Allure Metal Works, Inc. v. JRM Constr. Mgt., LLC

2024 NY Slip Op 32538(U)
CourtNew York Supreme Court, New York County
DecidedJuly 23, 2024
DocketIndex No. 154956/2016
StatusUnpublished

This text of 2024 NY Slip Op 32538(U) (Allure Metal Works, Inc. v. JRM Constr. Mgt., LLC) is published on Counsel Stack Legal Research, covering New York Supreme Court, New York County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allure Metal Works, Inc. v. JRM Constr. Mgt., LLC, 2024 NY Slip Op 32538(U) (N.Y. Super. Ct. 2024).

Opinion

Allure Metal Works, Inc. v JRM Constr. Mgt., LLC 2024 NY Slip Op 32538(U) July 23, 2024 Supreme Court, New York County Docket Number: Index No. 154956/2016 Judge: Sabrina Kraus Cases posted with a "30000" identifier, i.e., 2013 NY Slip Op 30001(U), are republished from various New York State and local government sources, including the New York State Unified Court System's eCourts Service. This opinion is uncorrected and not selected for official publication. [FILED: NEW YORK COUNTY CLERK 07/23/2024 12:53 P~ INDEX NO. 154956/2016 NYSCEF DOC. NO. 60 RECEIVED NYSCEF: 07/23/2024

SUPREME COURT OF THE STATE OF NEW YORK NEW YORK COUNTY PRESENT: HON. SABRINA KRAUS PART - - - -57M ----- Justice ------------------------------------------------------------------------------------ X

ALLURE METAL WORKS, INC., INDEX NO. 154956/2016

Plaintiff,

- V -

JRM CONSTRUCTION MANAGEMENT, LLC, ORCA MECHANICAL, INC.,3 COLUMBUS CIRCLE, LLC, VIGILANT INSURANCE COMPANY

Defendants. ------------------------------------------------------------------------------------ X

BACKGROUND

Plaintiff commenced this action seeking sums that were alleged not paid for work done as

a subcontractor on a construction project. This Court held a bench trial on May 14-16, 2024, and

at the conclusion of the trial, the Court reserved decision. For the reasons set forth below, the

Court finds Plaintiff is entitled to judgment against Defendants.

FINDINGS OF FACT

Plaintiff was a subcontractor for ORCA Mechanical, Inc. ("ORCA"). Plaintiff

manufactured and installed HVAC ductwork on the 14th , 16th and 17th floor of the building at 3

Columbus Circle, New York, New York. JRM Construction Management, LLC ("JRM") was

the general contractor for the job. ORCA was a subcontractor to JRM. The building is owned

by 3 Columbus Circle, LLC, and managed by the Moinian Group. Plaintiff filed a mechanic's

lien on May 2, 2016, which was bonded by Vigilant Insurance Company.

OTHER ORDER- NON-MOTION 1 of 5 Page 1 of 5 [* 1] [FILED: NEW YORK COUNTY CLERK 07/23/2024 12:53 P~ INDEX NO. 154956/2016 NYSCEF DOC. NO. 60 RECEIVED NYSCEF: 07/23/2024

The parties entered into an agreement regarding the scope of the work and an agreed

upon price of $225,000.00 (Ex 1). Plaintiff was to manufacture and install ductwork in the

subject premises according to the plans of the architect and the engineer on the job.

Plaintiff prepared shop drawings of the ductwork which were submitted to ORCA.

ORCA submitted the drawings to JRM who submitted them to the architect and the engineer for

approval. There were several rounds of such submissions, and the drawings were finally

approved in March 2015.

Prior to bidding for the job, Mr. Kem and Mr. Kulic went to the site for a walkthrough.

No walls had been constructed and Plaintiff was told that the duct work would go in before the

walls were erected. However, Defendants erected the walls before the installation of the

ductwork which caused delays in the job.

As the work progressed, Plaintiff submitted change orders to ORCA for changes in the

work and material required at the job. The total amount of the change orders submitted were

$157,433.00. Plaintiff performed all of the required work under the contract and the change

orders.

At a meeting between the parties on June 23, 2015, ORCA agreed to pay Plaintiff

$45,098.50 for the change orders. ORCA never made that payment. The total amount paid by

ORCA for the goods and services was $184,500.00. Based on the parties' agreements there is

therefore a balance due to Plaintiff in the amount of $85,598.50.

Plaintiff seeks additional amounts for change orders. Plaintiff acknowledges it has no

signed purchase orders for the additional amounts, but stated they proceeded with the work

without them so as not to delay the job further, and so that the job could be completed.

2 of 5 Page 2 of 5 [* 2] [FILED: NEW YORK COUNTY CLERK 07/23/2024 12:53 P~ INDEX NO. 154956/2016 NYSCEF DOC. NO. 60 RECEIVED NYSCEF: 07/23/2024

In addition to the documents submitted in evidence, the Court heard the testimony of:

Richard Kem, Plaintiffs principal; Benjamin Projansky, from JRM; Edward Kulic, principal of

ORCA, and David Gonzalez, a supervisor on the job for plaintiff. The Court found all the

witnesses credible, except for Mr. Kulic. In particular, the court credits the testimony of David

Gonzlaez that Plaintiffs work was completed in November 2015.

Benjamin Projansky acknowledged that JRM has approved Plaintiff as a subcontractor on

other jobs that took place after the work at Columbus Circle, and that Plaintiff completed the

project at Columbus Circle.

DISCUSSION

Plaintiff established a prima facie case against Defendants. Allure and ORCA had an

agreement to do the work for $225.000. The work was done, and Defendants failed to establish

any claim regarding alleged defects in the work at trial or that they had to pay another company

to finish the work.

The parties agreed to an additional $45,098.50 for the change orders, and while the

additional work was done, that amount was never paid. Although Mr. Kem testified he had only

agreed to accept the lower amount if it was paid within one week, he billed for the lower amount

well after that date and the Court finds he is bound to accept the amount he agreed to.

The first cause of action in Plaintiffs complaint asserts that Plaintiff provided work labor

and services to ORCA at their request and at an agreed price and that ORCA refused to pay.

Both parties at trial agreed that there was a contract for the initial $225,000 and a subsequent

agreed for an amount to be paid by the change orders. Thus, the Court reads the first cause of

action, as pled, as encompassing a cause of action for breach of contract. Assuming arguendo

that the first cause of action did not sufficiently allege the elements of breach of contract the

3 of 5 Page 3 of 5 [* 3] [FILED: NEW YORK COUNTY CLERK 07/23/2024 12:53 P~ INDEX NO. 154956/2016 NYSCEF DOC. NO. 60 RECEIVED NYSCEF: 07/23/2024

Court may sua sponte amend the pleadings to conform to the proof adduced at trial [Rennert

Diana & Co. v Kin Chevrolet, Inc. 137 AD2d 589 (2 nd Dept, 1988); CPLR 30235(c)]. There is no

prejudice in doing so, as Defendant treated the first cause of action as a breach of contract claim

as set forth in Defendant's memorandum of law and asserted a counterclaim for breach of the

contract, which it pursued at trial.

Both parties argue in their post-trial memoranda that there was a contract between the

parties, although they disagree as to who was the breaching party. Both parties also reference a

quantum meruit cause of action as being encompassed in the first cause of action, but, as there

was an agreed price for most of the work the Court does not find same as applicable.

Additionally, to the extent that Plaintiff sued for amounts above what was agreed to be paid, the

Court finds that Plaintiff failed to establish a claim to same at trial.

Defendants second through fifth counterclaims are dismissed. Defendants failed to

establish a prima facie entitlement to relief under same at trial. Defendant failed to prove any

negligence or unworkman like conduct by Defendants. Similarly, it was established at trial that

ORCA has bid on contracts with JRM and there was no evidence that Plaintiffs work on the job

caused ORCA a loss of profits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NDL Associates, Inc. v. Villanova Heights, Inc.
99 A.D.3d 450 (Appellate Division of the Supreme Court of New York, 2012)
Rennert Diana & Co. v. Kin Chevrolet, Inc.
137 A.D.2d 589 (Appellate Division of the Supreme Court of New York, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
2024 NY Slip Op 32538(U), Counsel Stack Legal Research, https://law.counselstack.com/opinion/allure-metal-works-inc-v-jrm-constr-mgt-llc-nysupctnewyork-2024.