Allied Erecting & Dismantiling Co., Inc. v. Ohio Edison Co.

2011 Ohio 2627
CourtOhio Court of Appeals
DecidedMay 26, 2011
Docket10-MA-25
StatusPublished
Cited by3 cases

This text of 2011 Ohio 2627 (Allied Erecting & Dismantiling Co., Inc. v. Ohio Edison Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Erecting & Dismantiling Co., Inc. v. Ohio Edison Co., 2011 Ohio 2627 (Ohio Ct. App. 2011).

Opinion

[Cite as Allied Erecting & Dismantiling Co., Inc. v. Ohio Edison Co., 2011-Ohio-2627.] STATE OF OHIO, MAHONING COUNTY

IN THE COURT OF APPEALS

SEVENTH DISTRICT

ALLIED ERECTING AND DISMANTLING ) CO., INC., et al., ) ) PLAINTIFFS-APPELLANTS, ) ) CASE NO. 10-MA-25 V. ) ) OPINION OHIO EDISON COMPANY, ) ) DEFENDANT-APPELLEE. )

CHARACTER OF PROCEEDINGS: Civil Appeal from Court of Common Pleas of Mahoning County, Ohio Case No. 06CV3604

JUDGMENT: Affirmed

APPEARANCES: For Plaintiffs-Appellants Attorney F. Timothy Grieco Attorney Timothy D. Berkebile 44th Floor, 600 Grant Street Pittsburgh, PA 15219

Attorney Kevin L. Bradford Attorney Jay M. Skolnick Attorney Peter B. Grinstein Attorney Kathryn A. Vadas 20 West Federal St., Suite 600 Youngstown, Ohio 44503-1423

For Defendant-Appellee Attorney John T. Dellick P.O. Box 6077 Youngstown, Ohio 44501-6077 JUDGES:

Hon. Gene Donofrio Hon. Joseph J. Vukovich Hon. Mary DeGenaro

Dated: May 26, 2011 [Cite as Allied Erecting & Dismantiling Co., Inc. v. Ohio Edison Co., 2011-Ohio-2627.] DONOFRIO, J.

{¶1} Plaintiffs-appellants Allied Erecting and Dismantling Company, Inc. (AED) and Allied Gator, Inc. (Allied Gator) (collectively Allied) appeal a Mahoning County Common Pleas Court decision awarding a balance due on a contract Allied had with defendant-appellee Ohio Edison Company (Ohio Edison). {¶2} In early 2006, Allied sought to expand its manufacturing facility. That expansion would require an increase in the power needed for the facility which in turn would require the building of an electrical substation with two transformers. {¶3} On April 21, 2006, representatives from Allied and Ohio Edison met to discuss construction of the substation and the acquisition of two transformers. Allied was represented by its president, John Ramun, as well as Ed Klein, an electrical draftsman, and Jim Feuse, an engineer for Allied. Ohio Edison was represented by Lisa Nentwick, Senior Account Manager, and John Podnar. According to Ramun, Nentwick and Podnar agreed that Ohio Edison would provide the main substation design, supply electrical components, and solicit and receive bids for the construction of the substation. A cost plus fifteen percent was discussed as the cost of the project. {¶4} On May 1, 2006, Nentwick sent Ramun a written contract for the design and procurement of the two transformers required for the substation. Attorneys for both Ohio Edison and Allied reviewed the contract and negotiations followed. By the time Ramun signed the contract on May 8, 2006, the price for the transformers was $833,657.52. {¶5} In August 2006, representatives of Allied and Ohio Edison met again to discuss construction of the substation. Ohio Edison indicated that the mark-up was going to have to be twenty-seven percent, not the fifteen percent discussed in April. Allied objected to the pricing and further discussions for the design and construction of the substation ended. {¶6} On September 14, 2006, Allied sued Ohio Edison for specific performance and an accounting. Allied alleged that the April 21, 2006 discussions between representatives from both Ohio Edison and Allied resulted in an agreement -2-

for Ohio Edison to design and build Allied an electrical substation, including the procurement of two transformers for the substation. In the weeks following the filing of the complaint, the parties attempted to conciliate the dispute and Ohio Edison produced documents pertaining to the design of the substation. According to Allied, this caused a delay in Allied constructing the substation thus requiring it to store the two transformers. {¶7} As a result, Allied filed an amended complaint on May 18, 2007, setting forth two counts. The first count was for an accounting to determine Ohio Edison’s actual costs in purchasing the two transformers. Due to the alleged breach of the alleged agreement to design and build the substation, Allied contends Ohio Edison should not be allowed to profit from the mark-up of the transformers. The second count was for breach of what Allied perceived was a contract that resulted from the April 21, 2006 meeting. {¶8} Ohio Edison filed an answer and two counterclaims. The first count of the counterclaim sought declaratory judgment that no agreement had been reached between Allied and Ohio Edison for Ohio Edison to design and build the substation. Ohio Edison alleged that it performed only preliminary conceptual work to enable Ohio Edison to begin pricing the substation design and construction. The second counterclaim was for breach of the written contract between Ohio Edison and Allied for Ohio Edison to obtain the two transformers. Ohio Edison contended that there was a balance due on the transformers of $166,731.50 plus interest. {¶9} On August 20, 2009, Ohio Edison filed a motion for partial summary judgment. On November 5, 2009, a magistrate sustained the motion in part and overruled it in part. The magistrate found that the contract between Ohio Edison and Allied regarding the acquisition of the two transformers was clear, unambiguous, and susceptible of only one interpretation. The magistrate noted that the contract contained no reference that it was contingent upon any other condition or agreement. Therefore, the magistrate concluded that parol evidence was inadmissible to vary or otherwise contradict that contract. Consequently, the magistrate ordered Allied to -3-

pay the balance remaining due on the transformers. However, the magistrate did find that there were genuine issues of material fact concerning whether the parties entered into an enforceable oral contract to design and build the substation. Following a premature appeal to this court and the subsequent denial of Allied’s objections to the magistrate’s decision, this timely appeal followed. {¶10} Allied advances three assignments of error. Allied’s first assignment of error states: {¶11} “The trial court committed reversible error when it granted Defendant- Appellee’s Motion for Partial Summary Judgment and found that parol evidence of the April 21, 2006 Oral Contract, was inadmissible to demonstrate that the Written Transformer Contract was a part of the overarching April 21, 2006 Oral Contract.” {¶12} The thrust of Allied’s argument on appeal is that the transformer contract was part of an overarching agreement to design and build a substation which was orally agreed upon at the April 21, 2006 meeting. Allied believes parol evidence of the April 21, 2006 discussions should have been allowed to have been admitted to establish this overarching agreement. Ohio Edison views the transformer contract and the April 21, 2006 discussions separately. It views the transformer contract as a wholly integrated contract upon which Allied has not fully paid the balance due and the April 21, 2006 discussions as evidence it performed only preliminary conceptual work to enable Ohio Edison to begin pricing the substation design and construction. It contends any discussions that occurred at the April 21, 2006 meeting are barred by the parol evidence rule to vary or alter the terms of the transformers contract. {¶13} “The parol-evidence rule is a principle of common law providing that ‘a writing intended by the parties to be a final embodiment of their agreement cannot be modified by evidence of earlier or contemporaneous agreements that might add to, vary, or contradict the writing.’ Black’s Law Dictionary (8th Ed.2004) 1149; see, also, Galmish v. Cicchini (2000), 90 Ohio St.3d 22, 26, 734 N.E.2d 782, quoting 11 Williston on Contracts (4th Ed.1999) 569-570, Section 33:4. The rule ‘operates to -4-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clay v. Schriver Allison Courtley Co.
2018 Ohio 3371 (Ohio Court of Appeals, 2018)
Robinson v. Vanex Tube Corp.
2016 Ohio 268 (Ohio Court of Appeals, 2016)
Hugenberg v. Huntington Bancshares, Inc.
2012 Ohio 3344 (Ohio Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ohio 2627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-erecting-dismantiling-co-inc-v-ohio-edison--ohioctapp-2011.