Allfirst Bank v. Progress Rail Services Corp.

178 F. Supp. 2d 513, 2001 U.S. Dist. LEXIS 21631, 2001 WL 1663935
CourtDistrict Court, D. Maryland
DecidedDecember 27, 2001
DocketCiv. H-01-2527, Civ. H-01-2991
StatusPublished
Cited by6 cases

This text of 178 F. Supp. 2d 513 (Allfirst Bank v. Progress Rail Services Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allfirst Bank v. Progress Rail Services Corp., 178 F. Supp. 2d 513, 2001 U.S. Dist. LEXIS 21631, 2001 WL 1663935 (D. Md. 2001).

Opinion

MEMORANDUM AND ORDER

ALEXANDER HARVEY, II, Senior District Judge.

These two civil actions are substantially identical. The parties are the same, and the legal and factual issues which have been raised are similar.

Civil No. H-01-2527 was instituted by plaintiff Allfirst Bank (“Allfirst”) in this Court on August 24, 2001. Named as defendants in this case are Progress Rail Services Corporation (“Progress Rail”) and Railcar, Ltd. (“Railcar”). In its one-count complaint, plaintiff Allfirst seeks damages for breach of contract and specific performance of the contract.

Civil No. H-01-2991 was docketed in this Court on October 9, 2001, following its transfer from the Northern District ,of Georgia. The plaintiffs in that case are Progress Rail and Railcar and the defendant is Allfirst. That civil action was originally filed in the Superior Court of Fulton County, Georgia on August 1, 2001 and was removed by defendant Allfirst to the United States District Court for the Northern District of Georgia, Atlanta Division, on the ground that diversity jurisdiction existed. By Order entered in the case on October 2, 2001, United States District Judge Thomas W. Thrash, Jr. denied plaintiffs’ motion to remand, denied defendant’s motion to dismiss, and granted defendant’s motion to transfer the case to this Court pursuant to 28 U.S.C. § 1404(a). In Civil No. H-01-2991, the plaintiffs are seeking a declaratory judgment and in-junctive relief.

There are three motions now pending before this Court in, these two cases. In Civil No. H-01-2991, Progress Rail and Railcar have filed a motion to retransfer *516 and/or remand. 1 Progress Rail and Rail-car have filed a motion to stay or dismiss Civil No. H-01-2527 without prejudice. Allfirst has filed in both cases a motion to consolidate. Memoranda and exhibits in support of and in opposition to these motions have been filed by the parties.

Following its review of the pleadings, memoranda and exhibits, this Court is satisfied that no hearing is necessary. See Local Rule 105.6. For the reasons stated herein, the motion to retransfer and/or remand filed by Progress Rail and Railcar in Civil No. H-01-2991 will be denied, the motion to stay or dismiss without prejudice filed by Progress Rail and Railcar in Civil No. H-01-2527 will be denied, and All-first’s motion to consolidate these two cases will be granted.

I

Background Facts

Allfirst is a commercial bank with its principal place of business in Maryland. 2 In 1998, Allfirst entered into discussions with Progress Rail and Railcar concerning the financing of used rail cars owned by Progress Rail and Railcar which had been leased to various railroads. Progress Rail is an Alabama corporation with its principal place of business in that state, and Railcar is a Georgia corporation with its principal offices in Georgia. 3

Allfirst has had a business relationship with Progress Rail and Railcar for some 10 years. During the course of this relationship, there were a number of transactions between the parties involving the sale to Allfirst or the financing by Allfirst of railroad rolling stock which were subject to leases to third parties. On November 30, 1998, the parties entered into three different written agreements, an Assignment Agreement, a Service Agreement and a First Loss Deficiency Guarantee (“FLDG”) (collectively “the Agreements”). The parties to the Assignment Agreement are Allfirst, Progress Rail and Railcar, while only Allfirst and Progress Rail are signatories to the Service Agreement. Under the FLDG, Progress Rail extended certain guarantees to Allfirst.

Pursuant to the Assignment Agreement as later amended, Progress Rail and Rail-car sold 996 used railcars to Allfirst for an advance of $13,184,510 and assigned to Allfirst the leases to which these railcars were subject. Under this Agreement, Progress Rail assumed certain obligations of the lessor and was to provide various services to Allfirst. Progress Rail agreed to collect rentals under the leases, to maintain and repair the railcars, to make certain payments to Allfirst and, when a lease expired, to re-let or sell the car.

As various leases expired during the period covered by the Agreements, the railroads returned leased rail cars. According to Progress Rail, the market for leased rail cars has collapsed, and the returned cars cannot be re-leased. It is Progress Rail’s position that the 1998 transaction was not a loan financing and that the repair obligation of Progress Rail is not a payment guarantee. Allfirst contends that under the Agreements, Prog *517 ress Rail was obligated to repair the cars regardless of their economic value and was further obligated to guarantee the minimum rentals agreed upon. Progress Rail in turn maintains that its liability for loss of value of the cars is limited and that it has overpaid its obligations under the FLDC.

The Agreements set forth in some detail the rights and obligations of the parties during the Agreements’ terms which were to end on November 30, 2003. The many disputes which are addressed in the pleadings in these two cases arise as a result of the sharp conflict between the parties concerning the proper interpretation to be given to their contractual rights and obligations as provided in the Agreements.

II

The Motion to Retransfer

After it had removed to the Northern District of Georgia the action brought against it in a Georgia state court by Progress Rail and Railcar, Allfirst filed a motion to dismiss and a motion to transfer. Progress Rail and Railcar in turn filed a motion to remand the case to the Superior Court of Fulton County. Those motions were briefed by the parties, and their memoranda are on file here and have been reviewed by this Court. In his Order filed on October 2, 2001, Judge Thrash denied the motion to dismiss and the motion to remand and granted Allfirst’s motion to transfer the case to this Court pursuant to 28 U.S.C. § 1404(a).

In their pending motion to retransfer, Progress Rail and Railcar are in effect requesting this Court to act as an appellate court and reverse the ruling made by Judge Thrash after full briefing of the matter in his Court. On the record here, this Court is not disposed to play “jurisdictional ping-pong” and retransfer this case to the Northern District of Georgia. See Moses v. Business Card Express, Inc., 929 F.2d 1131, 1137 (6th Cir.1991).

The ruling made by Judge Thrash constitutes the law of the case. Columbus-America Discovery Group v. Atlantic Mut. Ins. Co., 203 F.3d 291, 304 (4th Cir.2000). Under that doctrine, when a court decides upon a rule of law, that decision should continue to govern the same issues in subsequent stages in the same case. Arizona v. California,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Casey v. Consol Energy Inc.
S.D. West Virginia, 2017
Fitzwater v. CONSOL Energy, Inc.
S.D. West Virginia, 2017
Nace v. Miller
28 A.3d 737 (Court of Special Appeals of Maryland, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
178 F. Supp. 2d 513, 2001 U.S. Dist. LEXIS 21631, 2001 WL 1663935, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allfirst-bank-v-progress-rail-services-corp-mdd-2001.