Alleghany Iron Co. v. Teaford

31 S.E. 525, 96 Va. 372, 1898 Va. LEXIS 102
CourtSupreme Court of Virginia
DecidedSeptember 22, 1898
StatusPublished
Cited by19 cases

This text of 31 S.E. 525 (Alleghany Iron Co. v. Teaford) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alleghany Iron Co. v. Teaford, 31 S.E. 525, 96 Va. 372, 1898 Va. LEXIS 102 (Va. 1898).

Opinion

Biely, J.,

delivered the opinion of the court.

This is a writ of error to a judgment rendered in two actions of assumpsit, which, being between the same parties and growing out of the same matter, were consolidated by the court.

[374]*374On December 10, 1895, a contract was entered into between the Alleghany Iron Company and K. H. Teaford by which it agreed, among other things, to take from him 10,000 tons of iron ore from a certain mine, at $1.10 per ton. The ore was to be delivered at the mine in a crude state, on board of the cars of the company, and thence hauled to its washer and washed» the hauling and washing to be at its expense. J. E. Hannah acquired from Teaford an interest in the contract, became jointly interested with him in its performance and was united with him as co-plaintiff. They commenced to mine and deliver the ore in January, and continued to do so up to the 17th day of February, when the severity of the weather caused the pump connected with the washer to freeze and break, thereby preventing the washing of the ore, and stopping the plaintiffs from delivering it. The company did not resume operations until the 1st of June, when the plaintiffs again commenced to deliver ore under the contract, but the company rejected it in such quantity that they claimed the rejection to be improper, and a breach of the contract.

One of the suits was for the amount due for ore delivered iii the month of J une, and the other was for damages for breach of the contract.

The contract was in the form of a letter from the general manager of the company to Teaford, and accepted by him. It contained, among other provisions, the following:

“ Should your superintendent from any cause ship us a car of material that, according to the judgment of our washer foreman, be unfit to wash, this car is to be side-tracked until your superintendent-can go and look at it, and the two are to decide what is best to be done about this car, that is, whether it shall he dumped and thrown away, or washed, to arrive at its true value in comparison with the other cars.”

On the trial, the plaintiffs introduced testimony to prove the damages resulting to them from the delay of the company in resuming operations, thereby-preventing them from delivering any ore between the 17th of February and the 1st of June. [375]*375The defendant objected to the testimony, but the court overruled its objection and admitted the testimony. The admission of this evidence is the subject of the first bill of exception, and constitutes the first assignment of error.

The general manager of the company informed the plaintiffs of the injury to the pump, and assured them that a new one would be procured in five or six days, and the work proceed. Time went on, but the place of the broken pump was not supplied, nor the work resumed. Assurance was again and again given, when complaint of the delay was made, that the pump would be soon procured, whereby the plaintiffs were kept in a state of expectation and comparative idleness, waiting for the resumption of operations. After a delay of more than three months, extending from the 17th of [February to the last of May, a second-hand pump belonging to the president of the defendant company, which had been used by him in a coal shaft, was brought, and work resumed, but this was not done until the president had purchased a tract of land in the vicinity containing iron ore, and the company had built a railroad to it of several miles, and gotten ready to mine and manufacture ore from it. Evidence had been introduced tending to prove that the long delay in procuring another pump and resuming work was unnecessary and unreasonable. Under these circumstances, evidence was admissible to show that the plaintiffs had suffered loss from the delay, and the court did not err in overruling the objection of the defendant.

The next assignment of error relates to the admission of testimony to prove that the ore in the cars which were sidetracked in June by order of the washer foreman was such as should have been received, and that it was improperly rejected. The propriety of admitting the testimony is very clear. The washer foreman and the superintendent had been unable to agree as to the ore. No provision had been made in the contract, in case of disagreement between the washer foreman and the superintendent, with respect to ore in cars that [376]*376should be side-tracked by order of the washer foreman on account of its unfitness, in his judgment, to be washed. In the absence of any such provision, the propriety of the rejection of the ore had to be settled in some other way. The company declined to arbitrate the matter, and there was no other way of settling it than by a resort to the tribunals of the land established for the adjudication of the rights of parties, and the settlement of controversies. The jury could not decide the question of fact in issue except upon evidence as to the character of the ore. Clearly, evidence for’ this purpose was pertinent and admissible. The case is wholly unlike that of Condon v. S. S. R. Co., 14 Gratt. 302, relied upon by the plaintiff in error, and plainly distingushable from it. In that case the contract made the engineer of the railroad company the sole arbiter of all questions of law or fact arising under the contract. By its express terms his decision was to be “ obligatory and conclusive between the parties, without further recourse of appeal.” But in this case the washer foreman was not the sole judge or final arbiter of any dispute as to the ore. He had merely the power to have side-tracked any car containing material which he regarded as unfit to be washed, but its subsequent and final disposition was to be determined by the concurrent judgment of himself and the superintendent. He alone could not decide against its acceptance. If they differed' as to the ore in any car which had been side-tracked, the contract not providing for such a contingency, the result was the same with respect to that particular ore as if no provision had been made in the contract for deciding a dispute as to any ore rejected by the company. In such case, if the parties could not agree upon some other mode of settling the dispute, resort must necessarily be to the courts, and the matter be there determined upon evidence as to the character of the rejected ore.

After the plaintiffs had concluded their testimony and rested their case, the counsel of the defendant moved the court to strike out all the testimony of the plaintiffs tending to show [377]*377loss during the cessation of the work from the 17th of February to the 1st of June, and also all testimony tending to show the judgment of other parties than the washer foreman as to the character of the ore rejected by him, and to exclude all of the said evidence from the consideration of the jury. The court rightly overruled the motion. The evidence was, as we have seen, properly admitted by the court, and being so admitted, the jury were entitled to consider it.

Upon the conclusion of all the testimony, the defendant offered ten instructions, which it asked to be given to the jury. The court refused to give the instructions or any of them, and gave instead three instructions for the plaintiffs, and two for the defendant. The refusal of the court to give the ten instructions asked for by the defendant, and the giving of instructions 1, 2, and .3, for the plaintiffs, constitute the next assignment of error. The court committed no error with respect to the instructions refused or given.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. I. duPont deNemours & Co. v. Universal Moulded Products Corp.
62 S.E.2d 233 (Supreme Court of Virginia, 1950)
Lawson v. Southwestern Voluntary Ass'n
191 S.E. 648 (Supreme Court of Virginia, 1937)
Shenandoah Milling Co. v. Phosphate Products Corp.
171 S.E. 681 (Supreme Court of Virginia, 1933)
Tidewater Plumbing Supply Co. v. Emory Foundry Co.
127 S.E. 87 (Supreme Court of Virginia, 1925)
Palmer v. Charles E. Frosst & Co.
123 S.E. 357 (Supreme Court of Virginia, 1924)
Lehigh Portland Cement Co. v. Virginia Steamship Co.
111 S.E. 104 (Supreme Court of Virginia, 1922)
Atlantic Coast Line Railroad Co. v. A. M. Walkup Co.
112 S.E. 663 (Supreme Court of Virginia, 1922)
Raven Red Ash Coal Co. v. Herron
75 S.E. 752 (Supreme Court of Virginia, 1912)
Whitehead v. Syndicate
68 S.E. 263 (Supreme Court of Virginia, 1910)
Coburn v. California Portland Cement Co.
77 P. 771 (California Supreme Court, 1904)
Occidental Consolidated Min. Co. v. Comstock Tunnel Co.
125 F. 244 (U.S. Circuit Court for the District of Nevada, 1903)
American Hide & Leather Co. v. Chalkley & Co.
44 S.E. 705 (Supreme Court of Virginia, 1903)
Consumers Ice Co. v. Jennings
42 S.E. 879 (Supreme Court of Virginia, 1902)
Grubb v. Burford
37 S.E. 4 (Supreme Court of Virginia, 1900)
Womack v. Circle
29 Va. 192 (Supreme Court of Virginia, 1877)
Norfolk & Petersburg R. R. v. Ormsby
27 Va. 455 (Supreme Court of Virginia, 1876)

Cite This Page — Counsel Stack

Bluebook (online)
31 S.E. 525, 96 Va. 372, 1898 Va. LEXIS 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alleghany-iron-co-v-teaford-va-1898.