Allington & Curtis Manufacturing Co. v. Detroit Reduction Co.

95 N.W. 562, 133 Mich. 427, 1903 Mich. LEXIS 523
CourtMichigan Supreme Court
DecidedJune 23, 1903
DocketDocket No. 45.
StatusPublished
Cited by1 cases

This text of 95 N.W. 562 (Allington & Curtis Manufacturing Co. v. Detroit Reduction Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allington & Curtis Manufacturing Co. v. Detroit Reduction Co., 95 N.W. 562, 133 Mich. 427, 1903 Mich. LEXIS 523 (Mich. 1903).

Opinion

Hooker, C. J.

The plaintiff contracted with the defend-. ant to manufacture and deliver certain machinery for collecting the product from its ore pulverizers in use at Cripple Creek, or, to state it more accurately in the language of the contract:

“ The contractor is to furnish all of the sheet-metal material and iron hangers for pipes, dust collectors, centrifugal traps, grading chambers, valves, and fans, in manufactured state, for two complete dust-collecting systems, to be connected to your two pulverizers. The systems to be of the return type, which is practically dustless, and to be substantially like pencil sketch submitted for approval. All of the material, except the fans,, is sold f. o. b. cars Saginaw, Mich., and the fans, which are to be No. 10 Sturtevant Monogram pattern, are furnished f. o. b. cars Boston. All of the sheet-steel work is to be of No. 16 gauge galvanized steel, except the first joints in the delivery from the pulverizers, which is to be 13 gauge. The contractors are to furnish a mechanic to superintend and help install the plant, and all other labor is to be furnished by the purchaser .-
“The'- contractor is to design the working drawings for constructing and installing the system, and guarantees that each plant will convey all of the material pulverized to a fineness of 100 mesh and finer, and catch the greater bulk of the same in the centrifugal trap interposed between the pulverizer and the fan, thus saving wear and tear on the fan. The contractor further guarantees that the greater portion of the remainder of the material which passes through the fan will be caught in the dust collector, from which the air is finally returned to the pulverizer. A small portion of the volume of air will be allowed to escape from the dust collector to a small supplemental collector, to compensate for a small amount of fresh air continually taken into the pulverizer.
*430 “ Each pipe leading from the delivery of the pulverizers is to be supplied with an enlarged grading chamber, which is to be adjustable so as to prevent particles coarser than 100 mesh from passing through and into the pipe system.
‘ ‘ The purchaser is to prepare return openings 12" in diameter or an equivalent. On each side of each pulverizer the return pipes for the air are to be attached to these openings. The purchaser is to drive the fans to the required speed for handling the material, and pay the contractor eighteen hundred dollars for the fans and material furnished f. o. b. cars Boston and Saginaw, and pay the railroad fare, board, and $4.00 per day for mechanic’s time. The contractor is to furnish material for soldering, riveting, etc., and the purchaser is to furnish scaffolding and permanent supports for heavy parts. Payments are to be made to the contractor as follows: One-third on delivery of material, one-third when system is installed, and one-third thirty days after installation. Shipment to be made within two weeks.”

At the time this contract was negotiated, blue prints of defendant’s pulverizers were furnished to the plaintiff. The apparatus was duly received at Cripple Creek, and set up under the supervision of plaintiff’s expert. According to the defendant’s claim, repeated experiments, both by the expert while there and by defendant after his departure, failed to make the apparatus do the work as guaranteed. Being sued for the contract price, the defendant set up the warranties, and sought to recoup damages for a failure to perform the contract. A verdict was rendered for the plaintiff, and defendant has appealed.

The defendant was in the possession of' two ore pulverizers when it made its contract, as the contract shows. It sought to have the product of the pulverizers conveyed from them, and to that end the parties made the contract. The alleged warranties were; “(1) that each plant will convey all of the material pulverized to a fineness of 100 mesh and finer;” (2) that it will “catch the greater bulk of the same in the centrifugal trap interposed between the pulverizer and the fan, thus saving wear and tear on the fan;” (3) that “each pipe leading from the delivery of the *431 pulverizers is to be supplied with an enlarged grading chamber, which is to be adjustable so as to prevent particles coarser than 100 mesh from- passing through and into the pipe system.” It also provided that' “the contractor is to furnish all of the sheet-metal material and iron hangers for pipes, dust collectors, centrifugal traps, grading chambers, valves, and fans, in manufactured state, for two complete dust-collecting systems, to be connected to your two pulverizers,” as already stated.

The apparatus was shipped to, and arrived at, Independence, Colo. The defendant asserts that it was not shipped in a manufactured state, for the reason that the joints of pipe were not riveted together, and complains of the charge, in which the jury were told that the contract was complied with in that" particular. The testimony of the plaintiff showed that it followed the usual practice of its factory in "this respect, and, this being uncontradicted, we think the judge committed no error in his charge. He might have said to the jury that the contract contemplated the “manufactured condition” adopted by the plaintiff in its business. There was no testimony showing that such pipes were shipped by other factories in any other condition, if it would have been pertinent.

One of defendant’s witnesses testified that he had experience as a manufacturer of sheet iron, and it was the uniform custom to ship smokestacks in car lengths, joints being riveted. On cross-examination, counsel drew from him that he had experience in the manufacture of sheet iron in a Michigan institution. He was asked what had become of the institution, and, upon objection being made, •counsel stated to the court, in the presence of the jury:

“In connection with this, I offer to show by the cross-examination of this witness, who is testifying as‘an expert on this business, as he has testified, that he was the purchasing.and the selling agent <3f that company. I propose to show that that company was wrecked by his management, and became insolvent; that the Lansing Lumber Company and the Capitol Lumber Company were wrecked by *432 him; and that every institution with which he has become connected since he was in business has been wrecked and ruined, — for the purpose of testing his expert knowledge in any or all business. ”

The court sustained the objection. We think this statement not a sufficient cause for reversing the judgment.

Defendant’s counsel claim that the court erred in his charge upon the subject of the warranties. It is truly said that a failure to install machinery which should both convey and separate the grades of ore would be a breach of the warranty, and, if the instruction was that a failure to both convey and separate was essential to a breach, it was error. In our opinion, however, the charge is not open to such a construction, for it clearly states that a failure to do both was a breach of the warranty. It is clear that a failure to do one is a failure to do both, in the sense meant, and doubtless understood.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garey v. Kelvinator Corp.
271 N.W. 723 (Michigan Supreme Court, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
95 N.W. 562, 133 Mich. 427, 1903 Mich. LEXIS 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allington-curtis-manufacturing-co-v-detroit-reduction-co-mich-1903.