Allen v. United States

178 F. Supp. 21, 1959 U.S. Dist. LEXIS 2210
CourtDistrict Court, E.D. Pennsylvania
DecidedJuly 1, 1959
Docket241 of 1957
StatusPublished
Cited by4 cases

This text of 178 F. Supp. 21 (Allen v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen v. United States, 178 F. Supp. 21, 1959 U.S. Dist. LEXIS 2210 (E.D. Pa. 1959).

Opinion

LAYTON, District Judge.

This is an Admiralty proceeding brought on behalf of the libelant, Wilbert Allen, against the United States, as owner of the U.S.S. Casa Grande (LSD-13), 1 pursuant to the Public Vessels Act of 1925, 46 U.S.C.A. §§ 781-790. Allen, a shipyard welder, seeks to recover damages for injuries sustained in a fall while he was engaged in removing temporary staging in the forward ballast tank of the Casa Grande. The staging was erected in the tank by the contractor which had contracted to make extensive repairs and alterations to the vessel. Pursuant to Admiralty Rule 56, 28 U.S.C.A., the respondent, United States, impleaded the contractor, Keystone Drydock and Ship Repair Co., Inc., libelant’s employer, asserting a right of indemnification over against the latter.

Allen charges that the Casa Grande was unseaworthy due to the defects in the staging which gave way while he was standing on it and, furthermore, that the government was negligent in failing to furnish him with a reasonably safe place to work.

Whether or not the Casa Grande was seaworthy in large part depends upon Allen’s status while working about her which, in turn, depends upon the nature of the repairs. Accordingly, a rather detailed statement as to the nature, extent and cost of the overhaul is required.

Prior to June 7, 1956, the LSD-type-vessel was found to be well adapted to-the work of Arctic Base Supply except, for the fact that the hull was not of sufficient strength to navigate in ice condi *23 tions. Moreover, the Casa Grande was then in need of an extensive overhaul and, in addition, a request had been made to the Bureau of Ships for certain alterations, the most substantial of which were (a) the stiffening of the entire hull just mentioned and (b) the removal of the mast for the installation of extensive new radar equipment.

On June 7, 1956, while en route from Sonerestrom to Goose Bay, Labrador, the Casa Grande was struck by an iceberg causing such extensive damage to the hull as to compel her immediate return to the United States. So serious was the hull damage that her captain refused to take on a return cargo of floating barges. Temporary emergency repairs were effected which enabled her to limp back to Norfolk where she was ordered to Philadelphia for the overhaul, repairs and alterations previously mentioned as well as the repairs to the hull. At Fort Mifflin, all ammunition was unloaded. At the Sun Shipbuilding Co., she was drydoeked to ascertain the exact nature of the damage to the hull. This was found to be a hole 20 feet high and 40 feet long together with extensive cracks in the hull. The hole itself was like a “rolled up sardine can”. While at the Sun Drydock, the propellers 2 were removed. She remained there until the bid for repairs and alterations was awarded to Keystone and then she was towed by Navy tug to a point near the Keystone yard where she was placed under tow by a civilian tug under the direction of a civilian pilot, taken into the custody of, and berthed by, Keystone at its dock.

The Overhaul

The work on the radar mast was both extensive and costly. The mast had to be unstepped, hoisted onto the dock by crane and transferred to the yard. After the new equipment was installed, the mast had to be restepped.

The work of stiffening the entire hull, exclusive of repairs to the hull, was substantial also. Heavy steel strengthening members were inserted and welded in place around the entire hull and a large bulkhead was installed in the fore-peak tank. The designs for these alterations were apparently prepared by the Bureau of Ships in accordance with drawings and blueprints made up by Naval architects. It appears also that the services of a shipyard were needed in fabricating the plates which comprised the bulkhead some of which were so large (3 feet x 8 feet) as to necessitate cutting a hole in the deck in order that they could be lowered into the forepeak tank. The hull stiffening job alone required the services of about 45 men for a substantial portion of the time the ship was at Keystone.

Aside from the alterations to the radar mast and the strengthening of the hull, numerous major and minor repairs were made. The ship’s starboard turbine had to be completely removed and trucked back to the manufacturer. The task of transferring the turbine from the ship onto a truck was substantial in itself, involving, as it did, the removal of a good deal of wooden and steel decking and the assistance of a shipyard crane. Both boilers had to be tom down and completely rebricked. The steering mechanism was entirely overhauled. The ship’s ballasting system, vitally important to the functioning of a Landing Ship Dry-dock, was found to be in an unusually bad condition due to extensive rust, requiring the removal of much rusted pipe, some as large as 6 inches in diameter, together with the installation of new pumps. This job alone took two weeks. In. addition, certain new type pumps were installed in other parts of the ship to replace existing pumps and new propellers had to be installed. Some steel decking (not the decking torn out to *24 remove the turbine) was removed and replaced and over 4,000 feet of new wooden decking was installed. There were repairs to the radio. The two boiler room blowers were removed and ice damage to the bow (exclusive of hull damage) was repaired.

In addition to all this was the substantial job of fabricating plates and welding for the repair of the 800 square foot hole in the hull.

In summation, the repairs, alterations and overhaul took in excess of 2% months. During 1% months of that period, the Casa Grande was drydocked. The services of 275 Keystone employes were required, and even aside from the very costly equipment on the radar mast, the job cost $700,000. Including this radar equipment, which the government itself supplied, it may be assumed that the over-all. job cost nearly $1,000,000.

The Law

It has long been settled that a shipowner is liable to indemnity for injuries to seamen as the result of unseaworthiness of the ship. Mahnich v. Southern Steamship Co., 321 U.S. 96, 64 S.Ct. 455, 88 L.Ed. 561; The Osceola, 189 U.S. 158, 23 S.Ct. 483, 47 L.Ed. 760. This indemnity, however, extends only to those who are performing work on vessels in navigation and work which is historically and traditionally performed by seamen. United New York and New Jersey Pilots Ass’n v. Halecki, 358 U.S. 613, 79 S.Ct. 517, 3 L.Ed.2d 541; Desper v. Starved Rock Ferry Co., 342 U.S. 187, 72 S.Ct. 216, 96 L.Ed. 205.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roy Speese v. United States
440 F.2d 1164 (Third Circuit, 1971)
Lupo v. Consolidated Mariners, Inc.
261 F. Supp. 450 (S.D. New York, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
178 F. Supp. 21, 1959 U.S. Dist. LEXIS 2210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-v-united-states-paed-1959.