AMEC Earth & Environmental, Inc. v. SolSource Energy Solutions, LLC

854 F. Supp. 2d 1014, 2012 WL 592859, 2012 U.S. Dist. LEXIS 22714
CourtDistrict Court, D. Colorado
DecidedFebruary 22, 2012
DocketCivil Action No. 11-cv-00135-PAB-KLM
StatusPublished

This text of 854 F. Supp. 2d 1014 (AMEC Earth & Environmental, Inc. v. SolSource Energy Solutions, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AMEC Earth & Environmental, Inc. v. SolSource Energy Solutions, LLC, 854 F. Supp. 2d 1014, 2012 WL 592859, 2012 U.S. Dist. LEXIS 22714 (D. Colo. 2012).

Opinion

ORDER

PHILIP A. BRIMMER, District Judge.

This matter is before the Court on Defendants’ Amended Motion to Dismiss AMEC’s Second, Fourth, and Fifth Claims for Relief [Docket No. 33] filed by defendants SolSource Energy Solutions, LLC1 and Jeffrey R. Scott. Because default has entered against defendant SolSource, the Court will consider the motion to dismiss in regard to defendant Scott only.2 The motion is fully briefed and ripe for disposition.

I. BACKGROUND

On June 26, 2009, AMEC Earth and Environmental, Inc. contracted with the Department of the Air Force, Air Education and Training Command (the “Air Force”) to build a 1.0 Mega-Watt Solar Photovoltaic array (the “PV array”).3 Docket No. 1 at 3, ¶ 10. On July 21, 2009, AMEC and SolSource entered into a subcontract under which SolSource agreed to provide all labor, materials, equipment and supervision necessary to build the PV array. Id. at ¶ 12. SolSource contracted to build the PV array in accordance with Air Force standards and to correct or replace any deficient work after the approval of the final payment, but prior to the expiration of one year after acceptance. See id. at 3-4, ¶¶ 13-14. The subcontract also contained an express warranty and a defective work clause wherein SolSource would: (1) perform all work according to accepted industry practice reflecting SolSource’s best professional knowledge and judgment; (2) incur all expenses to re-perform or procure work AMEC deemed inadequate or insufficient; (3) pay all costs of any correction needed, including compensation for additional professional services; and (4) pay for all direct and indirect costs of removing and replacing defective or rejected work. Docket No. 13-1 at 10-11.

According to AMEC, SolSource failed to adhere to the terms of the subcontract and materially breached the agreement when it: (1) assembled the foundation of the PV array with structural deficiencies; (2) completed only 60% of the PV array’s electrical system; (3) installed defective wiring resulting in an electrical fire; and (4) failed to compensate lower tier subcontractors despite receiving timely invoice payments. Id. at 15-18.

A. Foundation Deficiencies

AMEC alleges that SolSource agreed to construct a PV array able to withstand 120 [1016]*1016mile per hour winds and support a snow load of 40 pounds per square foot. Docket No. 1 at 4, ¶ 16. Additionally, SolSource promised to use vertical and battered piers to construct the foundation supports. Id. at ¶ 15. The subcontract also permitted SolSource to issue subcontracts with AMEC’s prior written consent. Docket No. 13-1 at 3, ¶ 12.

To complete construction of the foundation, SolSource entered into subcontract agreements with D & B Drilling, Inc.,4 Advanced Piping and Fabrication, LLC (“Advanced Piping”), and AZ-Tec Erectors, Inc. (“AZ-Tec”). Docket No. 1 at 5, ¶¶ 18-24. Once construction began, AMEC notified SolSource that the PV array showed signs of significant structural problems. Id. at 6, ¶ 26. Specifically, the PV array exhibited excessive movement and appeared out of alignment. Id. at ¶ 28. On May 24, 2010, AMEC issued a corrective action request demanding that SolSource remedy the problems associated with the PV array. Id. at ¶ 27. In June 2010, AMEC and the Air Force also requested information regarding the PV array’s engineering design and met with SolSource to develop a solution for the structural problems. Id. at ¶ 30.

AMEC asserts that between June 3, 2010 and August 17, 2010 it gave Sol-Source several requests to cure, yet Sol-Source did not repair the identified structural deficiencies. Id. at 6-7, ¶¶ 31-34. AMEC further alleges that, despite holding negotiations between the parties on September 2, 2010, the two sides were unable to reach an agreement. Id. at ¶ 38. On September 20, 2010, AMEC terminated the subcontract with SolSource, alleging a material breach of the contract since the PV array was unable to withstand strong winds because of structural deficiencies, SolSource used only vertical piers and not battered piers to construct the foundation, and SolSource subcontracted with D & B Drilling without AMEC’s input or approval. Id. at ¶ 39. AMEC asserts that, following the termination of SolSouree’s subcontract, it incurred approximately $75,000 in additional costs to correct the PV array’s structural and engineering deficiencies. Id. at ¶ 40.

B. Electrical Systems Installation

To complete the electrical systems for the PV array, SolSource contracted with Aerotek Energy Services, Inc., Intermountain Electric, Inc., CED, Inc., and Advanced Energy Industries, Inc. Docket No. 1 at 8, ¶ 42. In June 2010, AMEC paid an invoice from SolSource for approximately $292,000 for the installation of the electrical systems. Id. at ¶ 43. According to AMEC, as of September 20, 2010, Sol-Source had completed only 60% of the work required for the installation of the electrical systems. Id. at ¶ 44.

AMEC alleges that after the termination of the subcontract on September 20, 2010, it incurred $250,000 in additional costs to complete the installation of electrical components. Id. at ¶ 45. Additionally, AMEC paid $200,000 to repair newly discovered deficiencies with the electrical system, id. at ¶¶ 46-48, and incurred $75,000 in costs to repair damage from a fire started because SolSource allegedly installed electrical components improperly. Id. at 10, ¶ 52.

C. Lower Tier Subcontractors

On August 24, 2010, AMEC received a notice pursuant to the Miller Act, 40 [1017]*1017U.S.C. § 3133, from D & B Drilling demanding payment in the amount of $267,553.87. Docket No. 1 at 11, ¶ 57. D & B Drilling sought payment from AMEC for work performed on the PV array because SolSource failed to fully compensate D & B Drilling for its labor and materials. Id. After receipt of D & B Drilling’s notice, AMEC sent SolSource several cure notices directing SolSource to pay its lower tier subcontractors. Id. at ¶¶ 58-59. AMEC contends that SolSource failed to pay D & B Drilling approximately $167,553.87, Advanced Piping $86,314.82, and AZ-Tec $20,000. Id. at 11-12, ¶¶ 62-64.

D. Defendants’ Motion to Dismiss

On January 20, 2011, AMEC filed a complaint [Docket No. 1] bringing claims against defendants SolSource and Mr. Scott for: (1) breach of contract; (2) negligence; (3) indemnification; (4) breach of fiduciary duty because of non-compliance with the Colorado Mechanics’ Lien Trust Fund Statute, Colo.Rev.Stat. § 38-22-127; and (5) civil theft. Docket No. 1 at 14-18. AMEC alleges that Mr. Scott, as president of SolSource, is personally liable for damages under claims four and five because of his non-compliance with the Trust Fund Statute. Id.

On April 14, 2011, defendants filed a motion to dismiss [Docket No. 33]. Mr. Scott requests that the Court dismiss AMEC’s fourth and fifth claims for relief and dismiss him as an individual defendant because AMEC lacks standing to sue under the Trust Fund Statute. Docket No. 33 at 5. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erickson v. Pardus
551 U.S. 89 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
J.M. Mangum v. Siegfried
5 F. App'x 856 (Tenth Circuit, 2001)
Moffett v. Halliburton Energy Services, Inc.
291 F.3d 1227 (Tenth Circuit, 2002)
Dubbs Ex Rel. Dubbs v. Head Start, Inc.
336 F.3d 1194 (Tenth Circuit, 2003)
Maestas v. State of Colorado
351 F.3d 1001 (Tenth Circuit, 2003)
Alvarado v. KOB-TV, L.L.C.
493 F.3d 1210 (Tenth Circuit, 2007)
Port City Properties v. Union Pacific Railroad
518 F.3d 1186 (Tenth Circuit, 2008)
Bryson v. Gonzales
534 F.3d 1282 (Tenth Circuit, 2008)
Flooring Design Associates, Inc. v. Novick
923 P.2d 216 (Colorado Court of Appeals, 1995)
Syfrett v. Pullen
209 P.3d 1167 (Colorado Court of Appeals, 2008)
Fowler & Peth, Inc. v. Regan
151 P.3d 1281 (Supreme Court of Colorado, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
854 F. Supp. 2d 1014, 2012 WL 592859, 2012 U.S. Dist. LEXIS 22714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amec-earth-environmental-inc-v-solsource-energy-solutions-llc-cod-2012.