AME & FE Investments, Ltd. v. NEC Networks, LLC, D/B/A CapturRX, and Chris Hotchkiss

CourtCourt of Appeals of Texas
DecidedSeptember 24, 2025
Docket04-24-00159-CV
StatusPublished

This text of AME & FE Investments, Ltd. v. NEC Networks, LLC, D/B/A CapturRX, and Chris Hotchkiss (AME & FE Investments, Ltd. v. NEC Networks, LLC, D/B/A CapturRX, and Chris Hotchkiss) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AME & FE Investments, Ltd. v. NEC Networks, LLC, D/B/A CapturRX, and Chris Hotchkiss, (Tex. Ct. App. 2025).

Opinion

Fourth Court of Appeals San Antonio, Texas MEMORANDUM OPINION

No. 04-24-00159-CV

AME & FE INVESTMENTS, LTD., Appellant

v.

NEC NETWORKS, LLC, d/b/a CAPTURERX, Appellee

From the 73rd Judicial District Court, Bexar County, Texas Trial Court No. 2012CI11952 Honorable David A. Canales, Judge Presiding

Opinion by: Lori Massey Brissette, Justice

Sitting: Rebeca C. Martinez, Chief Justice Lori I. Valenzuela, Justice Lori Massey Brissette, Justice

Delivered and Filed: September 24, 2025

AFFIRMED

In this contract dispute spanning more than a decade, we are asked to weigh in for a third

time. 1 In our most recent opinion, we (1) reversed the portion of the trial court’s March 10, 2017

1 See AME & FE Investments, Ltd. v. NEC Networks, LLC (AME II), No. 04-17-00332-CV, 2019 WL 286121 (Tex. App.—San Antonio Jan. 23, 2019, no pet.) (mem. op.) (affirming in part, reversing and rendering in part, and reversing and remanding NEC’s request for specific performance to trial court for determination of amount to be paid pursuant to certain notes); AME & FE Investments, Ltd. v. NEC Networks, LLC (AME I), 582 S.W.3d 294 (Tex. App.—San Antonio 2017, pet. denied) (granting motion challenging trial court’s order setting security and remanding to trial court for entry of order consistent with opinion). 04-24-00159-CV

judgment granting appellee NEC Networks, LLC’s request for specific performance and vacating

appellant AME & FE Investments, Ltd.’s liens and security interests and (2) remanded “to the trial

court for a determination of the amount to be paid by NEC to AME pursuant to the Convertible

Promissory Notes dated February 27, 2009 and September 1, 2009.” AME II, 2019 WL 286121, at

*18. On remand, the trial court ordered NEC to pay $1,507,916.67. AME appeals again, arguing

the trial court erred in its determination of the amount. Based on the law and the record, we affirm.

BACKGROUND

A. Facts

The facts of this case are well-established and outlined in our prior opinions. Pursuant to a

Note Purchase Agreement (NPA), AME loaned NEC $500,000 on February 27, 2009 (Note 1) and

$1 million on September 1, 2009 (Note 2), both loans being secured by liens on NEC’s property.

AME had the option of converting the principal amounts due into an equity interest in NEC on or

before the Maturity Date of October 1, 2011. AME did not exercise its conversion option prior to

that date. Thus, per the NPA, NEC’s Maturity Date for purposes of repayment of the Notes became

March 29, 2012, 180 days after the October date. While NEC asked for a payoff letter stating the

final amount due, informing AME that it had been approved for a new loan that would enable NEC

to pay off the Notes held by AME, AME did not provide a letter until after the March 29th Maturity

Date. In the payoff letter, dated March 28th but sent on April 2nd, AME stated that NEC would

owe an additional per diem charge of $409.84, or a monthly interest payment of $12,500, if the

Notes were not paid by the March 29th Maturity Date. NEC continued to make such payments,

and AME continued to accept them, until November 19, 2012 when NEC tendered a cashier’s

check for $1,507,916.67 in payment of the outstanding loan principal plus accrued interest. AME,

however, refused to accept the tender or to release its liens on NEC’s property.

-2- 04-24-00159-CV

B. Trial Court Proceedings

In July 2012, before the November 2012 tender, NEC filed suit against AME asserting

claims for breach of contract and seeking a declaratory judgment that AME’s option to convert the

loan into an equity interest had expired. AME filed counterclaims for breach of contract, fraud,

and fraudulent transfer. The trial court granted summary judgment to NEC, finding that AME

breached the contract by refusing to accept NEC’s payoff tender and refusing to release its liens.

The trial court also granted summary judgment in favor of NEC on AME’s counterclaims for

breach of contract and for specific performance. The jury then found that (1) AME breached the

contract first, (2) AME’s breach was not excused by a prior breach by NEC, but (3) NEC did

breach the contract by failing to pay off the Notes by April 3, 2012 (providing a grace period). The

jury awarded $6,000 to NEC but refused to award attorney’s fees. NEC then moved for specific

performance, requesting that AME’s liens be vacated, which request was granted by the trial court.

C. Prior Appeal

In the prior appeal of the trial court’s judgment, we recognized that AME chose repayment

by failing to exercise its conversion option, that AME acknowledged NEC’s ability to make

repayment after the contractual deadline, and that AME accepted NEC’s post-deadline interest

payments. We affirmed the jury’s finding that AME breached its contracts by failing to accept the

payoff tender and the finding that AME’s breach was not excused. We, however, reversed the

judgment of $6,000 against AME, sustaining AME’s legal sufficiency challenge to the damage

award. We also held the trial court erred by granting the equitable remedy of specific performance

to NEC, vacating AME’s liens, without requiring NEC to perform its repayment obligations under

the Contract. AME II, 2019 WL 286121, at *12 (citing DiGuiseppe v. Lawler, 269 S.W.3d 588,

594 (Tex. 2008). While AME urged us to modify the trial court’s judgment to award it

-3- 04-24-00159-CV

$1,511,855.25, we refused to do so. Instead, we remanded the matter to the trial court to determine

the amount NEC must pay under the Contract to support the award of specific performance,

specifically noting that the trial court was required to take into account the interest payments made

by NEC after the March 29th Maturity Date. Id. at *2, 17–18.

D. Trial on Remand

On remand, NEC argued that the amount it must pay to obtain specific performance is

$1,507,916.67, asserting as this court did in its prior opinion, that AME’s asserted amount due of

$1,511,855.25 did not account for interest payments made by NEC between March and November

of 2012. AME argued that it was entitled to the principal and interest owed on the Notes as well as

all actual expenses of collection, court costs, and reasonable attorney’s fees. On May 4, 2023, the

trial court held the remand trial. The parties included as exhibits R-1 to R-6, respectively, the NPA,

the Notes, the security agreement, AME’s payoff letter, and NEC’s November 2012 tender letter

which was accompanied by a cashier’s check for $1,507,916.67. On December 6, 2023, the trial

court issued a final judgment on remand ordering NEC to pay AME $1,507,916.67 pursuant to the

Notes to support NEC’s award of specific performance vacating AME’s liens.

On January 24, 2024 the trial court issued its findings of fact and conclusions of law. 2

Specifically, the trial court found that NEC is required, pursuant to the Notes, to pay AME

2 AME contends the trial court erred when it failed to enter additional findings of fact and conclusions of law. See TEX. R. CIV. P. 298 (allowing request for additional findings or conclusions). But, a “trial court is only required to make additional findings on ultimate issues; additional findings that relate to an evidentiary point are improper.” Villarreal v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DiGiuseppe v. Lawler
269 S.W.3d 588 (Texas Supreme Court, 2008)
Jamestown Partners v. City of Fort Worth
83 S.W.3d 376 (Court of Appeals of Texas, 2002)
Hudson v. Wakefield
711 S.W.2d 628 (Texas Supreme Court, 1986)
Rich v. Olah
274 S.W.3d 878 (Court of Appeals of Texas, 2008)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
II Deerfield Ltd. Partnership v. Henry Building, Inc.
41 S.W.3d 259 (Court of Appeals of Texas, 2001)
Sterling Projects, Inc. v. Fields
530 S.W.2d 602 (Court of Appeals of Texas, 1975)
Baker Marine Corp. v. Weatherby Engineering Co.
710 S.W.2d 690 (Court of Appeals of Texas, 1986)
Graham Central Station, Inc. v. Jesus Peña
442 S.W.3d 261 (Texas Supreme Court, 2014)
Egna Bishop Villarreal v. Guillermo Gonzalez Guerra
446 S.W.3d 404 (Court of Appeals of Texas, 2014)
Phillips v. Bramlett
407 S.W.3d 229 (Texas Supreme Court, 2013)
Scott Pelley P.C. v. Wynne
578 S.W.3d 694 (Court of Appeals of Texas, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
AME & FE Investments, Ltd. v. NEC Networks, LLC, D/B/A CapturRX, and Chris Hotchkiss, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ame-fe-investments-ltd-v-nec-networks-llc-dba-capturrx-and-chris-texapp-2025.