Allied Erecting v. U.S. Steel Corp.

Court of Appeals for the Sixth Circuit·Decided May 12, 2020·No. 19-3326·Unpublished

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 20a0266n.06

No. 19-3326

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT FILED May 12, 2020

DEBORAH S. HUNT, Clerk

ALLIED ERECTING AND DISMANTLING ) CO., INC., )

) ON APPEAL FROM THE Plaintiff–Appellant, ) UNITED STATES DISTRICT ) COURT FOR THE NORTHERN v. ) DISTRICT OF OHIO )

UNITED STATES STEEL CORPORATION, )

) OPINION

Defendant–Appellee. )

)

BEFORE: MERRITT, MOORE, and BUSH, Circuit Judges.

KAREN NELSON MOORE, Circuit Judge. This complex contractual dispute is rooted in a decades-long fight between Allied Erecting and Dismantling Company, Inc. (“Allied”) and United States Steel Corporation (“U.S. Steel”) over dismantling work Allied performed (or, in some cases, did not perform) at a defunct U.S. Steel steelmaking plant in eastern Pennsylvania (“Fairless”). The dispute culminated in a three-week jury trial in 2015, which in turn resulted in a $10.7 million judgment in U.S. Steel’s favor.

Two years ago, we issued an opinion affirming that judgment in substantial part. See Allied Erecting & Dismantling Co. v. U.S. Steel Corp., 726 F. App’x 279 (6th Cir. 2018) (“Allied I”). In that decision, however, we left open one question for the district court to resolve on remand: whether two of Allied’s breach of contract claims—“count IV” and “count V” of Allied’s complaint, which, we concluded, the district court had erroneously dismissed on statute of limitations grounds—could be resolved by the court as a matter of law, or whether the underlying

factual disputes were sufficiently material such that another jury trial would be needed to address them. The district court thought no genuine disputes of material fact existed and so it granted U.S. Steel judgment as a matter of law (“JMOL”) on both counts. Allied again appealed.

We are sympathetic to the district court’s desire to bring this case to an end. As noted above, this complex commercial litigation has lasted literally decades, and has already resulted in one time-consuming jury trial (and one remand after appeal). But sometimes the law and efficiency are not on the same team. And, in our view, the law in this case requires that we do the inefficient thing. That is, that we REVERSE the district court’s grant of JMOL and REMAND— again—so that the court can conduct a new trial on Allied’s two remaining claims.

I. BACKGROUND

Because we have reviewed this case’s background once before, in this decision we focus on only those facts relevant to the parties’ present dispute.

A.

There are two contracts at issue. They are long and complicated in the abstract. But when one focuses on just the provisions pertinent to this appeal, it quickly becomes apparent that the material exchange is a simple one: Allied dismantles U.S. Steel’s Fairless plant at essentially no cost, and, in return, U.S. Steel lets Allied keep and sell the scrap metal generated by that dismantling work.

First, there is the parties’ 1992 construction contract (which concerned dismantling work to be performed at the “hot end” of the Fairless plant1 and which the parties refer to as the

1 This litigation concerns dismantling work to be performed at the “cold end” of the plant, by contrast. But the distinction is immaterial for present purposes.

“1992 Specification”). In this contract, U.S. Steel promised Allied that, after it (U.S. Steel) completed asbestos removal at any Fairless facility it intended to dismantle, it would “assign to [Allied] ownership of [that] facility,” R.269-2 (1992 Specification § 5.2) (Page ID #18069), in exchange for just one dollar, id. § 8.1 (Page ID #18084). And, the contract continued, this assignment of ownership would include, among other materials, (a) “[a]ll ferrous and non-ferrous scrap resulting from the dismantling work,” (b) “[a]ll ferrous and non-ferrous scrap located within each dismantling area,” and (c) “[r]ailroad track located within a specific dismantling area which exclusively serves that dismantling area.” Id. §§ 5.2.1, 5.2.2, 5.2.5 (Page ID #18069–70). Moreover, the contract noted near its conclusion, although U.S. Steel could not “remove any complete facility from the scope of this Specification” after Allied commenced work at that facility, U.S. Steel could remove “a building” from Allied’s scope of work, so long as U.S. Steel paid Allied “50% of the ‘Scrap Value.’” Id. §§ 10.2, 10.3 (Page ID #18084).

Second, there is the 2003 settlement agreement between the parties (the “2003 AIP”), which built upon the 1992 Specification. In this contract, U.S. Steel promised Allied that “[a]ny further dismantling work” that needed to be done at the Fairless plant (and that U.S. Steel had “released and authorized in writing for dismantling”) would “be awarded to and performed by [Allied]” pursuant to “the same relevant terms and conditions contained in” the 1992 Specification. R.269-4 (2003 AIP § III) (Page ID #18108). Indeed, just like in the 1992 Specification, this agreement stated explicitly, “[Allied] will own all ferrous and non-ferrous scrap generated on any projects awarded to [it].” Id. § II(B)(7) (Page ID #18107). And in exchange for all this, the agreement concluded, Allied would conduct its dismantling free of charge. See id. § III (Page ID #18108) (“[S]uch dismantling shall be at no cost to U.S. Steel. . . .”).

B.

We now turn to Allied’s two breach of contract claims, and the evidence it adduced at trial in support of those claims.

First, there is Allied’s breach of contract count IV. Here, Allied alleges that U.S. Steel removed certain buildings from the scope of Allied’s dismantling work without compensating Allied for the buildings’ scrap value, thus violating the 1992 Specification’s removal compensation provision. See R.43 (2d Am. Compl.) (Page ID #549–51). And, as evidence of this breach, Allied points to the following trial testimony and documentation:

(1) In 2004, U.S. Steel “released and authorized” the Fairless plant’s “Tin and Sheet” facility for dismantling (thus awarding that facility to Allied under the 2003 AIP), see, e.g., R.274 (Trial Tr.) (Page ID #18768–77);

(2) Shortly thereafter, Allied commenced work at the Tin and Sheet facility (thus satisfying the removal compensation provision’s precondition for compensation), see, e.g., id. at Page ID #18857, 18868;

(3) during or after June 2008,2 U.S. Steel removed from Allied’s scope of dismantling work certain buildings within the Tin and Sheet facility, see, e.g., Allied I, 726 F. App’x at 285 (collecting record citations);

(4) U.S. Steel failed to pay Allied 50% of the removed buildings’ “Scrap Value,”

in violation of the 1992 Specification’s removal compensation provision, see, e.g., R.274 (Trial Tr.) (Page ID #18868–69); and (5) this breach caused Allied to suffer damages, see, e.g., R.280 (Trial Tr.) (Page ID #20558–61).

2 Why “June 2008”? Because, in our prior decision, we emphasized that the only reason U.S. Steel was not entitled to JMOL on Allied’s breach of contract counts IV and V (whereas U.S. Steel was so entitled on Allied’s other contract claim) was that “Allied introduced evidence that could lead a reasonable factfinder to conclude that U.S. Steel” breached the contractual provisions at issue in counts IV and V “within the four-year period preceding Allied’s filing of its June 2012 complaint,” i.e., within the relevant Pennsylvania statute of limitations. Allied I, 726 F. App’x at 285. Thus, if Allied rested its contract claims on breaches that occurred before June 2008, that would contradict our prior ruling.

Second, there is Allied’s (distinct but similar) breach of contract count V. Here, Allied more broadly alleges that U.S. Steel refused to let Allied remove any scrap or railroad track from the Tin and Sheet facility—all of which Allied supposedly owned—thus violating the 1992 Specification’s assignment of ownership provision. See R.43 (2d Am. Compl.) (Page ID #551– 53). And, as evidence of this breach, Allied points to the following trial testimony and documentation:

Free access — add to your briefcase to read the full text and ask questions with AI

Allied Erecting v. U.S. Steel Corp., (6th Cir. 2020).

Allied Erecting v. U.S. Steel Corp. (Allied Erecting v. U.S. Steel Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related