Alma Perales and David Plummer v. Sunstone Pools & Outdoor Living LLC

Court of Appeals of Texas·Decided July 17, 2024·No. 05-24-00010-CV·Published

Opinion

AFFIRMED in part; REVERSED and RENDERED in part; REMANDED; and Opinion Filed July 17, 2024

S In The

Court of Appeals

Fifth District of Texas at Dallas No. 05-24-00010-CV

ALMA PERALES AND DAVID PLUMMER, Appellants V.

SUNSTONE POOLS & OUTDOOR LIVING LLC, Appellee

On Appeal from the 44th Judicial District Court Dallas County, Texas

Trial Court Cause No. DC-23-13419

MEMORANDUM OPINION

Before Justices Smith, Miskel, and Breedlove Opinion by Justice Smith

Appellants Alma Perales and David Plummer appeal the trial court’s order denying their motion to dismiss under the Texas Citizens’ Participation Act (TCPA). See TEX. CIV. PRAC. & REM. CODE ANN. §§ 27.001–27.011. For the reasons discussed below, we affirm in part, reverse in part, and remand for further proceedings consistent with this opinion.

Factual and Procedural Background Appellants hired appellee Sunstone Pools & Outdoor Living LLC to renovate their pool and backyard. The parties entered into a construction agreement on May

25, 2023, which outlined each task to be completed and the amount it would cost. The amounts were due at commencement and then after completion of certain tasks. The written agreement did not include a timeframe for completion of each task or of the overall project, nor did it state that time was of the essence. According to appellants, however, Sunstone originally said the project would be completed by July 4, 2023.

Shortly after work commenced on the project, appellants became concerned with the amount of work and quality of work that had been performed. Appellants requested Sunstone to provide a schedule due to their concerns that Sunstone was not diligently completing the project. On June 20, 2023, Sunstone provided a prospective schedule with a project completion date of July 15, 2023, barring any delays by weather. Appellants responded that they “would prefer for the whole project to be completed by 7/14.” Sunstone replied that it would “work hard to finish your project by that date.”

Further delays occurred, as well as continued disputes regarding the quality of work that had been performed. Appellants sent an email to Sunstone emphasizing that Sunstone was yet again behind schedule and that appellants were inclined to not continue with the project or pay for any uncompleted work if the project was not completed by July 14, 2023. Appellants also noted “that to settle any money that needs to be refunded or paid after July 14, 2023, we will be requesting an itemize[d] copy of the cost of material, labor and how [our] money was spent and used that

could also be used as evidence in court through discovery.” In response, Sunstone informed appellants that there was no construction schedule in the agreement that would trigger cancellation of phases of construction or refunds for work not yet completed. Sunstone further responded, “Considering your stated intent and promise to breach our construction agreement signed by you by withholding funds for contracted work based on arbitrary conditions not included in the construction agreement, we have no choice but [to] stop work and pull off the job.” Sunstone also informed appellants that it could “re-commence scheduling labor and materials for your project” if appellants rescinded their “threats to withhold funds based on schedule dates.” Appellants did not rescind their demands, and Sunstone ceased work on the project. Sunstone also denied appellants’ request for an itemization of material costs and labor.

Believing that Sunstone had not completed work for which appellants paid, appellants sought a chargeback of $15,000 for the commencement amount that they paid in early June. After speaking with both parties, the credit card company released the funds to Sunstone. Appellants also posted the following negative public review on Google:

BEWARE: SunStone Pools & Outdoor Living, cancelled an unfinished project via email using a bogus excuse while owing us thousands of dollars and leaving us with an unusable backyard full of rocks, sand, holes, rusted metals, and trash.

The owner, Brad, is refusing to return the money and give us an itemized breakdown of all cost and labor. He has threaten (sic) to

countersue me if I take any legal action and has name dropped his Attorney, A. H., to attempt to intimidate me. Below is a summary and I have a attached a more detail (sic) timeline of events. May 21, 2023.

Agreement. Total Cost $62,950. Verbally discussed with Byron (Sales person) that I needed the project completed July 4th. As of July 5th, I have given SunStone Pools $36,950 and they have only completed $20,550 worth of work.

....

By July 5, I started receiving text and calls that they were having trouble sourcing the travertine that they knew back on June 19 that they had to pre order 3 weeks in advance. That night I sent an official notification to everyone that I needed that project completed by the agreed date of July 14, 2023 as agreed verbally and in writing.

On July 6. Brad sent me an email cancelling the project because according to him, me asking for the project to be completed by the date that was agreed verbally and in writing was “anticipatory breach of contract.”

SunStone Pools stopped work and abandon (sic) the job, so I requested an itemized breakdown of all costs and labor to determine the exact amount owed to us and that any money owed to us be returned by July 10, 2023 end of day. Brad the owner has refused.

I filed a claim with the BBB and his only response was that he cancelled the project because “I promised not to pay” which is lie and I submitted the email as proof.

Appellants posted a similar review on Yelp and submitted a complaint to the Better Business Bureau.

Sunstone posted a response on the Google review explaining that it did not cancel the project but that, instead, appellants sent an email promising not to pay if the job was not finished by July 14. Sunstone further explained that any contractor who was working with someone who created an arbitrary deadline to finish the job

in order to get paid would do the same. Sunstone also alleged that this was just the beginning of appellants’ dishonesty, as appellants had already tried to blame Sunstone for cracks in the plaster. Appellants replied, adding the following statement to their Google review: “His response to this review is a lie. All I want is my money back for a job he cancelled so that I can get someone to clean the mess his company left behind.”

The parties were unable to settle their dispute, and Sunstone filed suit against appellants alleging claims for anticipatory breach of contract, defamation, and business disparagement. Appellants filed a general denial and countersued for claims of breach of implied warranty of good and workmanlike performance, breach of contract, unjust enrichment, and violations of the Texas Deceptive Trade Practices Act (DTPA). See TEX. BUS. & COM. CODE ANN. §§ 17.41–17.63. Appellants also filed a motion to dismiss under the TCPA. See TEX. CIV. PRAC. & REM. CODE § 27.003. In their motion, appellants argued that Sunstone sued them in response to their negative review of Sunstone’s services on Google, which was an exercise of their rights of free speech. Sunstone filed a response and appellants filed a reply. After a hearing, the trial court denied appellant’s motion to dismiss. This expedited interlocutory appeal ensued. See id. §§ 27.008(b), 51.014(a)(12).

On appeal, appellants argue that Sunstone failed to present any admissible evidence in its response to appellants’ motion to dismiss to support its claims. Thus, appellants assert that the trial court erred in denying their motion to dismiss.

Free access — add to your briefcase to read the full text and ask questions with AI

Alma Perales and David Plummer v. Sunstone Pools & Outdoor Living LLC, (Tex. Ct. App. 2024).

Alma Perales and David Plummer v. Sunstone Pools & Outdoor Living LLC (Alma Perales and David Plummer v. Sunstone Pools & Outdoor Living LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related