Alter Co. v. United States

412 F. Supp. 73, 1976 U.S. Dist. LEXIS 15532
CourtDistrict Court, S.D. Iowa
DecidedApril 16, 1976
DocketCiv. 73-20-D
StatusPublished
Cited by2 cases

This text of 412 F. Supp. 73 (Alter Co. v. United States) is published on Counsel Stack Legal Research, covering District Court, S.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alter Co. v. United States, 412 F. Supp. 73, 1976 U.S. Dist. LEXIS 15532 (S.D. Iowa 1976).

Opinion

ORDER

STUART, District Judge.

This cause came on for trial to the Court on August 12, 1975 on the issue of liability. Plaintiff seeks to recover damages from the United States on the theory that the government lock personnel negligently utilized their statutory and regulatory power to control movements of tows in government locks and approaches so as to cause the Motor Vessel (M/V) YETTA ALTER to lose control of her tow and to subsequently collide with Dam 25 on the upper Mississippi River. The government has counterclaimed for the minimal damages to the dam resulting from the collision. The Court has jurisdiction over the case pursuant to the Suits in Admiralty Act, 46 U.S.C. § 741 et seq. The final brief was filed March 22, 1976. After examining the transcript of the trial, the exhibits, and post-trial briefs of the parties, the Court now enters this memorandum opinion which constitutes the findings of fact and conclusions of law.

The Court holds that the primary responsibility for this accident must rest with the plaintiff. Pilot Barrier negligently operated his vessel by backing her tow out of the forebay. The Alter Company was negligent in entrusting the tow to a novice pilot under the river conditions as they existed in early January of 1973. The government personnel operating Lock and Dam 25 were guilty of incidental negligence in the performance of their duties. The Court will thus order a 90%-10% proration of the damages incurred.

Plaintiff owned the YETTA ALTER, a steel hulled river towboat 106.5 feet long and 30 feet wide powered by two diesel engines of about 900 horsepower each. Each diesel engine had an “overload” capacity which would increase the rate of engine rotation. A steering rudder was located immediately aft of each propeller and two backing rudders were located forward of each propeller, with one backing rudder located on each side of the propeller shaft. On the date of the collision with Dam 25, both engines and all steering mechanisms were in good working order.

On January 2, 1973, the YETTA ALTER departed from LaGrange, Missouri, destined for Cairo, Illinois, with a tow of eight loaded barges. The barges were each 35 feet wide and about 195 feet long. The eight barges were arranged in three rows of three barges each, except that there was no barge in the aft position of the port row. The tow was thus 585 feet long and 105 feet wide. The YETTA ALTER was made up *75 to the center stern barge with wire rigging or face wires, port and starboard.

Navigation of the YETTA ALTER was under the responsibility of the Master, Jimmy Hardin, and the Pilot, Gary Barrier. Hardin navigated the before watches (6 to 12) and Barrier handled the after watches (12 to 6). Captain Hardin had served on towboats for over 11 years and had made over 500 trips on the upper Mississippi River. Pilot Barrier, on the other hand, had been a pilot for less than a month and had been a steersman for about six months. He had never navigated a tow or more than four barges through any lock on the upper Mississippi or on any other river. He had never navigated a tow of any size through Lock 25.

When the YETTA ALTER departed in early January of 1973, the Mississippi was at a high water stage with floating and drifting ice which collected in the approaches to the locks. Ice conditions vary from lock to lock. Adjacent to each lock is a dam with a corresponding number. On January 2-4, 1973, dams 22, 24, 25 and 26 were at “open river”. (There is no lock and dam 23) Open river indicates that the gates of the dam regulating water flow through the dam are completely raised. When the river is at open river, there generally exists a condition known as “out-draft”. This is a current from the shore out into the river above the lock and dam. There was evidence that the outdraft above lock and dam 25 on January 4, 1973 was about 7 miles per hour. This was described as very severe.

The proposed journey of the YETTA ALTER and her barges would take her through four locks. The YETTA ALTER went through Lock 22 without incident.

At about midnight on January 3, 1973, the YETTA ALTER arrived at Lock 24. At this lock, ice had pushed into the forebay so that the lock operator could not open the lock gates. The lockmaster requested the YETTA ALTER to break ice in the forebay. Captain Hardin tied off the tow about % of a mile above the lock and took the towboat into the forebay to break ice. Shortly thereafter, Barrier came on duty and spent the next five hours or so breaking ice. When Hardin came back on duty, he was able to bring the tow into the forebay. Although considerable ice had been displaced from the front of the lock gates, the remaining ice still made it impossible for the tow to go into the lock. Hardin pushed the tow about 400 feet into the ice and tied the tow off to the land guidewall. He then broke free and spent over three hours breaking and working ice from the front of the tow after which he was able to push the tow into the lock chamber. When Barrier came back on duty at noon on January 4, 1973, the tow was still in the lock. Shortly thereafter, the YETTA ALTER completed the lockage at Lock 24 and proceeded downriver. It took over 12 hours of tedious and patient seamanship for the YETTA ALTER and her tow to complete the lockage at Lock 24. This contrasts sharply with the hurried effort at Lock 25.

Lock and Dam 25 is about 32 miles downriver from Lock and Dam 24. The last tie off location above Lock 25 is at Sandy Creek, three or four miles above the lock. When the YETTA ALTER was seven or eight miles above Lock and Dam 25, Barrier called the lock on his radio. He advised the lock operator, Ezra F. Williams, of his location and his tow and asked about the conditions at the lock and whether he should tie off the tow and come down “lightboat” to break ice as had been done at Lock 24. Williams advised that the dam was at open river, that there was an outdraft and ice in the forebay and stated that the boat and her barges were cleared for an approach to Lock 25.

Lock 25 is 110 feet wide and is located on the right descending bank of the Mississippi River near Winfield, Missouri. The lock facility includes a concrete, land guidewall, which extends 600 feet upriver from the lock chamber along the right descending bank. A parallel concrete wall extends 450 feet upriver at the west end of the dam and is known as the river guidewall. The area between the land guidewall and the river *76 guidewall is the forebay; the distance between the two is about 300 feet. A shorter wall, the “bullnose”, extends about 120 feet upstream from the lock gates into the fore-bay. The bullnose is midway between, and parallel to, the land guidewall and the river wall. The main lock chamber is formed by lock gates located between the bullnose and the land guidewall. A revetted rock bank, or dike, extends about 1200 feet upstream from, and about 50 feet inshore of, the upriver end of the land wall. Along the length of this rock revetment, at 200 feet intervals, are six IV2 inch steel mooring cables. There are also tow mooring cables on the upriver end of the river guidewall.

On the afternoon of January 4, 1973, there was ice in the forebay at Lock 25, but it was not as severe as at Lock 24. The lock operator at 24 had been unable to open the lock gates because of the severe ice conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Complaint of Ingram Barge Co.
194 F. Supp. 3d 766 (N.D. Illinois, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
412 F. Supp. 73, 1976 U.S. Dist. LEXIS 15532, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alter-co-v-united-states-iasd-1976.