Alliant Energy Corp. v. Federal Energy Regulatory Commission

253 F.3d 748, 347 U.S. App. D.C. 35, 2001 U.S. App. LEXIS 13500, 2001 WL 681708
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 19, 2001
Docket99-1448, 99-1544
StatusPublished
Cited by4 cases

This text of 253 F.3d 748 (Alliant Energy Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alliant Energy Corp. v. Federal Energy Regulatory Commission, 253 F.3d 748, 347 U.S. App. D.C. 35, 2001 U.S. App. LEXIS 13500, 2001 WL 681708 (D.C. Cir. 2001).

Opinion

Opinion for the court filed by Circuit Judge KAREN LeCRAFT HENDERSON.

KAREN LeCRAFT HENDERSON, Circuit Judge:

The petitioners challenge two decisions of the Federal Energy Regulatory Commission (Commission or FERC) that ordered the Mid-Continent Area Power Pool (MAPP) to refund “third party compensation” charges it assessed customers after March 1, 1997 for transmitting electricity into or outside of the MAPP geographical area. First, a group of petitioning MAPP members (MAPP petitioners) assert that the ordered refunds are impermissibly retroactive and that they were incorrectly calculated. In addition, petitioner Enron, a MAPP member and beneficiary of the refunds, maintains the refunds should include not only the third party compensation charges, as the Commission directed, but also a portion of the amounts Em-on paid MAPP border utilities, based on their tariff rates, to transmit the energy inside or outside the MAPP area. For the reasons set forth below, we reject all of the petitioners’ arguments and deny both petitions for review.

I.

MAPP is an association of energy transmission utilities, generators and marketers serving an area encompassing part or all of several midwestern and western states and two Canadian provinces. Among other functions, MAPP coordinates energy sales and transmissions between and among its members. Before 1994 MAPP’s energy pooling agreement required its members to provide free, reciprocal transmission service to other members. In 1994 the pooling agreement was amended with the addition of a tariff, “Schedule F,” that imposed a charge for transmissions among MAPP members, but at a discounted distance-based rate rather than at the individual transmitting members’ filed tariff rates. FERC accepted the new agreement, including Schedule F, in a decision dated December 15, 1994. Mid-Continent Area Power Pool, 69 F.E.R.C. ¶ 61,347, 1994 WL 701296 (1994). The Commission provided the following explanation for its decision to accept the new schedule:

Notwithstanding our concerns with the calculations and adjustments discussed above, we will accept the proposed MAPP rates for filing because MAPP’s methodology produces rates that are just and reasonable and not unduly discriminatory or preferential when tested against traditional standards. We note that the single system-wide MAPP rate that members will pay for service over the entire MAPP system is lower than the rate that each jurisdictional MAPP member could separately propose under a traditional rate while taking into account distance and power flows.

Id. at 62,307.

In March 1996 MAPP filed a proposed restated pooling agreement that amended Schedule F to include a new section 2.4 requiring that a MAPP member purchasing energy from or selling energy to a nonmember arrange for extra-MAPP trans *751 mission with a MAPP border utility (paying the border utility’s tariff for the transmission) and, in addition, that the member pay MAPP itself the Schedule F intra-pool transmission charge in order “to compensate Members for third party use of their systems in connection with [the] sales or purchases.” Joint Appendix (JA) 56. 1

On May 16, 1996 the Commission issued “Order 888,” a final rule which requires generally that each public utility, and utility pool, file an “open access tariff’ by a specific deadline. Promoting Wholesale Competition Through Open Access Nondiscriminatory Transmission Services by Public Utilities and Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, 61 Fed. Reg. 21,-540, 21,541 (1996) (codified at 18 C.F.R. § 35.28). The order required power pools such as MAPP to file both “reformed power pooling agreements” and “a joint pool-wide Final Rule pro forma tariff’ not later than December 31, 1996. Id. at 31,728. The reformed power pool agreement must “establish open, non-discriminatory membership provisions and modify any provisions that are unduly discriminatory or preferential.” Id. The tariffs, like all open access tariffs filed under Order 888, are required to conform both to the “pro forma tariff’ set out in the final rule 2 and to FERC’s 1994 Transmission Pricing Policy Statement-, 59 Fed. Reg. 55,031 (1994), clarified, 71 F.E.R.C. ¶ 61,195,1995 WL 308644 (1995) (Policy Statement). 3 See Order 888, 61 Fed. Reg. at 21,541, 21,618-19.

On September 12, 1996 the Commission issued a decision accepting the restated MAPP agreement filed the previous March, including Schedule F. Mid-Continent Area Power Pool, 76 F.E.R.C. ¶ 61,-261, 1996 WL 518530 (1996). The Commission noted its 1994 order had found that the tariffs methodology, “while flawed, produced rates that were just and reasonable and not unduly discriminatory or preferential when tested against traditional standards” because “the single sys *752 tem-wide MAPP rate that members would pay for service over the entire MAPP system would be lower than the rate that each public utility MAPP member could separately propose under a traditional, postage stamp rate while taking into account distance and power flows.” Id. at 62,341-42 (citing 69 F.E.R.C. at 62,307). The 1996 restated Schedule F, the Commission concluded, “still produces rates that are reasonable when compared to the rate that each public-utility MAPP member could separately propose using a traditional, postage stamp rate methodology.” Id. at 62,342. The Commission nevertheless warned MAPP:

Nothing in this order relieves MAPP public utility members of their obligations under Order No. 888 to file a joint pool-wide pro forma tariff no later than December 31, 1996, and to begin to take service under that tariff for all pool transactions no later than December 31, 1996. They must also file a reformed power pooling agreement no later than December 31, 1996 that establishes open, non-discriminatory membership provisions and modifies any provisions that are unduly discriminatory or preferential. When those filings are made, the Commission will review rate and non-rate issues pertaining to MAPP to ensure that MAPP’s public utility mem-

bers are complying with Order No. 888. Id. at 62,336; see also id. at 63,342 (noting that “issue [of special rates] can be renewed when MAPP files its joint poolwide pro forma transmission tariff in response to Order No. 888”); id. n. 11 (“Under Order No. 888, public-utility members of loose pools like MAPP must file reformed power pooling agreements no later than December 31, 1996, and a joint pool-wide pro forma transmission tariff no later than December 31, 1996. Therefore, we will soon have another opportunity to review rate issues when the revised MAPP agreement is filed.”).

On December 24, 1996 MAPP submitted a “compliance filing,” as required by Order 888, which included a substantially unchanged Schedule F.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alliant Energy v. Nebraska Public Power District
347 F.3d 1046 (Eighth Circuit, 2003)
Atl City Elec Co v. FERC
329 F.3d 856 (D.C. Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
253 F.3d 748, 347 U.S. App. D.C. 35, 2001 U.S. App. LEXIS 13500, 2001 WL 681708, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alliant-energy-corp-v-federal-energy-regulatory-commission-cadc-2001.