Alliance for the Wild Rockies v. Marten

253 F. Supp. 3d 1108, 2017 U.S. Dist. LEXIS 82251
CourtDistrict Court, D. Montana
DecidedMay 30, 2017
DocketCV 17-21-M-DLC
StatusPublished
Cited by7 cases

This text of 253 F. Supp. 3d 1108 (Alliance for the Wild Rockies v. Marten) is published on Counsel Stack Legal Research, covering District Court, D. Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alliance for the Wild Rockies v. Marten, 253 F. Supp. 3d 1108, 2017 U.S. Dist. LEXIS 82251 (D. Mont. 2017).

Opinion

ORDER

Dana L. Christensen, Chief Judge

Before the Court is the motion for preliminary injunction of Plaintiffs Alliance for the Wild Rockies and Native Ecosystems Council (collectively “Plaintiffs”). Defendants Leanne Marten, Regional Forester for Region One of the United States Forest Service and the United States Forest Service (collectively “Defendants”) oppose the motion. As discussed below, the Court will grant the motion and preliminarily enjoin the Stonewall Vegetation Project until a final ruling is issued on the merits.

BACKGROUND

On February Í7, 2017, Plaintiffs filed suit seeking declaratory and injunctive relief contending that Defendants’ approval of the Stonewall Vegetation Project (the “Project”) violates federal law, specifically the Endangered Species Act (“ESA”), 16 U.S.C. § 1531 et seq. The Project is located on the Lincoln Ranger District in the Helena National Forest and is approximately four miles from the town of Lincoln, Montana. The Project area totals approximately 24,010 acres and includes management activities on 4,868 acres. Planned management activities are set to begin June 1, 2017, and include logging or thinning on 2,668 acres and prescribed burning on 2,220 acres.1 The Project authorizes 'the construction of 0.9 miles of temporary roads and 31.5 miles of road maintenance or reconstruction. Defendants state that this area largely consists of dead lodgepole pine due to disease and insect infestation. As a result, Defendants contend that implementation of the Project will improve forest health and reduce the risk of high-intensity wildfires in the area. However, this area is also frequented by various wildlife, including the Canada lynx.

In 2000, Canada lynx were listed as a threatened species under the ESA. In 2006, the United States Fish and Wildlife Service (“FWS”) designated 1,841 square miles as critical habitat for the species. However, the FWS failed to designate any National Forest land as critical habitat. Later, in 2007, the Forest Service adopted the Northern Rocky Mountain Lynx Management Direction, known as the “Lynx Amendment,” which set specific guidelines and standards for activities that may have an adverse effect on the species. At the same time the Forest Service initiated consultation with the FWS pursuant to section 7 of the ESA, 16 U.S.C. § 1536(a)(2), and determined that the management direction outlined in the Lynx Amendment did not jeopardize the Canada lynx. However, after completing the consultation process the FWS determined that its decisions relating to the designation of critical habitat were flawed and reevaluated its data. As a result of this reevaluation, the FWS subsequently revised the critical habitat designation for the lynx from 1,841 to 39,000 square miles.

In 2012, an environmental organization filed suit in this Court alleging that the Forest Service violated the ESA by failing to reinitiate section 7 consultation following the redesignation of Canada lynx eriti[1111]*1111cal habitat. Salix v. U.S. Forest Serv., 944 F.Supp.2d 984, 986 (D. Mont. 2013). The Court agreed and ordered reinitiation of consultation. Salix, 944 F.Supp.2d at 1002-1003. Following an appeal by the Forest Service, the Court of Appeals for the Ninth Circuit affirmed the Court’s determination that section 7 consultation must be reinitiated. Cottonwood Envtl. L. Ctr. v. U.S. Forest Serv., 789 F.3d 1075, 1088 (9th Cir. 2015), cert. denied, — U.S. —, 137 S.Ct. 293, 196 L.Ed.2d 213 (2016). Consequently, reconsultation between the FWS and the Forest Service began on November 2, 2016, and is currently ongoing. Plaintiffs contend, among other arguments, that the Forest Service is violating the ESA, specifically section 7(d), by implementing the Project prior to the completion of consultation. Accordingly, Plaintiffs seek to enjoin commencement of the Project until the parties’ cross-motions for summary judgment can be adjudicated on the merits.

ANALYSIS

“A preliminary injunction is an extraordinary remedy never awarded as of right.” Winter v. Nat. Resources Def. Council, Inc., 555 U.S. 7, 24, 129 S.Ct. 365, 172 L.Ed.2d 249 (2008) (citation omitted). Generally, a party seeking a preliminary injunction must establish that: (1) it is likely to succeed on the merits; (2) it is likely to suffer irreparable harm in the absence of preliminary relief; (3) the balance of equities tips in its favor; and (4) an injunction is in the public interest. Winter, 555 U.S. at 20, 129 S.Ct. 365 (citations omitted). However, “serious questions going to the merits and a balance of hardships that tips sharply towards the plaintiff can support issuance of a preliminary injunction, so long as the plaintiff also shows that there is a likelihood of irreparable injury and that the injunction is in the public interest.” All. for the Wild Rockies v. Cottrell, 632 F.3d 1127, 1135 (9th Cir. 2011).

A. Likelihood of Irreparable Injury

The Court will first address whether Plaintiffs have alleged a sufficient likelihood of irreparable harm to warrant a preliminary injunction of the Project.2 Plaintiffs have adequately alleged that implementation of the Project would likely cause irreparable harm to their members. These members have expressed “recreational, scientific, spiritual, vocational and educational interests” in viewing and utilizing “the area in its undisturbed state.” (Doc. 8-1 at 3.) Implementation of the Project, Plaintiffs argue, would cause irreparable harm to these interests.

As previously stated by the Ninth Circuit, establishing a likelihood of irreparable harm “should not be an onerous task for plaintiffs.” Cottonwood, 789 F.3d at 1091. Indeed, Plaintiffs’ expressed desire to visit the area in an undisturbed state is all that is required to sufficiently allege harm under ESA. Cottrell, 632 F.3d at 1135 (finding plaintiffs’ allegation that a proposed timber project would “harm its members’ ability to ‘view, experience, and utilize’ the areas in their undisturbed state” satisfied the irreparable harm requirement under Winter). Plaintiffs have sufficiently alleged a likelihood of irreparable injury to warrant a preliminary injunction.

[1112]*1112B. Public Interest and Balance of Hardships

When the government is a party under a preliminary injunction analysis, the public interest and balance of equities factors merge. Drakes Bay Oyster Co. v. Jewell, 747 F.3d 1073, 1092 (9th Cir. 2014) (citing Nken v. Holder, 556 U.S. 418, 435, 129 S.Ct. 1749, 173 L.Ed.2d 550 (2009)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
253 F. Supp. 3d 1108, 2017 U.S. Dist. LEXIS 82251, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alliance-for-the-wild-rockies-v-marten-mtd-2017.