Alpert v. Jarrell Carpentry Company

510 S.W.2d 136
CourtCourt of Appeals of Texas
DecidedMay 2, 1974
Docket18324
StatusPublished
Cited by5 cases

This text of 510 S.W.2d 136 (Alpert v. Jarrell Carpentry Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alpert v. Jarrell Carpentry Company, 510 S.W.2d 136 (Tex. Ct. App. 1974).

Opinion

GUITTARD, Justice.

Jarrell Carpentry Company, a partnership, sued Robert Alpert on an oral contract for home repairs and remodeling. On trial the jury found in answer to special issues (1) that plaintiff did not substantially perform in accordance with the terms and specifications of the contract between the parties, (2) that the balance due and owing to plaintiff from defendant after allowance of all proper offsets, credits and payments in favor of either party was $830.03, and (3) that the amount of a reasonable fee for plaintiff’s attorney was “none.” The trial court rendered judgment for plaintiff in the amount found by the jury and denied plaintiff’s claim for attorney’s fee. Defendant appeals, contending in his single point of error that in view of the finding that plaintiff did not substantially perform its contractual obligation, it was not entitled to any recovery in absence of findings of the reasonable value of any benefits to defendant from plaintiff’s work. By cross-point, plaintiff complains of denial of the attorney’s fee. We affirm.

1. Substantial performance

We overrule defendant’s point because we conclude that recovery for part performance is allowed by the terms of the oral contract and that the answer to the substantial performance issue does not establish that the work was defective.

The contract was made between Dock Jarrell, one of the partners in plaintiff Jarrell Carpentry Company, and William H. Carter, agent for defendant Alpert. According to Carter’s testimony, he gave Jarrell a written list of items of work to be done, which included renovation of the interior and exterior of the house. He testified that he agreed with Jarrell that the work would be performed on a time-and-material basis plus thirty percent because they could not determine the exact extent of the work. He testified that he also told Jarrell that if the work was not progressing satisfactorily, plaintiff would be asked to leave the job.

According to Jarrell, no list was provided but he and Carter walked through the house and Carter pointed out what defendant wanted done. Jarrell testified that he agreed to do the work for time and materials plus thirty percent, and that it was agreed that he could be paid off and terminated at any time.

After this agreement was made, plaintiff began the work on a Wednesday. At the end of that week or the following Monday plaintiff submitted an invoice in the amount of $1,704.05, and defendant paid it. During the second week a dispute arose as to whether the paint on the garage was the right color. Defendant complained to Carter that the color was wrong and also that the work was not progressing satisfactorily. Carter made an inspection and then, on Wednesday of the second week, *138 notified Jarrell that plaintiff’s employment was terminated. Plaintiff submitted a second invoice for $2,406.50 for labor and materials plus thirty percent, but defendant refused to pay. Defendant employed another contractor to finish the work and paid him a total of $12,500. This contractor testified as witness for defendant that of that total charge, $3,050 was for correcting and repairing plaintiff’s work, and that the reasonable value of all the work performed by plaintiff, including that for which plaintiff had been paid, was “roughly a thousand dollars.”

Plaintiff sued on a sworn account for the alleged balance of $2,406.50, and in the alternative for that amount on the express contract, and in the further alternative in quantum meruit alleging the reasonable value of plaintiff’s services to be in the same amount.

Defendant contends on this appeal that the contract does not permit recovery according to its terms unless plaintiff performs the work in substantial compliance with the contractual terms and specifications. He construes the jury’s finding that plaintiff did not substantially perform as a finding that the work as performed was defective rather than incomplete, and, consequently, he argues that plaintiff was not entitled to recover on the contract on a time-and-material basis and, since the jury made no finding of the value of any benefits to defendant, neither was it entitled to recover on a quantum meruit basis.

We do not agree that the finding of no substantial performance established that the work done was defective. Although no definite plans and specifications were established for the job, the undisputed evidence shows that at the time plaintiff’s services were terminated, plaintiff had performed only part of the work discussed by Jarrell and Carter at the time the contract was made. The court’s charge did not limit “substantial performance” to that part of the work actually done by plaintiff at the time of termination. The issue inquired whether plaintiff substantially performed “in accordance with the terms and specifications in the contract,” and an instruction accompanying the issue defined “substantial performance” as “performance by the plaintiff of all important and essential particulars of the contract, with only such omissions or deviations from the contract as are inadvertent and unintentional, are not due to bad faith, and are merely trivial defects or omissions.” Under this issue and instruction the jury could well have understood “terms and specifications of the contract” to include all the work discussed by the parties, and according to this interpretation would have had no alternative under the undisputed evidence but to answer, as they did, that plaintiff “did not substantially perform,” without determining the quality of the performance. Since defendant had the privilege under the contract to terminate plaintiff’s employment at any time on payment at the contract rate for work done, we hold that the contract permits recovery for partial performance and that the finding that defendant did not substantially perform does not bar recovery on the contract for the work done to the time of termination.

The amount of plaintiff’s recovery is established by the answer to the second special issue, which inquired the balance due the plaintiff from defendant “after the allowance of all proper offsets, credits and payments, if any, shown by a preponderance of the evidence to exist in favor of either party.” Defendant objected to this issue on various grounds, but has not brought those objections forward because he limits his prayer to one for rendition of judgment in his favor and expressly states that he would rather that the case be affirmed than remanded for a new trial. In this state of the record, we must affirm, since we find ample basis in the record for recovery on the contract of an amount in excess of the $830.03 found by the jury. Apparently the jury allowed some items of plaintiff’s claim and disallowed others. This verdict was permissible in view of the broad language of the issue. Defendant’s *139 only argument here is that no recovery was proper in absence of a finding of the value of benefits to defendant, and we reject that argument for the reasons above given.

2. Attorney’s fee

By cross-point plaintiff complains that the trial court erred in denying recovery for its attorney’s fee notwithstanding the jury’s answer of “none” to the issue inquiring the amount of a reasonable fee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bobbie Brooks, Inc. v. Goldstein
567 S.W.2d 902 (Court of Appeals of Texas, 1978)
TJ Service Co. v. Major Energy Co., Inc.
552 S.W.2d 598 (Court of Appeals of Texas, 1977)
Hanson Southwest Corp. v. Dal-Mac Construction Co.
554 S.W.2d 712 (Court of Appeals of Texas, 1977)
Howard v. French-Brown Floors Co.
542 S.W.2d 709 (Court of Appeals of Texas, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
510 S.W.2d 136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alpert-v-jarrell-carpentry-company-texapp-1974.