All American Excavation, Inc. v. Austin Materials, LLC

CourtCourt of Appeals of Texas
DecidedApril 13, 2016
Docket04-15-00779-CV
StatusPublished

This text of All American Excavation, Inc. v. Austin Materials, LLC (All American Excavation, Inc. v. Austin Materials, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All American Excavation, Inc. v. Austin Materials, LLC, (Tex. Ct. App. 2016).

Opinion

Fourth Court of Appeals San Antonio, Texas MEMORANDUM OPINION Nos. 04-15-00779-CV; 04-15-00780-CV; 04-15-000781-CV & 04-15-00782-CV

ALL AMERICAN EXCAVATION, INC., Appellant

v. AUSTIN AUSTIN MATERIALS, LLC d/b/a Ramming Paving Company, Appellee

From the 131st Judicial District Court, Bexar County, Texas Trial Court Nos. 2015-CI-10299; 2015-CI-10743; 2015-CI-13685 & 2015-CI-11880 Honorable Antonia Arteaga, Judge Presiding

Opinion by: Sandee Bryan Marion, Chief Justice

Sitting: Sandee Bryan Marion, Chief Justice Karen Angelini, Justice Luz Elena D. Chapa, Justice

Delivered and Filed: April 13, 2016

REVERSED AND REMANDED

All American Excavation, Inc. (“AAE”) appeals the trial court’s order in each of the

underlying causes denying its motion to abate and compel arbitration. AAE contends the trial

court erred in denying its motion to compel arbitration because AAE established as a matter of law

the claims asserted against it in the underlying causes by Austin Materials, LLC d/b/a Ramming

Paving Company were within the scope of a valid arbitration agreement. AAE further contends

the trial court erred in failing to abate the underlying causes pending the arbitration. We reverse

the trial court’s orders. 04-15-00779-CV; 04-15-00780-CV; 04-15-00781-CV & 04-15-00782-CV

FACTUAL AND PROCEDURAL BACKGROUND

In 2013, AAE and Ramming Paving entered into a Subcontract Agreement containing

general provisions applicable to work to be performed by Ramming Paving for AAE. The work

was generally described as asphalt paving, seal coat and striping services. The Subcontract

Agreement stated that the owner, architect, and contract price would be determined by individual

purchase orders. The Subcontract Agreement contained a broad arbitration provision

encompassing “any dispute, controversy or claim” between the parties.

In 2015, Ramming Paving filed the underlying lawsuits against AAE claiming AAE had

failed to pay Ramming Paving for various services and materials it had provided on four

construction projects. AAE filed counter-claims asserting no amounts were due because of offsets

and back charges for defective work. In addition, AAE filed a motion to compel arbitration and

abate in each lawsuit.

On November 20, 2015, the trial court conducted a hearing on AAE’s motions. At the

hearing, AAE presented an affidavit from its President in each lawsuit. Ramming Paving

presented argument during the hearing regarding various reasons the Subcontract Agreement and

the arbitration provision contained therein were unenforceable, including lack of consideration or

mutuality and absence of specificity or detail. The trial court took the matter under advisement at

the conclusion of the hearing. After the hearing, both parties filed letter briefs further clarifying

their arguments. The trial court subsequently signed orders denying AAE’s motions, and AAE

now appeals.

VALIDITY OF AGREEMENT

“A party attempting to compel arbitration must first establish that the dispute in question

falls within the scope of a valid arbitration agreement.” J.M. Davidson, Inc. v. Webster, 128

S.W.3d 223, 227 (Tex. 2003). “If the other party resists arbitration, the trial court must determine -2- 04-15-00779-CV; 04-15-00780-CV; 04-15-00781-CV & 04-15-00782-CV

whether a valid agreement to arbitrate exists.” Id. Ordinary principles of state contract law

determine whether a valid agreement to arbitrate exists. G.T. Leach Builders, LLC v. Sapphire

V.P., LP, 458 S.W.3d 502, 524 (Tex. 2015). If the evidence establishes a valid agreement, “the

burden shifts to the party opposing arbitration to raise an affirmative defense to enforcing

arbitration.” J.M. Davidson, Inc., 128 S.W.3d at 227. “The trial court’s determination of the

arbitration agreement’s validity is a legal question subject to de novo review.” Id.

AAE contends it proved the validity of the agreement; therefore, the trial court erred in

denying its motions to compel arbitration. Ramming Paving responds the agreement is not an

enforceable contract because its terms were too indefinite and the agreement was not supported by

consideration.

A. Indefiniteness of Subcontract Agreement

Ramming Paving contends the Subcontract Agreement lacks specificity because it refers

to documents in an exhibit which is not attached, refers to a purchase order which was not

introduced into evidence, and does not specify the required retainage. AAE responds the

Subcontract Agreement is a typical master agreement containing general terms which govern the

parties’ legal relationship upon the subsequent execution and acceptance of a purchase order or

other similar request for work or services on a specific project.

Generally, “[i]n order to be legally binding, a contract must be sufficiently definite in its

terms so that a court can understand what the promisor undertook.” T.O. Stanley Boot Co. v. Bank

of El Paso, 847 S.W.2d 218, 221 (Tex. 1992). In the context of a master service agreement

between a contractor and a subcontractor, the master service agreement is not sufficiently definite

to bind either party to perform any services. Moser v. Aminoil, USA, Inc., 618 F. Supp. 774, 779

(W. Dist. La. 1985). The master service agreement “merely sets forth [the parties’] agreement to

abide by certain terms should they enter into contractual relations in the future.” Id. Once the -3- 04-15-00779-CV; 04-15-00780-CV; 04-15-00781-CV & 04-15-00782-CV

contractor requests the services of the subcontractor, however, the request provides the remaining

material terms, and “the terms of the master service agreement are incorporated automatically into

the written or verbal contract to perform the specified services.” Id.

“The law favors finding agreements sufficiently definite for enforcement,” particularly

where services have been provided under the contract for which compensation was to be paid.

America’s Favorite Chicken Co. v. Samaras, 929 S.W.2d 617, 623 (Tex. App.—San Antonio

1996, writ denied). “Where the evidence shows that the parties intended to enter into an

agreement, the courts should find the contract to be definite enough to grant a remedy provided

that there is a certain basis for determining the remedy.” Id.

In this case, the Subcontract Agreement provided the general terms that would govern any

asphalt paving, seal coat and striping services Ramming Paving provided to AAE. The remaining

material terms, including the identity of the specific project and the pricing terms, were to be

provided in a subsequent purchase order exchanged between the parties. Once AAE and Ramming

Paving agreed to the terms in a subsequent purchase order, the purchase order and the Subcontract

Agreement together would provide all material terms, thereby forming an enforceable contract.

During the hearing before the trial court, Ramming Paving referenced the Houston court’s

decision in ODL Servs., Inc. v. ConocoPhillips Co., 264 S.W.3d 399 (Tex. App.—Houston [1st

Dist.] 2008, no pet.), which it also cites in its brief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
In Re AdvancePCS Health L.P.
172 S.W.3d 603 (Texas Supreme Court, 2005)
In Re Palm Harbor Homes, Inc.
195 S.W.3d 672 (Texas Supreme Court, 2006)
In Re Merrill Lynch Trust Co. FSB
235 S.W.3d 185 (Texas Supreme Court, 2007)
In Re 24R, Inc.
324 S.W.3d 564 (Texas Supreme Court, 2010)
Henry v. Gonzalez
18 S.W.3d 684 (Court of Appeals of Texas, 2000)
Sheshtawy v. Sheshtawy
150 S.W.3d 772 (Court of Appeals of Texas, 2004)
America's Favorite Chicken Co. v. Samaras
929 S.W.2d 617 (Court of Appeals of Texas, 1996)
ODL Services, Inc. v. ConocoPhillips Co.
264 S.W.3d 399 (Court of Appeals of Texas, 2008)
Moser v. Aminoil, U.S.A., Inc.
618 F. Supp. 774 (W.D. Louisiana, 1985)
950 Corbindale, L.P. v. Kotts Capital Holdings Ltd. Partnership
316 S.W.3d 191 (Court of Appeals of Texas, 2010)
Federal Sign v. Texas Southern University
951 S.W.2d 401 (Texas Supreme Court, 1997)
T.O. Stanley Boot Co. v. Bank of El Paso
847 S.W.2d 218 (Texas Supreme Court, 1993)
Robert Marx and Debbie Marx v. Fdp, Lp
474 S.W.3d 368 (Court of Appeals of Texas, 2015)
G.T. Leach Builders, LLC v. Sapphire V.P., Lp
458 S.W.3d 502 (Texas Supreme Court, 2015)
Guillermo Garza D/B/A Wilhome Builders & Construction v. Jesse Cantu
431 S.W.3d 96 (Court of Appeals of Texas, 2013)
Cleveland Construction, Inc. v. Levco Construction, Inc.
359 S.W.3d 843 (Court of Appeals of Texas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
All American Excavation, Inc. v. Austin Materials, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-american-excavation-inc-v-austin-materials-llc-texapp-2016.