Alliance for the Wild Rockies, et al. v. Tom Vilsack, in his official capacity as Secretary of the Department of Agriculture, et al.

District Court, D. Montana·Decided May 28, 2026·No. 9:24-cv-00010·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MONTANA MISSOULA DIVISION

ALLIANCE FOR THE WILD ROCKIES, et al., CV 24-10-—M-DLC Plaintiffs, Vs. ORDER TOM VILSACK, in his official capacity as Secretary of the Department of Agriculture, et al., Defendants, and RAVALLI COUNTY, MONTANA and MONTANA DEPARTMENT OF NATURAL RESOURCES AND CONSERVATION, Defendant-Intervenors.

Plaintiffs are environmental organizations challenging the United States Forest Service’s (the “Forest Service”) and the United States Fish and Wildlife Service’s (the “Fish and Wildlife Service”) approval of a forest treatment project in the Bitterroot National Forest (the “Mud Creek Proj ect” or the “Project”). (Doc. 43.) There are also two defendant intervenors, Ravalli County and the Montana Department of Natural Resources and Conservation. (See Docs. 21, 34.) At this

point in the case, Plaintiffs’ claims are three-fold. First, Plaintiffs argue that the Forest Service failed to take a “hard look” at the Project’s effects on climate change in violation of National Environmental Policy Act (“NEPA”). Second, Plaintiffs argue that the Project does not meet habitat standards for pine martens in violation of the National Forest Management Act (“NFMA”). Finally, Plaintiffs

argue that the Project relied on impermissibly vague mitigation measures to offset impacts in violation of the Endangered Species Act (“ESA”). The parties filed cross-motions for summary judgment, (Docs. 55, 60, 65), and a motion hearing was held before United States Magistrate Judge Kathleen L. DeSoto on August 20, 2025, (see Doc. 83 (Min. Entry)). On September 30, 2025, Judge DeSoto entered Findings and Recommendations, recommending that

summary judgment be granted in favor of Federal Defendants and Defendant- Intervenors (collectively, “Defendants”). (Doc. 85.) Plaintiffs filed objections, (Doc. 86; see also Doc. 89), to which Federal Defendants responded, (Doc. 88; see also Doc. 93). Plaintiffs’ objections are reviewed de novo, 28 U.S.C. § 636(b)(1), and addressed individually below. The Findings and Recommendations are otherwise reviewed for clear error. See Thomas v. Arn, 474 U.S. 140, 154 (1985); United States v. Syrax, 235 F.3d 422, 427 (9th Cir. 2000) (defining “clear error”). Because Judge DeSoto provided a complete background of the Project, (Doc. 85 at 3-7), it is not restated here.

The Forest Service’s compliance with NEPA, NFMA, and the ESA is reviewed under the Administrative Procedure Act (“APA”). See Native Ecosystems Council v. Marten, 883 F.3d 783, 788 (9th Cir. 2018). The APA authorizes a court to “hold unlawful and set aside agency action, findings and conclusions found to be... arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). Agency action is arbitrary and capricious if the administrative record demonstrates that “the agency has relied on factors which Congress has not intended it to consider, entirely failed to consider an important aspect of the problem, offered an explanation for its decision that runs counter to the evidence before the agency, or is so implausible that it could not be ascribed to

a difference in view or the product of agency expertise.” Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983). Where an agency’s administrative record is complete and constitutes the whole and undisputed facts underlying agency decisionmaking, summary judgment is appropriate. See City & Cnty. of San Francisco v. United States, 130 F.3d 873, 877 (9th Cir. 1997). ANALYSIS As reflected in both the Findings and the parties’ filings, Plaintiffs’ claims evolved dramatically as the case proceeded, complicating judicial review and ultimately narrowing to the three issues identified above. Because Plaintiffs’

objections related to those issues lack merit, the September 30, 2025 Findings and Recommendations, (Doc. 85) is adopted in full. I. Supplemental Authority After both the Findings was issued and Plaintiffs’ objections were filed, Center for Biological Diversity v. United States Forest Service (“South Plateau”) was decided. See 811 F. Supp. 3d 1206 (D. Mont. 2025). Therein, this Court found that the Forest Service’s use of “condition-based management” to approve a logging project in the Custer Gallatin National Forest violated NEPA, NFMA, and the ESA, particularly as it related to road placement decisions and secure habitat for grizzly bears. See id. at 1229, 1231. In their citation of supplemental authority, Plaintiffs attempt to bootstrap their arguments in the present case to the successful challenges in South Plateau. (See Doc. 89.) Plaintiffs did not challenge the conditional management component of the Mud Creek Project. (See Doc. 43.) They are not permitted to do so now. To the extent South Plateau otherwise bears

on the legal issues in this case, that analysis has been incorporated below. I. NEPA “TNEPA] is a procedural statute that requires federal agencies to take a ‘hard look’ at the environmental consequences of their actions.” N. Cascades Conserv. Council v. U.S. Forest Serv., 136 F.4th 816, 821 (9th Cir. 2025) (internal quotation marks omitted). To satisfy the “hard look” requirement, an agency must provide “a

reasonably thorough discussion of the significant aspects of the probable environmental consequences.” Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety Admin., 538 F.3d 1172, 1194 (9th Cir. 2008). In their objections, Plaintiffs argue that the Forest Service failed to take the requisite “hard look” at the Project’s impacts on climate change because it relied on a forest-wide carbon assessment, see MC10563, and did not consider impacts at a site-specific level. To be sure, “merely discussing carbon impacts and concluding that they will be minor does not equate to a ‘hard look.’” Ctr. for Biological Diversity v. U.S. Forest Serv. (“Black Ram”), 687 F. Supp. 3d 1053, 1076-77 (D. Mont. 2023), overruled on other grounds 2025 WL 586358 (9th Cir. Feb. 24, 2025). “NEPA requires more than a statement of platitudes, it requires appraisal to the public of the actual impacts of an individual project.” /d. at 1077. But, contrary to Plaintiffs’ position, that mandate can be met if the forest-wide assessment is both recent enough and specific enough to reflect the impacts of the particular proposed project activity. See South Plateau, 811 F. Supp. 3d at 1218-19 (“Given the nature of th[e] Project and the recency and scope of the tiered analysis, the Forest Service adequately considered the Project’s cumulative effects on climate change.”) Here, the Forest Service completed the Forest Carbon Assessment for the Bitterroot National Forest in the Forest Service’s Northern Region in 2021. See MC0012805—33. The Project area falls within the same assessment area and involves the same types of fuel

management activities considered in the Assessment. See id.

Free access — add to your briefcase to read the full text and ask questions with AI

Alliance for the Wild Rockies, et al. v. Tom Vilsack, in his official capacity as Secretary of the Department of Agriculture, et al., (D. Mont. 2026).

Alliance for the Wild Rockies, et al. v. Tom Vilsack, in his official capacity as Secretary of the Department of Agriculture, et al. (Alliance for the Wild Rockies, et al. v. Tom Vilsack, in his official capacity as Secretary of the Department of Agriculture, et al.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related