Am. Environmental Group, Ltd. v. H.M. Miller Constr. Co.

2014 Ohio 4681
CourtOhio Court of Appeals
DecidedOctober 23, 2014
Docket100854
StatusPublished
Cited by3 cases

This text of 2014 Ohio 4681 (Am. Environmental Group, Ltd. v. H.M. Miller Constr. Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Am. Environmental Group, Ltd. v. H.M. Miller Constr. Co., 2014 Ohio 4681 (Ohio Ct. App. 2014).

Opinion

[Cite as Am. Environmental Group, Ltd. v. H.M. Miller Constr. Co. , 2014-Ohio-4681.]

Court of Appeals of Ohio EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

JOURNAL ENTRY AND OPINION No. 100854

AMERICAN ENVIRONMENTAL GROUP, LTD. PLAINTIFF-APPELLEE

vs.

H.M. MILLER CONSTRUCTION CO., ET AL. DEFENDANTS-APPELLANTS

JUDGMENT: REVERSED AND REMANDED

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-13-810811

BEFORE: E.T. Gallagher, J., Boyle, A.J., and Kilbane, J.

RELEASED AND JOURNALIZED: October 23, 2014 ATTORNEYS FOR APPELLANTS

Aaron S. Evenchik Rick L. Amburgey Andrew J. Natale Frantz Ward L.L.P. 2500 Key Center 127 Public Square Cleveland, Ohio 44114

ATTORNEYS FOR APPELLEE

Mark F. Craig Michael P. O’Donnell David Sporar Brouse McDowell, L.P.A. 600 Superior Avenue, East Suite 1600 Cleveland, Ohio 44114 EILEEN T. GALLAGHER, J.:

{¶1} Defendants-appellants, H.M. Miller Construction Co. (“H.M.M.”) and Ohio

Farmers Insurance Company (“OFIC”), collectively (“appellants”), appeal the denial of

their motion to quash subpoenas and for protective order. We find merit to the appeal,

reverse the trial court’s judgment and remand the case to the trial court for an in camera

inspection of the subpoenaed documents.

{¶2} This case arises from a construction project in the city of Fremont, Ohio

(“Fremont” or “the city”). The city planned to build a raw water reservoir and hired

H.M.M. as the general contractor for the project. Fremont also retained Arcadis, U.S.

Inc. (“Arcadis”), as the project engineer. OFIC was the surety for the payment bond on

the project.

{¶3} During construction, problems were discovered in the rock floor of the

reservoir that necessitated a change from a clay-lined reservoir to a geosynthetic-lined

reservoir. In May 2011, H.M.M. subcontracted with plaintiff-appellee, American

Environmental Group Ltd. (“AEG”), to install the geosynthetic liner. Payment and

contract disputes subsequently arose between Fremont and H.M.M., and H.M.M. failed to

pay AEG for the work it performed on the project. Ultimately, AEG filed a lien against

public funds, asserted a claim against the payment bond, and filed suit against H.M.M.,

OFIC, and Fremont in the Sandusky County Court of Common Pleas. The parties

recognized that H.M.M.’s failure to pay AEG was caused, in part, by the city’s refusal to pay H.M.M. In June 2012, H.M.M. filed suit against Fremont in the Sandusky County

Common Pleas Court.

{¶4} In June 2012, H.M.M. and Fremont participated in mediation to review the

claims and discuss completion of the project. The parties reached an agreement in which

Fremont agreed to pay a portion of H.M.M.’s and AEG’s claims, and H.M.M. agreed to

complete the project as outlined in a “Memorandum of Understanding” between Fremont

and H.M.M.

{¶5} H.M.M. subsequently met with AEG to review the Memorandum of

Understanding and to obtain AEG’s agreement to complete the reservoir project.

Following negotations, H.M.M., AEG, and OFIC entered into a “Liquidating and Joint

Prosecution Agreement” (“Joint Prosecution Agreement”), in which they agreed to

resolve the payment dispute between them and to collectively prosecute their claims

against Fremont. The Joint Prosecution Agreement provided, in relevant part:

CONTRACTOR [H.M.M.] and SUBCONTRACTOR [AEG] agree to jointly prosecute their respective claims relating to the project against the Project Owner through Contractor’s existing lawsuit in the Common Pleas Court of Sandusky County, (Case No. 12 CV 758) (“Lawsuit”) which claims will include those of SUBCONTRACTOR. Although SUBCONTRACTOR need not be a party to that Lawsuit to mitigate SUBCONTRACTOR’s legal expense. CONTRACTOR consents to sponsor SUBCONTRACTOR’s claims in the Lawsuit and all related alternative dispute resolution procedures, with SUBCONTRACTOR’s reasonable cooperation, in accordance with the Contract and applicable law, subject to CONTRACTOR’s sole right to direct and manage litigation.

{¶6} The litigation between H.M.M. and Fremont remained unresolved, and

H.M.M. and Freemont participated in a second mediation in October 2012. The parties were unable to resolve their dispute at this mediation. Consequently, Fremont filed suit

against the project engineer at Arcadis in the Sandusky County Court of Common Pleas.

This case was assigned to the same judge as other litigation arising from the Fremont

reservoir project.

{¶7} In an effort to settle all the litigation, Fremont, Arcadis, H.M.M., and another

construction company participated in a third mediation in January 2013 (“the Global

Mediation”). H.M.M. invited AEG to attend the mediation, but AEG declined. H.M.M.

and Fremont resolved their dispute at the mediation, and Fremont paid H.M.M. a lump

sum of $6.75 million to settle all claims. Although AEG claimed it was entitled to

almost $1 million, H.M.M. only paid AEG $144,622. As a result, AEG filed a complaint

against appellants in the Cuyahoga County Common Pleas Court, asserting claims for (1)

breach of contract, (2) a declaratory judgment declaring that H.M.M.’s payment under the

Joint Prosecution Agreement was not properly calculated under the terms of that

agreement, and (3) a claim against the payment bond for the reservoir project.

Appellants answered the complaint and asserted two counterclaims for declaratory

judgment declaring (1) that H.M.M. properly paid AEG in full under the Joint

Prosecution Agreement, and (2) that OFIC is not obligated to pay any additional amounts

to AEG under the payment bond.

{¶8} In September and October 2013, AEG issued subpoenas duces tecum to

Fremont and Arcadis, neither of whom are parties to this case. AEG served appellants

with notice of the subpoenas. In November 2013, appellants filed a motion to quash the subpoenas, or in the alternative, for protective order on the basis that the documents

sought by AEG constituted privileged mediation communications under R.C. 2710.01 et

seq.

{¶9} In an order denying the motion to quash, the trial court stated:

Insofar as the motion is for a protective order, the issue is not yet justiciable because I cannot assess whether the claimed privilege applies to any of the documents without knowing what the documents are.

* * *

Therefore, once the plaintiff gets the documents it must produce a complete copy of them to the defendants. Once the defendants review the documents, they are welcome to file another motion for protective order to prevent plaintiff from using privileged mediation communications in discovery or at trial and to “claw back” any such communications. The motion should include a request for an in camera inspection of the documents at issue.

In the meantime, until the privilege is decided, the plaintiff’s counsel is prohibited from sharing with the plaintiff, consulting experts, and other witnesses, any documents received in response to the subpoenas.

Appellants now appeal from this judgment.

Final Appealable Order

{¶10} As a threshold matter, we must determine whether the appeal is properly

before us. Pursuant to R.C. 2505.03(A), the jurisdiction of courts of appeals is limited to

the review of final orders, judgments, or decrees. State ex rel. Bd. of State Teachers

Retirement Sys. of Ohio v. Davis, 113 Ohio St.3d 410, 2007-Ohio-2205, 865 N.E.2d 1289,

¶ 44.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Albers v. Lyon
2026 Ohio 209 (Ohio Court of Appeals, 2026)
Shram v. Masadeh
2024 Ohio 1662 (Ohio Court of Appeals, 2024)
Whitehead v. Ohio Dept. of Rehab. & Corr.
2023 Ohio 625 (Ohio Court of Claims, 2023)
Molnar v. Wong
2021 Ohio 1402 (Ohio Court of Appeals, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 4681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/am-environmental-group-ltd-v-hm-miller-constr-co-ohioctapp-2014.