Allison v. Shell Oil Co.

495 N.E.2d 496, 113 Ill. 2d 26, 99 Ill. Dec. 115, 1986 Ill. LEXIS 281
CourtIllinois Supreme Court
DecidedJune 20, 1986
Docket61799, 61834 cons.
StatusPublished
Cited by95 cases

This text of 495 N.E.2d 496 (Allison v. Shell Oil Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allison v. Shell Oil Co., 495 N.E.2d 496, 113 Ill. 2d 26, 99 Ill. Dec. 115, 1986 Ill. LEXIS 281 (Ill. 1986).

Opinion

JUSTICE SIMON

delivered the opinion of the court:

This case presents for decision a question previously left unanswered by this court in Simmons v. Union Electric Co. (1984), 104 Ill. 2d 444, 454, and Heinrich v. Peabody International Cory. (1984), 99 Ill. 2d 344: whether implied indemnity remains a viable theory for shifting the costs of tortious conduct among jointly liable tortfeasors following adoption of “An Act in relation to contribution among joint tortfeasors” (the Act) (Ill. Rev. Stat. 1985, ch. 70, par. 301 et seq.). We note at the outset, however, that the claims for indemnification in this case are not premised upon an underlying action regarding a defective product or the would-be indemnitees’ vicarious liability for the conduct of their indemnitor (see Lowe v. Norfolk & Western Ry. Co. (1984), 124 Ill. App. 3d 80, 97), and we express no opinion on the continued vitality of implied indemnity in those cases. Neither does our opinion in this case affect the validity of explicit undertakings among two or more parties to shift from one party to another the ultimate cost of liability which may arise in favor of a third party.

In August 1979, defendant and third-party plaintiff Shell Oil Company (Shell) contracted with third-party defendant Strange & Coleman, Inc. (Strange & Coleman), for the latter to rebuild a “catcracker” unit at Shell’s Wood River refinery. Pursuant to the terms of their agreement, Strange & Coleman agreed to “furnish all labor, supervision, machinery, equipment, materials and supplies necessary” to rebuild the catcracker while taking responsibility “for all acts and omissions of its subcontractors.”

One such subcontractor, defendant and third-party plaintiff J. J. Wuellner, Inc. (Wuellner), was engaged by Strange & Coleman to provide scaffolding from which Strange & Coleman employees could hot-weld the multistory-tall “cyclone” portion of the catcracker. However, the scaffolding erected by Wuellner left an area of the cyclone inaccessible to Strange & Coleman’s boilermakers who were performing the welding. Strange & Coleman’s employees therefore ran a 2-foot by 12-foot board from the dust collector at the top of the cyclone to Wuellner’s scaffold, from which board the employees could reach the cyclone. Evidence admitted at trial showed the board was not secured to either the cyclone or the scaffold, although there was wire available with which to make it fast.

Kenneth Allison, the plaintiff and a boilermaker for Strange & Coleman, was injured while working atop the board; the board slipped, and both the board and Allison fell. Allison brought suit against Shell and Wuellner, asserting negligence and liability under the Structural Work Act (Ill. Rev. Stat. 1985, ch. 48, par. 60 et seq.). Defendants impleaded Strange & Coleman as a third-party defendant, seeking complete indemnification or, in the alternative, contribution. Prior to trial, Shell, Strange & Coleman and Wuellner entered into a settlement with Allison, and the third-party claims proceeded to trial in the circuit court of Madison County to determine what liability each defendant had for the settlement amount. The jury was instructed on both implied indemnity and contribution, and judgment was entered on the jury’s finding that Shell and Wuellner were entitled to indemnification from Strange & Coleman. On Strange & Coleman’s appeal, the appellate court reversed that judgment, reasoning that contribution had replaced “active-passive” indemnity in this State, and remanded the proceeding for a new trial (133 Ill. App. 3d 607). We allowed the third-party plaintiffs leave to appeal (94 Ill. 2d R. 315).

Implied indemnity has undergone a gradual metamorphosis. At common law, the doctrine evolved as a restitutionary device, a contract implied in law arising from the legal obligation of an indemnitee to satisfy liability caused by actions of his indemnitor. (F. Woodward, Quasi Contracts sec. 259 (1913); cf. 2 W. Blackstone *443 (if one party undertakes to perform business for another party and fails to, by a contract implied in law the one party “shall pay the other party such damages as he has sustained by such *** neglect”).) If, for example, an injured party could hold an employer or property owner vicariously liable for the negligence of an employee or other person, a right of indemnity would be implied in favor of the party liable in law who had not contributed to the injury. (Pfau v. Williamson (1872), 63 Ill. 16; Scott v. Curtis (1909), 195 N.Y. 424, 88 N.E. 794; see Van Slambrouk v. Economy Baler Co. (1985), 105 Ill. 2d 462, 469-70.) Thus, in order to establish a quasi-contractual right of indemnification, the supposed indemnitee would have to show that his liability was merely technical — that he had not acted wrongfully in any degree— and that it arose solely from a pretort relationship by which the supposed indemnitor impliedly promised to indemnify. See Nelson v. Cook (1856), 17 Ill. 443.

With the growth of tort liability for negligent acts, the doctrine of implied indemnity was extended in response to the rule in Merryweather v. Nixan (K.B. 1799), 101 Eng. Rep. 1337, 8 Term R. 186, which prohibited contribution among jointly negligent tortfeasors (e.g., Consolidated Ice Machine Co. v. Keifer (1890), 134 Ill. 481). The rule against contribution, harsh enough in cases where both tortfeasors were in pari delicto, was even harsher where the difference in relative degrees of fault was so great that the negligence of one tortfeasor could be labeled “primary” in relation to the “secondary” negligence of the other. (See generally Heinrich v. Peabody International Corp. (1985), 139 Ill. App. 3d 289, 291-92.) This court first indicated the possibility of relief for the less negligent party in John Griffiths & Son Co. v. National Fireproofing Co. (1923), 310 Ill. 331, 338-39 (upholding an express contract for indemnity):

“Where one [of two persons] is only passively negligent but is exposed to liability through the positive acts and actual negligence of the other, the parties are not in equal fault as to each other though both are equally liable to the injured person. *** [T]he ultimate loss may be visited upon the principal wrongdoer, who is made to respond for all the damages, where one less culpable, although legally liable to third persons, may escape the payment of damages assessed against him by putting the ultimate loss upon the one principally responsible for the injury done.”

Relying upon that dictum in the Griffiths case and adopting the doctrine of “active-passive negligence,” our appellate court recognized a right of “equitable” implied indemnity based upon the relative fault of the parties (see generally Skinner v. Reed-Prentice Division Package Machinery Co. (1977), 70 Ill. 2d 1, 11) where the relationship between legally liable parties did not impose vicarious liability upon the indemnitee or imply a promise to indemnify by the indemnitor (Gulf, Mobile & Ohio R.R. Co. v. Arthur Dixon Transfer Co. (1951), 343 Ill. App. 148). The movement of implied indemnity off its quasi-contractual foundation was completed in Reynolds v. Illinois Bell Telephone Co. (1964), 51 Ill. App. 2d 334, and Sargent v. Interstate Bakeries, Inc. (1967), 86 Ill. App. 2d 187. Recognizing that “[a]t common law the cases in which indemnity was allowed involved a defendant held liable without personal fault” (Sargent v. Interstate Bakeries, Inc. (1967), 86 Ill. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jordan v. Jewel Food Stores, Inc.
83 F. Supp. 3d 761 (N.D. Illinois, 2015)
Madden v. Anton Antonov & AV Transportation, Inc.
966 F. Supp. 2d 851 (D. Nebraska, 2013)
Uldrych v. VHS of Illinois, Inc.
927 N.E.2d 82 (Appellate Court of Illinois, 2010)
Marion Hospital Corp. v. Sterling Emergency Services of Illinois, Inc.
913 N.E.2d 140 (Appellate Court of Illinois, 2009)
Travelers Casualty & Surety Co. v. Bowman
893 N.E.2d 583 (Illinois Supreme Court, 2008)
Alberto-Culver Co. v. Aon Corp.
812 N.E.2d 369 (Appellate Court of Illinois, 2004)
Ciccone v. Dominick's Finer Foods, Inc.
731 N.E.2d 312 (Appellate Court of Illinois, 2000)
Franklin v. Morrison
711 A.2d 177 (Court of Appeals of Maryland, 1998)
Ganci v. Blauvelt
690 N.E.2d 649 (Appellate Court of Illinois, 1998)
Freislinger v. Emro Propane Co.
99 F.3d 1412 (Seventh Circuit, 1996)
Kerschner v. Weiss & Co.
667 N.E.2d 1351 (Appellate Court of Illinois, 1996)
Solich v. PORTES CANCER PREVENTION CENT.
652 N.E.2d 1211 (Appellate Court of Illinois, 1995)
Solich v. George & Anna Portes Cancer Prevention Center of Chicago, Inc.
273 Ill. App. 3d 977 (Appellate Court of Illinois, 1995)
Amrep Southwest, Inc. v. Shollenbarger Wood Treating, Inc.
893 P.2d 438 (New Mexico Supreme Court, 1995)
Ziarko v. Soo Line Railroad
641 N.E.2d 402 (Illinois Supreme Court, 1994)
Industrial Color, Inc. v. C P Inorganics, Inc.
244 Ill. App. 3d 436 (Appellate Court of Illinois, 1993)
Hahn v. Norfolk & Western Railway Co.
608 N.E.2d 683 (Appellate Court of Illinois, 1993)
Pfaff v. Chrysler Corp.
610 N.E.2d 51 (Illinois Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
495 N.E.2d 496, 113 Ill. 2d 26, 99 Ill. Dec. 115, 1986 Ill. LEXIS 281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allison-v-shell-oil-co-ill-1986.