Allens Creek/Corbetts Glen Preservation Group, Inc. v. West

2 F. App'x 162
CourtCourt of Appeals for the Second Circuit
DecidedJanuary 31, 2001
DocketNo. 00-6133
StatusPublished
Cited by10 cases

This text of 2 F. App'x 162 (Allens Creek/Corbetts Glen Preservation Group, Inc. v. West) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allens Creek/Corbetts Glen Preservation Group, Inc. v. West, 2 F. App'x 162 (2d Cir. 2001).

Opinion

SUMMARY ORDER

UPON DUE CONSIDERATION, IT IS HEREBY ORDERED, ADJUDGED AND DECREED that the judgment of the district court be, and it hereby is, AFFIRMED.

The plaintiffs-appellants appeal from a March 22, 2000 order of the district court granting summary judgment to the defendants-appellees on the ground of laches. See Allens Creek/Corbetts Glen Preservation Group, Inc. v. Caldera, 88 F.Supp .2d 77 (W.D.N.Y.2000).

This case arises from a dispute over the development of a twenty acre parcel of land, formerly the site of an abandoned sewage treatment plant, on the boundary between the towns of Brighton arid Penfield, New York. In January 1994, defendants Linden Associates and Linden Associates LLC (collectively “Linden”) requested approval from Penfield’s Planning Board for a project to construct a two-story, 54,000 square-foot light industrial building on one of four subdivided lots, along with parking spaces, landscaping, lighting, and walkways. The plaintiffs, several of whom reside near the site, opposed the development, asserting that it would involve unlawfully filling in wetlands. They have participated in several environmental reviews and other proceedings since 1994, including the State Environmental Quality Review Act process, three Article 78 actions in New York state court challenging the Planning Board’s determination under the Act, and the proceeding in which Linden obtained authorization from the Army Corps of Engineers.

In May 1994, Linden sought a ruling by the Corps that its proposed project qualified for approval under a nationwide permit issued pursuant to the Clean Water Act, 33 U.S.C. § 1344(e). Despite the plaintiffs’ objections, the Corps agreed on July 23, 1997 that the nationwide permit applied to Linden’s project, conditioned on Linden’s construction of a stormwater wetland management system and Linden’s donation of $44,000 for the development of wetlands at another location. The Corps authorized the commencement of construction at any point between August 7, 1997 and December 13, 1998 and sent a copy of its decision to plaintiff Jean Baric, who is a member of plaintiff Allens Creek/Corbetts Glenn Preservation Group, Inc. At a preconstruction meeting in January 1998 attended by two of the plaintiffs, a construction schedule, which indicated that work on the wetlands would begin in February 1998 and end in April 1998, was distributed.

The plaintiffs filed this suit on March 30, 1998, more than eight months after the [164]*164Corps’ authorization, but did not complete service on all of the defendants until April 22, 1998. At that time, the existing wetlands had been filled and the new storm-water wetland system was ninety-five percent complete. The plaintiffs’ complaint alleges that (1) the project required an individual permit under the Clean Water Act, 33 U.S.C. § 1344, rather than authorization pursuant to a nationwide permit; (2) the authorization under the nationwide permit was arbitrary, capricious, and unlawful because the New York water quality certification necessary to obtain such a permit was based on a materially different plan; and (3) the authorization under the nationwide permit was based on an arbitrary and capricious decision by the District Engineer of the Corps that the project would have a minimal environmental impact. The complaint sought relief in the form of (1) a declaratory judgment that authorization under the nationwide permit is null and void; (2) preliminary and permanent injunctions preventing Linden from placing fill in the wetlands; and (3) litigation costs and fees.

After filing suit and serving the defendants, the plaintiffs did not move for a preliminary injunction or for summary judgment. The defendants moved for summary judgment in November 1998 arguing that the action was barred by laches, and the plaintiffs responded in May 1999, more than five months after the deadline established by the district court. The plaintiffs also failed to file a statement of facts in dispute as required by Local Rule 56.

The district court granted the motion, holding that the plaintiffs’ unreasonable delay prejudiced the defendants because, inter alia, the projects were “virtually complete”; “[cjonstruction ... ha[d] progressed well beyond the preparatory stage”; “[t]he landscape ha[d] been substantially and irreversibly altered”; the “wetlands had been filled and the new drainage system had been nearly completed”; and Linden had spent substantial amounts of money. Allens Creek/Corbetts Glen Preservation Group, Inc., 88 F.Supp.2d at 84. The plaintiffs now appeal.

The standard of review applicable to a grant of summary judgment based on laches is unsettled in this Circuit. See Ikelionwu v. United States, 150 F.3d 233, 236-37 (2d Cir.1998) (discussing conflicting authority). We need not resolve this issue, however, because we would uphold the district court’s judgment under either de novo or abuse of discretion review.

“Laches is based on the maxim, ‘vigilantibus non dormientibus aequitas subvenit,’ meaning ‘equity aids the vigilant, not those who sleep on their rights.’ ” Id. at 237 (quoting Ivani Contracting Corp. v. City of New York, 103 F.3d 257, 259 (2d Cir.1997)). The equitable defense of laches bars an equitable claim where the plaintiff has unreasonably and inexcusably delayed, resulting in prejudice to the defendant. See id.;" Ivani 103 F.3d at 259. To prevail on this defense, the defendant must show that: “(1) the plaintiff knew of the defendant’s misconduct; (2) the plaintiff inexcusably delayed in taking action; and (3) the defendant was prejudiced by the delay.” Ikelionwu, 150 F.3d at 237.

The plaintiffs do not dispute that they had knowledge of the defendants’ plans for development as early as 1994 and of the Corps’ authorization — the final requirement for commencement of work on the site — in late July 1997. Nor do the plaintiffs dispute that they delayed by (1) waiting eight months after the Corps’ authorization, when the wetlands work was nearly completed, before challenging the authorization in court; and (2) never mov[165]*165ing for a preliminary injunction to prevent the work, even after filing suit.

With respect to prejudice, we agree with the district court that at the time of the filing of suit Linden had “expended considerable time, effort, and money in reliance on the governmental approvals of its plans.” Allens Creek/Corbetts Glen Preservation Group, Inc., 88 F.Supp.2d at 84. As of November 1998, when Linden moved for summary judgment, Linden had spent approximately $1 million on the project, including nearly $115,000 on the stormwater wetland system and on filling the wetlands. In addition, Linden had donated $44,000 to an offsite wetlands project. Although the plaintiffs are correct that laches should “be invoked sparingly in environmental cases because the plaintiff[s][are] not the only part[ies] to suffer harm by alleged environmental damage,” Neighbors of Cuddy Mountain v. U.S. Forest Service,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lafferty v. Virts
W.D. New York, 2024
Hill v. County of Niagara
W.D. New York, 2021
Ronnie Van Zant, Inc. v. Pyle
270 F. Supp. 3d 656 (S.D. New York, 2017)
Barnett v. Connecticut Light & Power Co.
967 F. Supp. 2d 593 (D. Connecticut, 2013)
Chesapeake Energy Corp. v. Bank of New York Mellon Trust Co.
957 F. Supp. 2d 316 (S.D. New York, 2013)
City of Newburgh v. SARNA
690 F. Supp. 2d 136 (S.D. New York, 2010)
Northwest Bypass Group v. U.S. Army Corps of Engineers
470 F. Supp. 2d 30 (D. New Hampshire, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2 F. App'x 162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allens-creekcorbetts-glen-preservation-group-inc-v-west-ca2-2001.