINOIS COMPANY d/b/a Ameren Illinois, ) Appeal from the ) Illinois Commerce Petitioner-Appellant, ) Commission ) v. ) ICC Docket Nos. 22-0487, ) 23-0082, and 24-0238 (cons.) ILLINOIS COMMERCE COMMISSION; THE ) CITIZENS UTILITY BOARD; ENVIRONMENTAL ) LAW & POLICY CENTER; VOTE SOLAR; SUNRUN, ) INC.; SOLAR ENERGY INDUSTRIES ASSOCIATION; ) COALITION FOR COMMUNITY SOLAR ACCESS; ) ILLINOIS SOLAR ENERGY ASSOCIATION; UNION ) OF CONCERNED SCIENTISTS; ILLINOIS ) INDUSTRIAL ENERGY CONSUMERS; NATURAL ) RESOURCES DEFENSE COUNSEL; ) ENVIRONMENTAL DEFENSE FUND; WALMART; ) INC.; FEDERAL EXECUTIVE AGENCIES; UNITED ) CONGREGATIONS OF METRO-EAST; AARP; ) PRAIRIE RIVERS NETWORK; ILLINOIS POWER ) AGENCY; THE PEOPLE OF THE STATE OF ) ILLINOIS AND COMMUNITY ORGANIZING AND ) FAMILY ISSUES, ) ) Respondents-Appellees. ) ______________________________________________________________________________

JUSTICE VAUGHAN delivered the judgment of the court. Justices Barberis and Boie concurred in the judgment.

ORDER

¶1 Held: The Illinois Commerce Commission’s orders reducing Ameren’s storm hardening investment in its refiled Grid Plan, disallowing Ameren’s request to include the Other Post-Employment Benefits asset in its rate base and setting Ameren’s rate on equity are affirmed where substantial evidence supported the orders.

1 ¶2 Petitioner, Ameren Illinois Company d/b/a Ameren Illinois (Ameren) seeks review of the

Illinois Commerce Commission’s (Commission) decisions in three consolidated Commission

appeals. Ameren contends that the Commission’s orders that reduced Ameren’s proposed budget

for subtransmission line hardening program, rejected Ameren’s request to include the other post-

employment benefits asset (OPEB) in its rate base, and setting Ameren’s rate on equity were

erroneous. For the following reasons, we affirm.

¶3 I. BACKGROUND

¶4 On July 21, 2022, the Commission, pursuant to section 16-108.18 of the Public Utilities

Act (Utilities Act), also known as the Climate & Equitable Jobs Act (Jobs Act) (220 ILCS 5/16-

108.18 (West 2020) (amended by Pub. Act 102-662 (eff. Sept. 15, 2021)), issued an order that

required each electric company serving more than 500,000 retail customers in Illinois to formulate

and submit a Multi-Year Integrated Grid Plan (Grid Plan) for Commission approval as required by

section 16-105.17(f) of the Utilities Act (220 ILCS 5/16-105.17(f) (West 2020)). The Commission

order, citing section 16-105.17(f)(2) of the Utilities Act (id. § 16-105.17(f)(2)), set forth numerous

requirements for the Grid Plan which was due no later than January 20, 2023.

¶5 Pursuant to the Jobs Act, the Commission was granted authority to modify a utility’s Grid

Plan to comply with the objectives set forth in section 16-105.17(f) of the Utilities Act. See Id.

§ 16-105.17(f)(5)(B). The Commission could approve, or modify and approve, a Grid Plan only

after finding that the Grid Plan reasonably incorporated input from the parties, was reasonable,

and in compliance with the section 16-105.17 objectives and requirements. Id. If those findings

could not be made, the Commission was required to reject the Grid Plan. Id. The Commission was

required to either approve (with or without modification) or reject the Grid Plan by December 15,

2 2023. Id. If the Grid Plan was rejected, the utility was required to refile its Grid Plan within three

months of the rejection. Id.

¶6 Ameren filed its Grid Plan and its Multi-Year Rate Plan (Rate Plan) (see Id. § 16-

108.18(d)) on January 20, 2023. In support of its Grid and Rate Plans, Ameren submitted numerous

pages of testimony and exhibits. Responsive, rebuttal, and sur-rebuttal evidence was submitted. 1

Evidentiary hearings were held before Administrative Law Judges Jessica Cardoni, Daniel Coultas

and Leslie Haynes (collectively the ALJs) on August 8, 2023, and again on August 24, 2023.

¶7 A. Ameren’s initial Grid and Rate Plans before the ALJs.

¶8 1. Ameren’s “storm hardening” project

¶9 Ameren’s initial Grid Plan included a subtransmission line hardening program known as

storm hardening in the corrective maintenance portion of its Grid Plan and requested $40.3 million

in its four-year budget for that program. Riley Adams, a senior manager of electric programs for

Ameren, provided testimony. Adams testified that his primary responsibility in that position was

to manage Ameren’s circuit and pole inspection programs, which inspected approximately 177,000

poles and 260 circuits annually. He explained that the $40.3 million budget would allow Ameren

to install a composite pole every fifth pole to support weaker and older poles. The purpose of the

composite pole installation was to prevent cascading collapses of subtransmission lines due to

significant high wind weather events like derechos and tornados, or extreme winter events that

resulted in ice loading on the lines.

1 Throughout these proceedings numerous entities entered their appearances. However, only those entities with relevant evidence or argument to the issues on appeal are addressed. Those entities included: (1) Commission Staff (Staff); the Attorney General (State); (3) Illinois Industrial Consumer, Federal Executive Agencies, Citizens Utility Board, United Congregations of Metro-East and Prairie Rivers Network (collectively known as IFCUP); and (4) Walmart. 3 ¶ 10 Adams explained that many of the previous poles placed by Central Illinois Public Service

Company (CIPS) were old and lower grade than composite poles. He further explained that

installing a composite pole every fifth pole would provide greater resiliency and reliability,

improve public and worker safety, and would be more cost efficient than fixing the problem after

the lines collapsed. He stated that an engineering review identified and ranked 66 of the CIPS lines

that had potential for cascading. Twenty of those lines were previously retrofitted and resulted in

only 4 poles, as opposed to 20 or 30 poles, cascading during a storm event. In addition to the

remaining 46 CIPS lines, additional lines outside the old CIPS area were identified as “potentially

benefiting from hardening.” Adams testified that if the project was rejected, Ameren’s customers

would “continue to experience cascading failures on un-hardened, older, subtransmission lines

during storms” that led to lengthy resulting outages and additional resources to restore. The $40.3

million plan would harden 153.5 miles of poles in 2024, 146.5 miles of poles in 2025, 146.1 miles

of poles in 2026, and 122 miles of poles in 2027. A list of the proposed areas, broken down by

region, was attached to Adams’s testimony. The projects were ranked with a reliability score that

had the higher number “being more urgent”, the number of customers impacted for each project,

the number of poles needed, the estimated cost, the general age of the line, the project scope and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Willcox v. Consolidated Gas Co.
212 U.S. 19 (Supreme Court, 1909)
Federal Power Commission v. Hope Natural Gas Co.
320 U.S. 591 (Supreme Court, 1944)
Lange v. Freund
855 N.E.2d 162 (Appellate Court of Illinois, 2006)
Amax Zinc Co. v. Illinois Commerce Commission
463 N.E.2d 902 (Appellate Court of Illinois, 1984)
Village of Roselle v. Commonwealth Edison Co.
859 N.E.2d 1 (Appellate Court of Illinois, 2006)
Citizens Utilities Co. v. Illinois Commerce Commission
529 N.E.2d 510 (Illinois Supreme Court, 1988)
Commonwealth Edison Co. v. Illinois Commerce Commission
924 N.E.2d 1065 (Appellate Court of Illinois, 2009)
Continental Mobile Telephone Company, Inc. v. Illinois Commerce Commission
645 N.E.2d 516 (Appellate Court of Illinois, 1994)
Matthews v. Avalon Petroleum Co.
871 N.E.2d 859 (Appellate Court of Illinois, 2007)
Village of Apple River v. Illinois Commerce Commission
165 N.E.2d 329 (Illinois Supreme Court, 1960)
City of Alton v. Commerce Commission
165 N.E.2d 513 (Illinois Supreme Court, 1960)
United Cities Gas Co. v. Illinois Commerce Commission
643 N.E.2d 719 (Illinois Supreme Court, 1994)
Mabry v. Boler
2012 IL App (1st) 111464 (Appellate Court of Illinois, 2012)
City of Elgin v. Illinois Commerce Comm'n
2016 IL App (2d) 150047 (Appellate Court of Illinois, 2016)
Iowa-Illinois Gas & Electric Co. v. Illinois Commerce Commission
167 N.E.2d 414 (Illinois Supreme Court, 1960)
Illinois Consolidated Telephone Co. v. Illinois Commerce Commission
447 N.E.2d 295 (Illinois Supreme Court, 1983)
Citizens Utility Board v. Illinois Commerce Commission
651 N.E.2d 1089 (Illinois Supreme Court, 1995)
People ex rel. Raoul v. Illinois Commerce Comm'n
2021 IL App (1st) 200366 (Appellate Court of Illinois, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Ameren Illinois Co v. Illinois Commerce Commission, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ameren-illinois-co-v-illinois-commerce-commission-illappct-2026.