STATE OF VERMONT SUPERIOR COURT – ENVIRONMENTAL DIVISION

{ In re All Metals Recycling, Inc. { Docket No. 171-11-11 Vtec Discretionary Permit Application { {

Decision on Cross-Motions for Summary Judgment and Motion to Amend Statement of Questions Before us is an application for a discretionary zoning permit seeking approval for Appellee All Metals Recycling, Inc. (All Metals) to establish an outdoor storage area and install a scale house and scale at 38-42 Dorset Lane in the Town of Williston, Vermont to conduct what the application terms a “metals recycling operation.” Appellee Riggs Properties and Interested Person the Town of Williston, Vermont (the Town) are owners of the subject property on which All Metals seeks to conduct its proposed project. After a hearing, the Town of Williston Development Review Board (the DRB) granted the permit with conditions. Darlene Ashley, John Chandler, James Babcock, Jennifer Ashley, William Babcock, Shawn Chapman, William Burnett, Jeannine Burnett, Patty Shortsleeves, George Shortsleeves, Gary Boutin, Michael Burnett, and Mark Burnett (Neighbors) appeal the DRB’s decision and have filed an amended Statement of Questions including ten questions, five of which remain for this Court’s review.1 Now pending before the Court are All Metals’ motion for summary judgment on Neighbors’ Questions 3–5; the Town’s motion for summary judgment on Neighbors’ Question 10; Neighbors’ cross-motion for summary judgment on all questions; and Neighbors’ second motion to amend their Statement of Questions. All Metals is represented by Robert F. O’Neill, Esq. Neighbors are represented by Hobart F. Popick, Esq. The Town is represented by Paul S. Gillies, Esq.

Factual Background For the sole purpose of putting the pending motions into context, we recite the following facts, which we understand to be undisputed unless otherwise noted: 1. All Metals maintains a place of business at 38-42 Dorset Lane, Williston, Vermont (the Williston facility).

1In an April 2012 decision, we disposed of Neighbors’ original Questions 1, 2, 6, 7, and 9, and we granted Neighbors’ motion to amend their Statement of Questions to include a Question 10. In re All Metals Recycling, Inc., No. 171-11-11 Vtec, slip op. at 11–12 (Vt. Super. Ct. Envtl. Div. Apr. 23, 2012) (Walsh, J.).

1 2. The Williston facility is located in the Town’s Gateway Zoning District North (GDZN District). 3. The majority of the Williston facility consists of a portion of a commercial building and associated grounds which All Metals sub-leases from ReSOURCE: A Nonprofit Community Enterprise, Inc. (ReSource). 4. All Metals is one of three tenants in the 38-42 Dorset Lane building. In total, All Metals occupies roughly 10 to 15% of the 1800-square foot building, or between 180 and 270 square feet. 5. All Metals occupies two interior areas of the building, including a small office and a processing room containing hydraulic shears, mechanized Sawzall saws, and a platform scale. 6. All Metals also leases exterior space from ReSource, including parking space.2 Nevertheless, All Metals’ employees sometimes park outside of the premises leased by All Metals, including to the east side of the building. 7. Additionally, approximately 30% of the land occupied by All Metals is owned by the Town of Williston. On May 7, 2012, All Metals entered into a written lease with the Town authorizing All Metals’ use of the Town’s land. 8. Three All Metals employees work at the Williston facility. 9. All Metals advertises its services at the Williston facility to the general public. 10. The Williston facility is open for business from 8 a.m. to 4 p.m. Monday to Friday and 8 a.m. to 1 p.m. on Saturday. 11. The Williston facility services between 5 and 10 customers per day, and each customer visit typically lasts between 15 and 20 minutes. In the past, when the facility is busy, up to 3 customers may be at the facility at one time—one in process and two awaiting service. 12. At the Williston facility, All Metals purchases scrap metals from individuals and businesses for resale to third parties. All Metals does not accept garbage or trash at the Williston facility.

2 All Metals formally amended its sublease agreement with ReSource on November 29, 2012 to confirm that All Metals has 10 parking spaces available to it within the area subleased by All Metals. However, Neighbors still dispute whether sufficient parking actually exists inside All Metals’ rented premises. See (Resp. to All Metals’ Supplemental Statement of Material Facts at 4, filed Dec. 20, 2012.)

2 13. Trucks bearing metals arrive at the facility and are weighed and then unloaded. The trucks are then weighed again while empty. In some cases, All Metals will pick up a customer’s scrap metal and haul it to the Williston facility. 14. At the Williston facility, All Metals sorts and aggregates the metals it purchases. All Metals aggregates the scrap metal so that it may be shipped in a cost-effective manner. Aggregation may include trimming the metals using hydraulic shears and mechanized Sawzall saws and compacting the metals using a mechanized compactor. The aggregation process may also include the use of a tandem excavator and a skid steer. 15. Once the metals are sorted and aggregated, All Metals trucks the metals to either its location in Hardwick, Vermont or directly to a purchaser. All Metals sells the metals to customers who are not “end users,” but who include mills, processors, and refiners. 16. Prior to the filing of the permit application at issue in this case, All Metals conducted its business at the Williston facility without a permit from the Town. 17. On September 9, 2011, Sanborn, Head & Associates, on behalf of All Metals, submitted a discretionary permit application to the Town Zoning Administrator to “[e]stablish an outdoor storage area and install a scale house and scale to accommodate [the] existing metals recycling operation.” (Neighbors’ Exhibit B at AMR 9, 11, filed Oct. 22, 2012.)3 The permit application identified All Metals as the “Facility Operator.” Id. at AMR 11. 18. On October 25, 2011, the DRB considered and approved the discretionary permit application.

Motions for Summary Judgment Presently before the Court are All Metals’ motion for summary judgment on Neighbors’ Questions 3–5, the Town’s motion for summary judgment on Neighbors’ Question 10, and Neighbors’ cross-motion for summary judgment on all remaining questions in Neighbors’ Statement of Questions. We will grant summary judgment to a moving party upon a showing that “there is no genuine dispute as to any material fact and the movant is entitled to judgment

3 In our April 23, 2012 decision, we noted that under the Bylaw, the term “applicant” only refers to the owner or owners of the property on which development is proposed. All Metals, No. 171-11-11 Vtec, slip op. at 7–8. Thus, All Metals, even with a leasehold interest in the property at issue in this case, is not an applicant under the Bylaw. Id. We nevertheless understand from the permit application and attachments that All Metals, not Riggs Properties or the Town, will conduct the proposed activities and that the permit application was submitted by consultants retained by All Metals with the signed consent of Riggs Properties and the Town. (Neighbors’ Exhibit B at AMR 9, 11, filed Oct. 22, 2012.)

3 as a matter of law.” V.R.C.P. 56(a); V.R.E.C.P. 5(a)(2). We must “accept as true the [factual] allegations made in opposition to the motion for summary judgment” and give the non-moving party the benefit of all reasonable doubts and inferences. Robertson v. Mylan Labs., Inc., 2004 VT 15, ¶ 15, 176 Vt. 356 (internal citations omitted); see V.R.C.P. 56(c) (laying out summary judgment procedures).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Burlington v. Fairpoint Communications, Inc.
2009 VT 59 (Supreme Court of Vermont, 2009)
Robertson v. Mylan Laboratories, Inc.
2004 VT 15 (Supreme Court of Vermont, 2004)
Toys, Inc. v. F.M. Burlington Co.
582 A.2d 123 (Supreme Court of Vermont, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
All Metal Recycling, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-metal-recycling-inc-vtsuperct-2013.