Allied Tile Co. v. Miller-Stauch Construction Co.

743 S.W.2d 542, 1987 Mo. App. LEXIS 5001
CourtMissouri Court of Appeals
DecidedDecember 8, 1987
DocketNo. WD 39179
StatusPublished

This text of 743 S.W.2d 542 (Allied Tile Co. v. Miller-Stauch Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Tile Co. v. Miller-Stauch Construction Co., 743 S.W.2d 542, 1987 Mo. App. LEXIS 5001 (Mo. Ct. App. 1987).

Opinion

MANFORD, Judge.

This is a civil action seeking damages for breach of an oral contract. The judgment is reversed and the cause remanded.

Appellant has presented several alleged errors, but due to the disposition herein, only a single issue is considered. Appellant charges the trial court erred in admitting into evidence a written form of subcontract with the cancellation clause of said contract excised therefrom when said contract was admitted as proof of a preexisting oral contract.

The record reveals the following pertinent facts:

Appellant, Miller-Stauch Construction Company, Inc. (hereinafter Miller-Stauch) was original defendant at trial. Respondent, Allied Tile Company (hereinafter Allied) was original plaintiff at trial. Miller-Stauch was the general contractor for the construction of a building project, commonly known as Bankers Square, located in Overland Park, Kansas. Allied was a proposed tile subcontractor on the same project. Allied claims that the parties entered into an oral agreement on March 26, 1984 for the supply and installation of tile by Allied on the various building structures. The claim of a contract, of course, is denied by Miller-Stauch.

The area to be tile-covered included some 53,000 square feet of exterior tile, requiring the utilization of scaffolding to a height of six building stories. Miller-Stauch secured the bid as the general contractor and in turn gave notice to various subcontractors for bids regarding different phases of the work. Allied is a tile installation company and submitted its bid by telephone to Miller-Stauch on March 6, 1984.

David Bray of Allied testified, in summary, to the following:

Pursuant to submitting its bid, Allied secured the plans and specifications for the tile work. The plans and specifications detailed the technique of application, location of tile, and materials to be used. As noted above, Allied submitted its bid by telephone (not an uncommon practice) to Miller-Stauch on March 6, 1984, and agreed to do the work and supply the tile for $529,-100.00. The bid had two formats referenced alternate one and alternate two. For alternate two, the $529,100.00 sum was modified by $7,950.00. The bid provided that caulking was excluded and that an underlay coating called “brown coat” was included. By telephone, Bray was contacted by Bill Dean, President of Miller-Stauch, shortly after the bid by Allied was submitted. Bill Dean sought assurance from Allied that Allied could supply the necessary material and labor force, and have the tile work completed by late December, 1984. Allied assured'Dean that it could meet these requests.

On March 19 or 20, 1984, Gene Dean called David Bray to inquire if certain modifications to the plans and specifications would affect Allied’s bid. Bray assured Dean that the modifications would not change the bid and on March 21, 1984,-Allied sent adjusted calculations to Miller-Stauch. On March 26, 1984, Bill Dean of Miller-Stauch called Allied to determine whether Allied could secure the tile from a foreign manufacturer in time to meet the [544]*544construction deadline. Bray advised Bill Dean that a firm order would have to be placed with the manufacturer. During this conversation, according to Bray, he (Bray) asked if Allied was going to get the job and Bill Dean advised that Allied had the job and that Miller-Stauch would issue a written contract. Later the same day, Allied placed a tentative order for 53,200 square feet of tile. On this same date, Allied undertook other actions relative to the tile orders and samples. Correspondingly, on March 26, 1984, Miller-Stauch sent a letter to Allied requesting a break-out or breakdown of tile costs per building for each of the five buildings in the project.

In response to this letter, Allied forwarded break-out cost listing to Miller-Stauch on April 2,1984. On April 11,1984, Miller-Stauch forwarded to Allied a letter stating that the architects had approved the tile samples forwarded previously by Allied. On April 16, 1984, Allied, represented by Bray, participated in a meeting to discuss work scheduling. At this meeting, Bray was asked if Allied could obtain a performance bond. In addition, discussion was held regarding the scheduling of the tile work, savings which might be made by using alternative installation procedures, the plastering work, the scope and extent of caulking to be provided by Allied, and storage of the tile on the job location. At this same meeting, Bray asked if Miller-Stauch would be willing to place a $10,-000.00 deposit on the tile as per the request of the tile supplier. Allied denied that the foregoing matters discussed were demands (except the deposit) by Miller-Stauch.

On April 19, 1984, Gene Dean of Miller-Stauch called Bray and requested a performance bond of Allied. In turn, Bray requested a copy of the subcontract agreement to send to his bonding company. On April 20, 1984, Allied received the subcontract agreement, which was unsigned. The agreement reflected the terms provided in Allied’s original bid. Allied secured the required bond. On the same date (April 20, 1984), Miller-Stauch sent a letter to all subcontractors, stating there would be mandatory weekly job meetings. Allied received a copy of the letter. On April 30, 1984, after unsuccessful attempts to contact Gene Dean, Bray reached him and Dean advised Bray that Allied was not going to be used on the project. Allied subsequently received a letter, advising that it would not be used as the tile subcontractor. The letter stated that although Allied and Miller-Stauch had been negotiating, no formal agreement had been reached. On behalf of Allied, Bray can-celled the tile orders. Allied had some 60 hours of time involved, but no other actual out-of-pocket expenses.

This action commenced, seeking recovery of anticipated profits from the contract. Allied produced an expert, who testified that its profits from the $529,100.00 contract would have been $163,221.00. Before trial, Allied secured an order from the trial court permitting Allied to introduce the written subcontract agreement to prove Allied’s claim of an oral contract as of March 26, 1984, but with a portion of the agreement removed. The written agreement bore a date of April 10,1984. The removed portion was a cancellation provision which reads as follows:

XXVIII. Cancellation: The Contractor, by written notice executed by an Officer, shall have the right to terminate and cancel this Contract, without the Subcontractor being at fault, for any cause or for its own convenience, and require the Subcontractor to immediately stop work. In such event, the Contractor shall pay the Subcontractor for that work actually performed in an amount proportionate to this Contract price. The Contractor shall not be liable to the Subcontractor for any other costs, including prospective profits on work not performed. However, if the reason for the termination and cancellation of this Contract is due to any default or action by the Principal, A/E or as a result of Court Order or public authority, then the Contractor shall not be liable to the Subcontractor for any sum greater than that which the Contractor receives from the Principal on behalf of the Subcontractor’s performance less any costs incurred by the Contractor.

[545]*545Miller-Stauch opposed introduction of the above-agreement without the cancellation provision. At each occasion, Miller-Stauch’s position was denied. The agreement was introduced without the above term being included, over the objection of Miller-Stauch.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. Matthey Laundry & Dry Cleaning Company
350 S.W.2d 786 (Supreme Court of Missouri, 1961)
Sapp v. Key
287 S.W.2d 775 (Supreme Court of Missouri, 1956)
O'Laughlin v. Barstow
654 S.W.2d 95 (Missouri Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
743 S.W.2d 542, 1987 Mo. App. LEXIS 5001, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-tile-co-v-miller-stauch-construction-co-moctapp-1987.