Allen Farms, Inc. v. Broce Const. Co., Inc.

2006 OK CIV APP 36, 134 P.3d 852, 2005 Okla. Civ. App. LEXIS 129, 2006 WL 1154962
CourtCourt of Civil Appeals of Oklahoma
DecidedOctober 21, 2005
Docket100,522
StatusPublished
Cited by3 cases

This text of 2006 OK CIV APP 36 (Allen Farms, Inc. v. Broce Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen Farms, Inc. v. Broce Const. Co., Inc., 2006 OK CIV APP 36, 134 P.3d 852, 2005 Okla. Civ. App. LEXIS 129, 2006 WL 1154962 (Okla. Ct. App. 2005).

Opinion

Opinion by

LARRY JOPLIN, Presiding Judge.

¶ 1 Defendants/Appellants Broce Construction Company, Inc., a corporation, and St. Paul Seaboard Surety Company, a corporation (collectively, Broce or Defendants) seek review of the trial court’s orders granting judgment and attorney’s fees to Plaintiff/Ap-pellee Allen Farms, Inc., (Allen) in Allen’s action to recover an unpaid sum due for materials furnished. In this proceeding, Defendants challenge the trial court’s judgment for Allen as contrary to the governing contract and unsupported by the evidence, and the trial court’s post-judgment denial of its prayer for attorney’s fees as contrary to law. Having reviewed the record, however, we discern no errors of law or fact. The orders of the trial court are therefore affirmed.

¶ 2 Broce contracted with the Oklahoma Turnpike Authority (OTA) to construct slightly more than four miles of highway in McClain County. Pursuant to construction plan specifications, the contract required Broce to install solid slab grass sod to a width of ten feet along each side of the highway (over 61,000 square yards), and Broce subcontracted with Allen to provide and install the sod at $1.35 per square yard.

*854 ¶ 3 As it turned out, however, the project required substantially more sod than specified, apparently due to an error in the plan specifications by Triad Design Group, OTA’s project design engineers, and, by letter amendments to the prime contract, OTA approved installation of sod in excess of that called for by the plans. At the express direction of Broce, Alen consequently delivered and installed over 190,000 square yards of sod, some of which for the replacement of existing sod destroyed by Broce, and for which, Broce bore the obligation to pay. A second subcontractor, Sioux Construction Company, laid over 43,500 square yards.

¶4 Sioux Construction submitted an invoice to Broce, seeking payment of $58,752.00 for sod, and $6,900.00 for fencing installed at Broce’s direction. Alen submitted an invoice requesting payment of about $256,687.00 1 for 190,140 square yards of sod delivered and installed.

¶ 5 Alen and Broce subsequently met to draft a “spreadsheet” delineating the quantity of sod installed according to the project’s benchmarks, 2 and Alen then estimated over 215,000 square yards of sod had been laid by it and Sioux Construction. However, Broce and Triad subsequently reduced the amount to be claimed to slightly over 185,000 square yards, apparently without Alen’s input.

¶ 6 After negotiation of the final payment, OTA paid Broce for 185,373.67 square yards of sod a sum of $250,254.45. Broce paid Sioux Construction $48,841.19 in settlement of its invoice. Broce paid Alen a total of $148,816.87, 3 leaving an alleged balance due to Alen of $107,870.13.

¶ 7 When Broce refused to pay more, Alen commenced the instant suit to collect in 2002. In December 2003, Broce offered to confess judgment in the sum of $76,122.71. Alen neither responded to the offer, nor made a counter-offer. In January 2004, a month before trial, Broce tendered a payment to Alen of $68,254.58, leaving an alleged balance due of $37,048.68, recovery of which Alen sought at non-jury trial in February 2004.

¶ 8 At the non-jury trial, Broce admitted it bore liability for slightly more than $25,-500.00 4 in sod to replace existing sod destroyed. Broce presented evidence to show that its subcontract with Alen limited the amount payable for sod to the amount approved for payment by OTA pursuant to the prime contract as amended. Broce also presented evidence to show that it had negotiated the final payment from OTA according to the spreadsheet figures prepared with A-len’s input, and that its combined payments to Alen and Sioux Construction exceeded the sum paid by OTA for sod.

¶ 9 Alen presented evidence to show that Broce was liable to pay for all sod delivered and installed, both because Broce expressly authorized the installation of all sod delivered, and because Broce bore liability for the replacement of the existing sod in place which it destroyed during performance of the prime contract. Alen also presented evidence showing: Broce did not present OTA an accurate statement of all sums invoiced by Alen for sod provided at the time of the negotiation of the final project payment; Broce did not afford Alen an opportunity to present an accurate statement of the sod it delivered and installed during the negotiation of the final payment with OTA; OTA paid for substantially more sod than called for by the plan specifications; and, that Broce paid only $15,650.00 out of pocket for the existing sod destroyed during construction.

¶ 10 On consideration of the testimony and evidence, the trial court held for Alen, and awarded the claimed balance due of $37,048.68 with interest. Alen filed a post-judgment motion to assess attorney’s fees and costs as the prevailing party on the *855 contract claim under 12 O.S. § 936. Broce filed a post-judgment motion to assess attorney’s fees and costs pursuant to 12 O.S. § 1101.1, asserting Allen’s recovery of less than the pre-trial offer to confess. The trial court found § 1101.1 inapplicable, denied attorney’s fees to Broce, and granted costs and attorney’s fees to Allen in the sum of $26,230.31.

Standard of Review

¶ 11 We review the trial court’s rulings on questions of law de novo, without deference to the lower court’s legal conclusions. See, e.g., Fanning v. Brown, 2004 OK 7, 85 P.3d 841; K & H Well Service, Inc. v. Tcina, Inc., 2002 OK 62, 51 P.3d 1219. In cases tried to the bench without a jury, we review the record to determine whether competent evidence supports the trial court’s findings of fact, and if we find competent evidence to support the trial court’s order, we must affirm. K & H Well Service, Inc., 2002 OK 62, ¶9, 51 P.3d at 1230.

Evidentiary Challenges

¶ 12 In its second proposition, Broce challenges the trial court’s judgment to Allen as contrary to the evidence, particularly complaining the trial court erred in calculating its out-of-pocket sod expense as less than its admitted liability, and erroneously imposed liability on it for sod in excess of the 10-foot width requirement imposed by OTA. In its third proposition, Broce complains the trial court’s judgment runs contrary to its contract with Allen, limiting the amount payable to the amount approved for payment by OTA. 5 Allen responds, asserting the evidence showed that it delivered and installed all invoiced sod at the specific direction of Broce and/or its agents, and that Broce bears liability for all sod delivered and installed pursuant to an executed oral modification of the parties’ contract.

¶ 13 “A contract in writing may be altered by a contract in writing, or by an executed oral agreement, and not otherwise.” 15 O.S. § 237. “[T]he subsequent ‘executed oral agreement’ referred to in § 237, supra, must be established by ‘positive, clear and convincing’ proof.” Dewberry v. Universal C.I.T. Credit Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Citgo Petroleum Corp. v. RANGER ENTERPRISES, INC.
573 F. Supp. 2d 1114 (W.D. Wisconsin, 2008)
Hopkins v. Byrd
2006 OK CIV APP 132 (Court of Civil Appeals of Oklahoma, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2006 OK CIV APP 36, 134 P.3d 852, 2005 Okla. Civ. App. LEXIS 129, 2006 WL 1154962, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-farms-inc-v-broce-const-co-inc-oklacivapp-2005.