Ambrogetti v. Strahorn

232 P. 650, 113 Or. 265, 1925 Ore. LEXIS 199
CourtOregon Supreme Court
DecidedDecember 18, 1924
StatusPublished

This text of 232 P. 650 (Ambrogetti v. Strahorn) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ambrogetti v. Strahorn, 232 P. 650, 113 Or. 265, 1925 Ore. LEXIS 199 (Or. 1924).

Opinion

This was an action brought for the reasonable value of certain services performed by the plaintiff, as a contractor, for the defendant, in grading and building a portion of defendant's railroad in Klamath County, Oregon; in clearing a portion of the right of *Page 266 way; in making fills and doing other work incident to the grading, and in finding labor and furnishing materials for the work. The complaint alleges that the services and materials were reasonably worth the sum of $6,900.75, and that defendant has not paid any part thereof except the sum of $4,887.40, and judgment was demanded for the balance.

The defendant answered, and admitted that the plaintiff performed labor and rendered services for defendant between August 22, 1917, March 8, 1918, in connection with the construction of the Klamath Falls Municipal Railway, of which defendant was general contractor; admitted that plaintiff cleared a portion of the right of way for the railroad; admitted that plaintiff performed labor in the construction of the grade, but alleged that such labor was performed by plaintiff pursuant to an express contract entered into between plaintiff and defendant about August 20, 1917, and executed in writing under date of September 8, 1917, whereby plaintiff agreed to do the construction work therein specified, within the time fixed for completion, and under the terms and conditions of the contract, a copy of which was attached and made a part of the answer. Defendant denied that the labor alleged to have been performed was performed at defendant's request, but alleged that it was performed pursuant to plaintiff's obligations, as set forth in the contract, and denied generally all of the other allegations in the first paragraph of the complaint.

By way of a further and separate answer, and by way of counterclaim, defendant alleged the written contract; alleged that defendant had kept and performed the obligations of this contract on his part; that plaintiff partially performed the construction work therein undertaken by him, to the amount of *Page 267 $2,954.25, and that defendant had fully paid plaintiff for all work and all claims arising under the contract; that in pursuance to certain provisions in the written contract defendant had paid plaintiff, for work so performed under the contract and for money expended for the use of plaintiff, at his request, the total sum of $6,179.18. Defendant alleged that plaintiff is entitled to credit for work performed in the aforesaid sum of $2,954.25, and that plaintiff is entitled to credit for the return of materials furnished to him and charged to his account in the sum of $734.75, making a total credit of $3,689, leaving a balance in favor of defendant in the sum of $2,490.18. A statement of account was attached and marked Exhibit "B." Defendant then alleged that plaintiff, at the time the contract was entered into, represented to defendant that plaintiff was experienced in railway construction work, and insisted upon taking the work at a flat price per yard, rather than the customary manner of varying prices according to the classification of materials to be moved, and represented that he could complete the construction work by December 1, 1917, as stipulated in the contract; that, as a matter of fact, as disclosed by plaintiff's methods in handling the work, plaintiff was inexperienced in such construction work and did not progress with the work so fast as the same could have been done under capable management and efficient methods; that plaintiff did not complete the work by December 1, 1917, and that on December 3, 1917, he applied to defendant for an extension of time within which to complete the contract; that defendant suspended decision as to such extension, conditioned that plaintiff would cause the work under his contract to progress more rapidly; that about March 6, 1918, plaintiff having failed to progress so far as he should have, and plaintiff's *Page 268 indebtedness to defendant being steadily increased, by reason of plaintiff's observance of Section 34B of the contract, plaintiff was notified of his various breaches of and delinquencies under the contract, and the defendant, as provided in Sections 12 and 13 of the contract, declared the contract terminated and abandoned.

Then followed a second separate answer and defense, by way of counterclaim, setting forth Exhibit "A," and alleging that plaintiff had neglected to obey and fulfill the terms of the contract, and had only partially completed the construction work therein undertaken by him; that defendant was compelled to and did complete the work; that owing to the advance in labor and material costs the expense of completing the construction work exceeded what the same work would have cost if done within the contractual period by $2,000, in which sum defendant claimed damages. The answer concluded with a demand for the sum of $2,490.18, and the additional sum of $2,000, and for costs and disbursements.

Exhibit "A" is the ordinary form of railroad construction contract, too lengthy to be recited here.

Plaintiff then filed a reply, denying the allegations and new matter in defendant's answer; admitting, however, that he represented to the defendant that he was experienced in railroad construction work; admitting that he did not complete the construction work by December 1, 1917; admitting that he applied to defendant for an extension of time within which to complete the contract, and admitting that the defendant had declared the contract terminated and abandoned. For a further and separate reply plaintiff alleged that the defendant, through his duly authorized agent, solicited plaintiff to enter into a contract for clearing the right of way and grading *Page 269 the roadbed, with the work incidental thereto, on a portion of the proposed railroad then being constructed by defendant, and defendant at that time, through his agent, took plaintiff over a portion of the proposed railway line and showed him a definite and specified portion thereof which he proposed that plaintiff should clear and grade; that a large part of the portion so shown to him was of a soft material, easily handled and moved, and that after making a careful investigation thereof plaintiff offered to perform the work of clearing and grading all of said portion on the following terms:

"All excavations free haul 600 feet, including all excavated borrowed material: $.70 per cubic yard. $100 to be paid for the clearing and grubbing of the 100 foot right of way in addition to the amount paid for the wood cut and piled on the right of way; $1.75 per rick for all 24 inch wood cut and piled on said right of way, and, in addition, defendant agreed to pay plaintiff the actual cost to second party of laying pipe along said right of way."

Plaintiff alleged that in accordance with the agreement the defendant later prepared and submitted a written contract which it was understood between the parties should include all of the terms of said contract, but that defendant, in preparing said contract, wrongfully and fraudulently described the portion of said right of way by his station stakes in such manner as to exclude a large portion of the right of way which had been shown plaintiff and which he had agreed to clear and grade, said portion being the portion thereof which was easiest and cheapest to clear and grade, and included therein a large portion of right of way which consisted of rock and which was much more difficult and expensive to clear and grade; that defendant, after preparing said contract, induced plaintiff to sign the same, plaintiff believing *Page 270

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lovell v. Potts
207 P. 1006 (Oregon Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
232 P. 650, 113 Or. 265, 1925 Ore. LEXIS 199, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ambrogetti-v-strahorn-or-1924.