All Star Const. Co., Inc. v. Koehn

2007 SD 111, 741 N.W.2d 736, 2007 S.D. LEXIS 176
CourtSouth Dakota Supreme Court
DecidedOctober 31, 2007
Docket24405, 24413
StatusPublished
Cited by28 cases

This text of 2007 SD 111 (All Star Const. Co., Inc. v. Koehn) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All Star Const. Co., Inc. v. Koehn, 2007 SD 111, 741 N.W.2d 736, 2007 S.D. LEXIS 176 (S.D. 2007).

Opinion

*739 BARNETT, Circuit Judge.

[¶ 1.] All Star Construction Company, Inc., (All Star) appeals from a judgment ordering it to “specifically perform under the terms of the contract and complete the punch list items set forth in Exhibit 118 as revised from time to time on the record, as well as the reconstruction and repair of the showerf.]” The judgment also ordered Mark Koehn and Alicia Garcia (Homeowners) to “specifically perform under the terms of the contract and pay to [All Star] the sum of $56,516.81 as the reasonable value of the work completed and not yet paid.”

[¶ 2.] We affirm in part, reverse in part, and remand.

FACTS AND PROCEDURAL HISTORY

[¶ 3.] Homeowners are practicing attorneys in Rapid City, South Dakota. They decided to remodel their home and build an addition to it. They contacted All Star and, on November 1, 2002, signed a form contract provided by All Star. The contract contemplated that some items listed in the contract were allowances or estimates. While figures were listed in the contract for these items, the contract also stated that “estimates are provided for budgeting purposes only. More accurate pricing can be provided when design and construction details have been furnished.” Additionally, the contract stated that “[a]llowance figures are included as actual costs to the contractor. Final job expenses will be adjusted accordingly.” (emphasis supplied). Notably, the contract did not define actual costs.

[¶ 4.] In the contract All Star warranted that all work would be completed in a workmanlike manner according to standard practices. The contract provided that “any alteration or deviation from above specifications including extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate.” (emphasis supplied).

[¶ 5.] The base contract price was $122,500 plus excise taxes. Approximately $51,000 of this total was denominated as allowances, which could be revised when changes were ordered by Homeowners, or as costs increased over the stated allowances. All Star later claimed a fifteen percent markup for overhead as an actual cost, and later reduced the markup claim to eight percent. Neither figure appears in either the contract or the change orders. Furthermore, All Star admitted that neither markup had ever been discussed with Homeowners during construction.

[¶ 6.] Throughout the course of the project Homeowners requested changes in the plan and details. On four occasions All Star presented Homeowners with a written change order, which they signed. The change orders described generally what caused the extra bill, but did not specify whether an eight percent markup had been added in. The change orders simply listed labor and materials. A fifth change order was presented after the work was completed, and was not signed by Homeowners. At trial Homeowners conceded that the amount listed on the fifth change order was due and owing, with the exception of a possible unstated eight percent markup. To further complicate matters, other changes were requested or approved by Homeowners, and performed by All Star, yet neither side presented or demanded a written change order at the time.

[¶ 7.] All Star admitted at trial that it was required to secure a signed change order in every instance, and that it did not do so in all cases. However, All Star contended, and the trial court agreed, that in such instances Homeowners were present and living in the home and not only *740 requested the changes, but acquiesced despite the lack of a written change order.

[¶ 8.] In mid-2003 Homeowners were significantly behind in payments owed under the contract due to problems securing adequate financing. About this time, Homeowners hosted a family reunion and asked that All Star leave the jobsite. Due to the arrearages, All Star did not return to the home after the reunion, nor were they asked by Homeowners to come back. Homeowners did obtain some additional financing and were able to pay $90,000; however, this left almost $60,000 still owing. For two years there was no final construction or payment. Homeowners submitted a “punch list,” a list of finishing work that was not completed. All Star admitted that some of the finishing work was in fact not completed, but argued that its nonperformance was excused by Homeowners’ nonpayment. Additionally, the parties agreed that an expensive waterfall shower leaked, though they could not agree on the cause. Eventually All Star sued for payment under the contract. Homeowners sought an offset for unfinished or non-workmanlike efforts.

[¶ 9.] The case was heard at a court trial. After all evidence had been submitted, the trial court ruled from the bench. The trial court asked Homeowners if they wanted to amend their answer to seek specific performance. Homeowners so moved. The motion was granted over All Star’s objection. The trial court ordered All Star to go back in the home, fix the leaking shower, and complete the work listed on the punch list. The trial court further ordered the Homeowners to “spe■cifically perform” their part of the contract, by paying All Star $56,581.86. All Star sought prejudgment interest under SDCL 21-1-13.1. However, the trial court denied this claim on the ground that it had not awarded damages, but had instead awarded specific performance of $56,581.86.

[¶ 10.] The trial court denied All Star’s claim for an eight percent markup on any changes which were approved by Homeowners but not evidenced by a written change order. The written change orders do not specify whether they contain an eight percent markup. It is unclear whether the court intended that Homeowners be responsible for such a charge on the written change orders. Homeowners contend that they stipulated to all charges in the five change orders, except for any unstated eight percent markup.

[¶ 11.] All Star raises four issues on appeal:

Whether the trial court erred in ordering All Star to specifically perform under the contract.
Whether the trial court erred in failing to award prejudgment interest to All Star.
Whether All Star is entitled to an eight percent markup on labor and materials charged under change order number five.
Whether All Star is entitled to eight percent overhead or markup on the allowance overruns under the contract.

[¶ 12.] Homeowners filed a notice of review and raise one issue:

Whether Homeowners waived the requirement that all changes be in writing.

STANDARD OF REVIEW

[¶ 13.] We review the trial court’s findings of fact under the clearly erroneous standard. City of Deadwood v. Summit, Inc., 2000 SD 29, ¶ 9, 607 N.W.2d 22, 25. “Conclusions of law are reviewed under a de novo standard, giving no deference to the circuit court’s conclusions of law.” Id. The equitable remedy of specific performance is addressed to the sound *741

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murphey v. Pearson
981 N.W.2d 410 (South Dakota Supreme Court, 2022)
In re Estate of Radford
297 Neb. 748 (Nebraska Supreme Court, 2017)
Roseth v. Roseth
2013 S.D. 27 (South Dakota Supreme Court, 2013)
Gail M. Benson Living Trust v. Physicians Office Building, Inc.
2011 SD 30 (South Dakota Supreme Court, 2011)
Union Pacific Railroad v. CERTAIN UNDERWRITERS AT LLOYD'S LONDON
2009 SD 70 (South Dakota Supreme Court, 2009)
Gettysburg School District 53-1 v. Helms and Associates
2008 SD 35 (South Dakota Supreme Court, 2008)
Lamore Restaurant Group, LLC v. Akers
2008 SD 32 (South Dakota Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 SD 111, 741 N.W.2d 736, 2007 S.D. LEXIS 176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-star-const-co-inc-v-koehn-sd-2007.