Aloha Lumber Corporation v. Boise Cascade Corporation

19 F.3d 25, 1994 U.S. App. LEXIS 11142, 1994 WL 56927
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 18, 1994
Docket92-36729
StatusUnpublished

This text of 19 F.3d 25 (Aloha Lumber Corporation v. Boise Cascade Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aloha Lumber Corporation v. Boise Cascade Corporation, 19 F.3d 25, 1994 U.S. App. LEXIS 11142, 1994 WL 56927 (9th Cir. 1994).

Opinion

19 F.3d 25

NOTICE: Ninth Circuit Rule 36-3 provides that dispositions other than opinions or orders designated for publication are not precedential and should not be cited except when relevant under the doctrines of law of the case, res judicata, or collateral estoppel.
ALOHA LUMBER CORPORATION, Plaintiff-Appellant,
v.
BOISE CASCADE CORPORATION, Defendant-Appellee.

No. 92-36729.

United States Court of Appeals, Ninth Circuit.

Argued and Submitted Feb. 2, 1994.
Decided Feb. 18, 1994.

Before: GOODWIN, SCHROEDER, and NORRIS, Circuit Judges.

MEMORANDUM*

Aloha Lumber Corporation appeals a judgment by the district court holding that its agreement with Boise Cascade Corporation to pay $500,000 for the right to unilaterally terminate its obligations under a $43.2 million real estate purchase agreement was a valid and enforceable liquidated damages clause under Washington law. We affirm.

Aloha Lumber entered into a written agreement to purchase for $43.2 million approximately 89,000 acres of prime Northwest timberland owned by Boise Cascade. The sale was contingent on Aloha Lumber's ability to obtain financing. Pursuant to section 2.1 of the purchase and sale agreement, Aloha Lumber transferred $500,000 to Boise Cascade in partial payment of the purchase price. Section 2.2 of the agreement provided that "[i]n the event Aloha is unable to secure financing, then Aloha may terminate this Agreement without further liability to Boise Cascade, provided that Boise Cascade shall retain the $500,000 down payment."

Aloha Lumber claims that Boise Cascade suffered no actual damages as a result of Aloha Lumber's inability to close the purchase agreement, and therefore that section 2.2 constitutes an unenforceable penalty. Boise Cascade responds first that the $500,000 deposit is consideration for what it characterizes as a valid termination clause. In the alternative, Boise Cascade argues that if the $500,000 payment is to be considered an earnest money deposit, then the payment is valid as liquidated damages.

The district court upheld the payment, finding that it was a valid termination clause. In addition, the district court applied the two-part test used by Washington courts to determine whether a stipulated damages clause constitutes an unenforceable penalty, and further upheld section 2.2 as a valid liquidated damages clause.

We review de novo the district court's interpretation of Washington law. Brooks v. Hilton Casinos Inc., 959 F.2d 757, 759 (9th Cir.), cert. denied, 113 S.Ct. 300 (1992). We are bound to follow the decisions of Washington state's highest court in interpreting its law. See Meusy v. Montgomery Ward Life Ins. Co., 943 F.2d 1097, 1099 (9th Cir.1991). If no ruling exists from the Washington Supreme Court, we must follow intermediate appellate decisions unless convinced by other persuasive data that the state's high court would decide otherwise. Id.

I. Enforceability of the Purchase and Sale Agreement

A termination clause requires consideration to be valid. Otherwise, such a clause will be held to be an unenforceable illusory promise. See 17A Am.Jur.2d Contracts Sec. 560 (1993). Thus, there is a very fine line separating termination clauses from liquidated damages clauses. See, e.g., Watson v. Ingram, 851 P.2d 761, 762-763 (Wash.Ct.App.1993), review granted, 1994 Wash.Lexis 15 (1994) (holding that a contractual clause titled "Termination" was an enforceable liquidated damages clause). Nevertheless, we hold that sections 2.1 and 2.2 of the purchase and sale agreement are valid under either characterization.

Washington courts have generally applied a two-part test to determine whether the retention by the vendor of an earnest money deposit pursuant to a real estate sales contract is invalid as a penalty. The damages stipulated must be (1) a reasonable forecast of just compensation for the breach that may occur, and (2) the damages caused by the breach must be incapable or very difficult of accurate estimation. Management, Inc. v. Schlassberger, 235 P.2d 293, 297 (Wash.1951); Restatement of Contracts Sec. 339, at 552 (1932)).

The district court found that the $500,000 partial payment made by Aloha Lumber was a reasonable forecast of the potential damages for nonperformance of the contract in view of the risks to which Boise Cascade subjected itself by taking 89,000 acres of its prime Northwest timberland off the market during the closing period. These risks included the effect on Boise Cascade's stock price of publicly announcing a deal that it later might have to withdraw, overhead costs associated with continuing to manage the unpurchased land, and the loss of the use of the proceeds from the sale until another purchaser could be found. The district court did not make a specific finding that the damages caused by Aloha Lumber's termination of the contract were incapable or very difficult to accurately estimate. However, the court did contrast the present case to a prior Washington case in which damages were easily calculated and no actual loss appeared to have occurred. See Lind Building Corp. v. Pacific Bellevue Developments, 776 P.2d 977 (Wash.Ct.App.1989).

Aloha Lumber contends that the district court misapplied Washington law regarding stipulated damages. Relying on Lind Building Corp. v. Pacific Bellevue Developments, Aloha Lumber argues that Boise Cascade suffered no actual damages and thus should not be allowed to retain the $500,000 partial payment. In Lind Building Corp., Lind agreed to purchase real estate from Pacific Bellevue Developments for approximately $4 million. Lind paid $20,000 as an earnest money deposit on the date of execution of the agreement, and over the next several months made a series of additional deposits totalling $230,000. Lind eventually defaulted on the agreement, and Pacific Bellevue Developments retained the $250,000 as liquidated damages, in addition to eventually selling the property to a different purchaser for a little more than $5 million. The Washington Court of Appeals held that the $250,000 payment constituted a penalty and was invalid. Id. at 981-982.

In so holding, the Lind Building Corp. court added a third prong to the test set forth in Management, Inc. v. Schlassberger, 235 P.2d 293 (Wash.1951). A stipulated damages clause will be held invalid as a penalty if the retained deposit is substantial and the actual loss is minimal or nonexistent. Lind Building Corp., 776 P.2d at 983. Although never explicitly stated by Washington courts prior to Lind Building Corp., this requirement has been implicit in the analysis under the first prong of the Management, Inc. test, i.e., whether the retained deposit constitutes a reasonable forecast of just compensation for the breach that may occur. See, e.g., Northwest Collector, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northwest Collectors, Inc. v. Enders
446 P.2d 200 (Washington Supreme Court, 1968)
Lind Building Corp. v. Pacific Bellevue Developments
776 P.2d 977 (Court of Appeals of Washington, 1989)
Hemenway v. Miller
776 P.2d 710 (Court of Appeals of Washington, 1989)
Herzog Aluminum, Inc. v. General American Window Corp.
692 P.2d 867 (Court of Appeals of Washington, 1984)
Stevens v. Security Pacific Mortgage Corp.
768 P.2d 1007 (Court of Appeals of Washington, 1989)
Stryken v. Panell
832 P.2d 890 (Court of Appeals of Washington, 1992)
Management, Inc. v. Schassberger
235 P.2d 293 (Washington Supreme Court, 1951)
Watson v. Ingram
851 P.2d 761 (Court of Appeals of Washington, 1993)
Seattle-First National Bank v. Washington Insurance Guaranty Ass'n
804 P.2d 1263 (Washington Supreme Court, 1991)
Brooks v. Hilton Casinos Inc.
959 F.2d 757 (Ninth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
19 F.3d 25, 1994 U.S. App. LEXIS 11142, 1994 WL 56927, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aloha-lumber-corporation-v-boise-cascade-corporation-ca9-1994.