Allseas USA, Inc. v. Ps Fabricators, L.L.C. F/K/A Ps Fabricators & Constructors, L.L.C.

Court of Appeals of Texas·Decided December 28, 2012·No. 13-11-00186-CV·Published

Opinion

NUMBER 13-11-00186-CV

COURT OF APPEALS

THIRTEENTH DISTRICT OF TEXAS CORPUS CHRISTI - EDINBURG

ALLSEAS USA, INC., Appellant, v.

PS FABRICATORS, L.L.C. F/K/A PS FABRICATORS & CONSTRUCTORS, L.L.C., Appellee.

On appeal from the 269th District Court of Harris County, Texas.

MEMORANDUM OPINION1

Before Justices Rodriguez, Garza, and Benavides Memorandum Opinion by Justice Rodriguez

1 This case is before the Court on transfer from the Fourteenth Court of Appeals in Houston pursuant to an order issued by the Supreme Court of Texas. See TEX. GOV'T CODE ANN. § 73.001 (West 2005).

In this breach of contract case involving the construction and testing of underwater oil and gas pipeline equipment, appellant Allseas USA, Inc. challenges the jury's verdict in favor of appellee PS Fabricators, L.L.C. f/k/a PS Fabricators & Constructors, L.L.C. (PSF). By three issues, Allseas argues that: (1) the evidence was factually insufficient to support the jury's apparent finding that Allseas did not pay approximately $190,000 in factory acceptance testing charges to PSF; (2) the evidence was factually insufficient to support the total amount of damages awarded in light of PSF's failure to provide adequate documentation of its charges under the contract; and (3) the trial court abused its discretion in denying Allseas's motion for new trial based on newly discovered evidence. In the event the Court sustains its factual sufficiency challenges, Allseas requests that we suggest remittitur of the jury's damages and attorney's fees awards and, in the alternative, remand for a new trial. We affirm.

I. Factual Background

Allseas is in the business of constructing underwater oil and gas pipelines. PSF is a contractor that fabricates the structures that are used in the construction of underwater pipelines. In August 2006, Allseas contracted with PSF to build a series of structures that would be used in Allseas's construction of an underwater pipeline in the Gulf of Mexico for Discovery Producer Services, LLC. 2 Allseas and PSF's contractual relationship was governed by a Master Services Agreement (MSA).

At the end of September 2006, a work order was issued, pursuant to the MSA, for the fabrication of two of the structures—in-line sleds, or ILSs, that were to be installed at

2 Discovery Producer Services, LLC was not a party to the underlying lawsuit or this appeal.

designated points along the pipeline to allow future pipelines to connect to the existing pipeline through a prefabricated valve. At the end of October 2006, the parties executed a variation order, pursuant to the MSA, that governed the fabrication of a third structure—a pipeline end sled, or PLES, which would be installed to connect the pipeline to Discovery's floating production facility.

There were three phases in the fabrication projects. First, PSF fabricated the structures. Second, PSF would run the structures through factory acceptance testing—or FAT—to ensure that the structures performed as designed. Third, PSF would run the structures through system integration testing—or SIT—in which PSF woud attempt to duplicate the seafloor conditions on which the structures would be resting and ensure that the structures, as fabricated, would be able to be installed and function under those conditions.

Under the work and variation orders, which, pursuant to the MSA, set the price schedules, the fabrication work for each structure was to be billed at a set price, and both FAT and SIT were to be billed at cost plus five percent (also known as cost-plus charges). Under the MSA, any invoice containing charges based on costs associated with a rate sheet must be submitted with "appropriate documentation." FAT and SIT were charges based on rate sheet costs, and therefore, the MSA required that any invoice including FAT and SIT costs be supported by appropriate documentation.

PSF began working on the contract in September 2006, with fabrication and then testing continuing through February 2007. Throughout this time period, PSF sent Allseas periodic invoices for the work performed. Allseas paid the invoices through

March 2007 but, at that point, began having questions about the testing charges. 3 PSF revised the questioned invoices and provided Allseas documentation supporting the FAT and SIT cost-plus charges, but ultimately, Allseas was unsatisfied with the documentation PSF provided and refused to make further payments on the invoices.

The final total amount of SIT charges invoiced by PSF was $1,655,053.81; the final total amount of FAT charges invoiced by PSF was $210,924.71. It is undisputed that Allseas paid $768,795.62 in SIT charges; it remains disputed by the parties whether Allseas made any payments for the FAT charges.

II. Procedural Background In May 2008, PSF filed suit against Allseas, alleging that Allseas breached the MSA and associated work orders by failing to pay the invoiced SIT and FAT charges in full. 4 PSF prayed for $886,258.19 in damages for the unpaid SIT charges and $210,924.71 in damages for the unpaid FAT charges. Allseas answered, asserting as an affirmative defense that PSF's invoices did not comply with the parties' agreement as they were not accompanied by the required documentation. Allseas also asserted three counterclaims: breach of contract, alleging that PSF's failure to provide adequate documentation to support its invoices resulted in overpayment by Allseas; fraud, alleging that PSF charged Allseas for costs PSF knew were false; and a request for various declarations regarding the terms of the contract between the parties.

PSF's breach of contract claim and Allseas's breach of contract and fraud

3

The fixed costs for fabrication of the ILSs and PLES, and Allseas's payment of those fixed costs, are not at issue in this case.

4

PSF also alleged claims under the Theft Liability Act and for quantum meruit and unjust enrichment.

counterclaims were tried to a jury August 2-6, 2010. After the close of evidence, the jury was asked, in relevant part: (1) whether Allseas failed to comply with its agreement with PSF, to which the jury answered "yes"; (2) whether Allseas's failure to comply was excused, to which the jury answered "no"; (3) what sum of money would compensate PSF for Allseas's failure to comply, to which the jury answered $316,509 for "SIT-related services" and $88,000 for "FAT-related services"; (4) whether PSF failed to comply with its agreement with Allseas, to which the jury answered "no"; (5) whether PSF committed fraud against Allseas, to which the jury answered "no"; and (6) what a reasonable fee for PSF's attorneys would be, to which the jury answered $254,305. The trial court entered judgment on the jury's verdict, awarding PSF a total of $404,509 in damages, $254,305 in attorney's fees, and prejudgment interest. Allseas filed a motion for new trial, which was denied by the trial court. This appeal followed.

III. Evidence of Damages

By two issues, Allseas argues that the evidence was factually insufficient to support the FAT and SIT damages awarded by the jury. 5 Allseas urges us to suggest remittitur of the amounts awarded by the jury or, in the alternative, remand for a new trial. See TEX. R. APP. P. 46.3. A. Factual Sufficiency and Remittitur of Damages Where there is insufficient evidence to support the full amount of damages awarded but sufficient evidence to support a lesser award, the court of appeals may suggest a remittitur. Bechtel Corp. v. CITGO Products Pipeline Co., 271 S.W.3d 898,

5 Allseas does not challenge the jury's liability findings.

922 (Tex. App.—Austin 2008, no pet.); see TEX. R. APP. P. 46.3. The party prevailing in the trial court should be given the option of accepting the remittitur or having the case remanded for a new trial. Bechtel Corp., 271 S.W.3d at 922.

"Factual sufficiency is the sole remittitur standard for actual damages." Pope v.

Free access — add to your briefcase to read the full text and ask questions with AI

Allseas USA, Inc. v. Ps Fabricators, L.L.C. F/K/A Ps Fabricators & Constructors, L.L.C., (Tex. Ct. App. 2012).

Allseas USA, Inc. v. Ps Fabricators, L.L.C. F/K/A Ps Fabricators & Constructors, L.L.C. (Allseas USA, Inc. v. Ps Fabricators, L.L.C. F/K/A Ps Fabricators & Constructors, L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Waffle House, Inc. v. Williams
313 S.W.3d 796 (Texas Supreme Court, 2010)
Pope v. Moore
711 S.W.2d 622 (Texas Supreme Court, 1986)
Hartford Accident & Indemnity Company v. Gladney
335 S.W.2d 792 (Court of Appeals of Texas, 1960)
Moritz v. Preiss
121 S.W.3d 715 (Texas Supreme Court, 2003)
Jackson v. Van Winkle
660 S.W.2d 807 (Texas Supreme Court, 1983)
Cantu v. Butron
921 S.W.2d 344 (Court of Appeals of Texas, 1996)
In Re O'Connor
92 S.W.3d 446 (Texas Supreme Court, 2002)
First National Bank in Dallas v. Zimmerman
442 S.W.2d 674 (Texas Supreme Court, 1969)
Bechtel Corp. v. CITGO PRODUCTS PIPELINE CO.
271 S.W.3d 898 (Court of Appeals of Texas, 2008)
Missouri Pacific Railroad v. Roberson
25 S.W.3d 251 (Court of Appeals of Texas, 2000)
Ponce v. Sandoval
68 S.W.3d 799 (Court of Appeals of Texas, 2001)
McGalliard v. Kuhlmann
722 S.W.2d 694 (Texas Supreme Court, 1986)
Prati v. New Prime, Inc.
949 S.W.2d 552 (Court of Appeals of Texas, 1997)
In Re Thoma
873 S.W.2d 477 (Texas Supreme Court, 1994)
AMERICANN BANK OF WACO. v. Waco Airmotive, Inc.
818 S.W.2d 163 (Court of Appeals of Texas, 1991)
Thomas v. Oldham
895 S.W.2d 352 (Texas Supreme Court, 1995)
San Antonio Gas Co. v. Singleton
59 S.W. 920 (Court of Appeals of Texas, 1900)