Amanna v. Carvel

167 A.D. 557, 152 N.Y.S. 796, 1915 N.Y. App. Div. LEXIS 7441

This text of 167 A.D. 557 (Amanna v. Carvel) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amanna v. Carvel, 167 A.D. 557, 152 N.Y.S. 796, 1915 N.Y. App. Div. LEXIS 7441 (N.Y. Ct. App. 1915).

Opinion

Laughlin, J.:

This is an action to foreclose a mechanic’s lien. On the 13th day of August, 1912, the appellant Carvel entered into a contract, in writing, with the city of New York, by its board of [558]*558education, for the construction of the Bay Ridge High School building in the borough of Brooklyn, pursuant to plans and specifications thereto annexed and made a part thereof, for the gross sum of $416,500. This contract, however, was awarded to Oarvel on July 24, 1912, and on August 9, 1912, he entered into a subcontract, in writing, with the plaintiff, by which the latter agreed to do all the excavating work required by the plans and specifications, and Oarvel agreed to pay him seventy-three cents per cubic yard for earth excavation, and forty cents per cubic yard for excavating sand, which was to be left on the premises where designated by Oarvel, and one dollar and fifty cents per cubic yard “for excavating trenches and pier holes.” On the 14th day of September, 1912, Oarvel entered into another' contract in writing with the plaintiff, by which the latter agreed “ To furnish all the Labor and Material necessary to set in place and to do all the Rubble Stone work and all the Concrete Footings required according to the plans and specifications ” for the school building, and was to receive therefor five dollars per cubic yard for the rubble stone work, and five dollars and twenty-seven cents per cubic yard for concrete footings. The plaintiff duly filed a lien under both contracts on the 21th day of January, 1913, and this action was brought to foreclose the same. The defendant surety company executed a bond, upon which the lien was discharged.

The trial court found that the plaintiff excavated 2,924 cubic yards of earth for “trenches and pier holes and tunnels,” for which he was entitled to receive one dollar and fifty cents per cubic yard. The evidence is uncontroverted that plaintiff excavated that number of cubic yards of earth over and above the quantity for which the court held he was entitled to recover at the rate of seventy-three cents per cubic yard. The controversy with respect to this work is over the classification thereof. It is claimed by appellants that for a large part of it plaintiff was entitled to receive only seventy-three cents per cubic yard, on the theory that it did not constitute the excavation of trenches or pier holes within the contemplation of the contract on that subject. Our attention has not been drawn to any provision of the specifications defining what was meant by those terms as used in the contract; nor is it claimed that those [559]*559terms are in any manner defined either in the contract or the specifications, or that their meaning was apparent on or discoverable by an inspection of the plans. We find no part of the excavation work marked on the plans as “trenches” or “pier holes.” It was assumed by both parties that “pier holes ” referred to the excavations for the foundations of columns. So far as the record shows, the case was tried on the theory that the word “trenches” was used in the contract in the sense in which it is understood in the trade, and testimony was given on both sides with respect to that meaning. That testimony is conflicting, and presented a fair question of fact, upon which an appellate court would not be warranted in reversing the finding of the trial court and making a finding the other way; but a new trial might be awarded if the ends of justice require it. A civil engineer and surveyor called by plaintiff testified on cross-examination that “trenches,” as used by the trade in building construction, includes all excavation work below the level of the bottom of the cellar of the building. The plans required excavations to a considerable depth below the level of the bottom of the cellar of the building for the foundation walls, “pipe tunnels,” elevator and boiler pits, heat ducts and service entrance. All of those excavations were known as < trenches, ” according to plaintiff’s witness, but the testimony offered in behalf of appellants tends to show that none of them excepting those for the walls of the building, were “trenches,” and the reason indicated by the witnesses for appellants for thus confining the meaning of the word “trenches” is that a higher rate is allowed for trench work owing to the fact that the material has to be handled several times, as the trenches ordinarily are too narrow to admit the vehicle in which the earth is to be carted away. With respect to a large part of the other excavations claimed by the plaintiff to be trench work, it was shown that they were so large that wagons could be and were driven into them in excavating. While this theory seems reasonáble, still a question of fact was presented on conflicting evidence which might have been obviated if the parties had made a more definite agreement. Moreover, on reading the specifications we find a. provision relating to excavations by which the contractor [560]*560was required to “ Do all requisite excavating of earth and rock for piers, walls, columns, and drip pits, pavements, cesspools, catch basins, trenches (including those for sewers, drains, gas and water supply pipes), etc., as required by these specifications and the plans, sections and elevations. ” The parenthesis in this quotation clearly relates to trenches and by it excavations for gas and water supply pipes are included in the term “ trenches ” which extends its meaning beyond the claim of the appellants and probably includes the “ pipe tunnels ” which constitute the principal item of excavation now being considered, although neither party showed what kind of pipe was to go in the “pipe tunnels.” In the circumstances we are not disposed to interfere with the finding of the trial court that the plaintiff was entitled to receive one dollar and fifty cents per cubic yard for earth removed from all of these excavations below the level of the bottom of the cellar.

The trial court also found that the plaintiff excavated 2,962 cubic yards of earth outside of the area walls and foundation walls and carted it away, pursuant to an agreement between him and Carvel, by which he was to receive seventy-three cents per cubic yard therefor, which was the reasonable value thereof. The specifications show that it was Carvel’s duty under his contract with the city to sheet pile the exterior lines of the excavations for area walls and foundation walls, so that the ground outside of those lines would remain intact. There was conflicting testimony with respect to the number of cubic yards of earth the plaintiff was obliged to excavate outside those lines; but the testimony in his behalf tended to show the quantity as found by the trial court, and on the appeal counsel for the appellants accepts that finding as to quantity. The excavation of that earth was rendered necessary owing to the failure of Carvel to do the sheet piling required by his contract with the city, which it was conceded by his testimony and that of his superintendent was his duty as between him and the plaintiff. The court found that this was extra work, but that the price thereof was agreed upon at seventy-three cents per cubic yard. There is testimony to the effect that Carvel agreed to pay for this work as extra work and that he agreed that the price should be governed by the contract. Con[561]*561cededly seventy-three cents per cubic yard was the contract price for excavating all earth inside these exterior lines to the level of the bottom of the cellar. The only, evidence bearing on the reasonable value of that work is the contract price of similar work within the lines of the cellar of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
167 A.D. 557, 152 N.Y.S. 796, 1915 N.Y. App. Div. LEXIS 7441, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amanna-v-carvel-nyappdiv-1915.