Alma Perales and David Plummer v. Sunstone Pools & Outdoor Living LLC

CourtCourt of Appeals of Texas
DecidedJuly 17, 2024
Docket05-24-00010-CV
StatusPublished

This text of Alma Perales and David Plummer v. Sunstone Pools & Outdoor Living LLC (Alma Perales and David Plummer v. Sunstone Pools & Outdoor Living LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alma Perales and David Plummer v. Sunstone Pools & Outdoor Living LLC, (Tex. Ct. App. 2024).

Opinion

AFFIRMED in part; REVERSED and RENDERED in part; REMANDED; and Opinion Filed July 17, 2024

S In The Court of Appeals Fifth District of Texas at Dallas No. 05-24-00010-CV

ALMA PERALES AND DAVID PLUMMER, Appellants V. SUNSTONE POOLS & OUTDOOR LIVING LLC, Appellee

On Appeal from the 44th Judicial District Court Dallas County, Texas Trial Court Cause No. DC-23-13419

MEMORANDUM OPINION Before Justices Smith, Miskel, and Breedlove Opinion by Justice Smith

Appellants Alma Perales and David Plummer appeal the trial court’s order

denying their motion to dismiss under the Texas Citizens’ Participation Act (TCPA).

See TEX. CIV. PRAC. & REM. CODE ANN. §§ 27.001–27.011. For the reasons

discussed below, we affirm in part, reverse in part, and remand for further

proceedings consistent with this opinion.

Factual and Procedural Background

Appellants hired appellee Sunstone Pools & Outdoor Living LLC to renovate

their pool and backyard. The parties entered into a construction agreement on May 25, 2023, which outlined each task to be completed and the amount it would cost.

The amounts were due at commencement and then after completion of certain tasks.

The written agreement did not include a timeframe for completion of each task or of

the overall project, nor did it state that time was of the essence. According to

appellants, however, Sunstone originally said the project would be completed by

July 4, 2023.

Shortly after work commenced on the project, appellants became concerned

with the amount of work and quality of work that had been performed. Appellants

requested Sunstone to provide a schedule due to their concerns that Sunstone was

not diligently completing the project. On June 20, 2023, Sunstone provided a

prospective schedule with a project completion date of July 15, 2023, barring any

delays by weather. Appellants responded that they “would prefer for the whole

project to be completed by 7/14.” Sunstone replied that it would “work hard to finish

your project by that date.”

Further delays occurred, as well as continued disputes regarding the quality

of work that had been performed. Appellants sent an email to Sunstone emphasizing

that Sunstone was yet again behind schedule and that appellants were inclined to not

continue with the project or pay for any uncompleted work if the project was not

completed by July 14, 2023. Appellants also noted “that to settle any money that

needs to be refunded or paid after July 14, 2023, we will be requesting an itemize[d]

copy of the cost of material, labor and how [our] money was spent and used that

–2– could also be used as evidence in court through discovery.” In response, Sunstone

informed appellants that there was no construction schedule in the agreement that

would trigger cancellation of phases of construction or refunds for work not yet

completed. Sunstone further responded, “Considering your stated intent and

promise to breach our construction agreement signed by you by withholding funds

for contracted work based on arbitrary conditions not included in the construction

agreement, we have no choice but [to] stop work and pull off the job.” Sunstone

also informed appellants that it could “re-commence scheduling labor and materials

for your project” if appellants rescinded their “threats to withhold funds based on

schedule dates.” Appellants did not rescind their demands, and Sunstone ceased

work on the project. Sunstone also denied appellants’ request for an itemization of

material costs and labor.

Believing that Sunstone had not completed work for which appellants paid,

appellants sought a chargeback of $15,000 for the commencement amount that they

paid in early June. After speaking with both parties, the credit card company

released the funds to Sunstone. Appellants also posted the following negative public

review on Google:

BEWARE: SunStone Pools & Outdoor Living, cancelled an unfinished project via email using a bogus excuse while owing us thousands of dollars and leaving us with an unusable backyard full of rocks, sand, holes, rusted metals, and trash.

The owner, Brad, is refusing to return the money and give us an itemized breakdown of all cost and labor. He has threaten (sic) to

–3– countersue me if I take any legal action and has name dropped his Attorney, A. H., to attempt to intimidate me. Below is a summary and I have a attached a more detail (sic) timeline of events. May 21, 2023. Agreement. Total Cost $62,950. Verbally discussed with Byron (Sales person) that I needed the project completed July 4th. As of July 5th, I have given SunStone Pools $36,950 and they have only completed $20,550 worth of work.

....

By July 5, I started receiving text and calls that they were having trouble sourcing the travertine that they knew back on June 19 that they had to pre order 3 weeks in advance. That night I sent an official notification to everyone that I needed that project completed by the agreed date of July 14, 2023 as agreed verbally and in writing.

On July 6. Brad sent me an email cancelling the project because according to him, me asking for the project to be completed by the date that was agreed verbally and in writing was “anticipatory breach of contract.”

SunStone Pools stopped work and abandon (sic) the job, so I requested an itemized breakdown of all costs and labor to determine the exact amount owed to us and that any money owed to us be returned by July 10, 2023 end of day. Brad the owner has refused.

I filed a claim with the BBB and his only response was that he cancelled the project because “I promised not to pay” which is lie and I submitted the email as proof.

Appellants posted a similar review on Yelp and submitted a complaint to the Better

Business Bureau.

Sunstone posted a response on the Google review explaining that it did not

cancel the project but that, instead, appellants sent an email promising not to pay if

the job was not finished by July 14. Sunstone further explained that any contractor

who was working with someone who created an arbitrary deadline to finish the job

–4– in order to get paid would do the same. Sunstone also alleged that this was just the

beginning of appellants’ dishonesty, as appellants had already tried to blame

Sunstone for cracks in the plaster. Appellants replied, adding the following

statement to their Google review: “His response to this review is a lie. All I want is

my money back for a job he cancelled so that I can get someone to clean the mess

his company left behind.”

The parties were unable to settle their dispute, and Sunstone filed suit against

appellants alleging claims for anticipatory breach of contract, defamation, and

business disparagement. Appellants filed a general denial and countersued for

claims of breach of implied warranty of good and workmanlike performance, breach

of contract, unjust enrichment, and violations of the Texas Deceptive Trade Practices

Act (DTPA). See TEX. BUS. & COM. CODE ANN. §§ 17.41–17.63. Appellants also

filed a motion to dismiss under the TCPA. See TEX. CIV. PRAC. & REM. CODE §

27.003. In their motion, appellants argued that Sunstone sued them in response to

their negative review of Sunstone’s services on Google, which was an exercise of

their rights of free speech. Sunstone filed a response and appellants filed a reply.

After a hearing, the trial court denied appellant’s motion to dismiss. This expedited

interlocutory appeal ensued. See id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Alma Perales and David Plummer v. Sunstone Pools & Outdoor Living LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alma-perales-and-david-plummer-v-sunstone-pools-outdoor-living-llc-texapp-2024.