Algonquin Lng, Inc. And Algonquin Gas Transmission Company v. Federal Energy Regulatory Commission

570 F.2d 1043, 187 U.S. App. D.C. 134, 1978 U.S. App. LEXIS 12901
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 26, 1978
Docket76-2157
StatusPublished
Cited by3 cases

This text of 570 F.2d 1043 (Algonquin Lng, Inc. And Algonquin Gas Transmission Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Algonquin Lng, Inc. And Algonquin Gas Transmission Company v. Federal Energy Regulatory Commission, 570 F.2d 1043, 187 U.S. App. D.C. 134, 1978 U.S. App. LEXIS 12901 (D.C. Cir. 1978).

Opinion

Opinion for the Court filed by MARKEY, Chief Judge.

*1045 MARKEY, Chief Judge:

Appeal from Orders of the Federal Power Commission (now the Federal Energy Regulatory Commission) in Algonquin LNG, Inc., Docket No. CP75-14, affirming and adopting a Hearing Examiner’s decision requiring refunds of amounts collected in excess of a rate of $3.45 per barrel, and denying rehearing. We vacate the Orders and remand.

BACKGROUND

Algonquin, LNG, Inc. (Algonquin), a wholly-owned subsidiary of Algonquin Gas Transmission Co., owns and operates a 600,-000 barrel liquified natural gas (LNG) storage tank. On July 14, 1974, Algonquin filed with the Federal Power Commission (Commission) an application for a limited term certificate of public convenience and necessity under § 7 of the Natural Gas Act, as amended, 15 U.S.C. § 717f, 1 to store approximately 426,000 barrels of LNG 2 at $4.50 per barrel. The application included a “summary cost of service” and described that cost as “the derivation of the proposed rate.”

An order granting the certificate issued September 12, 1974. The certificate was set to expire May 1, 1975, was conditioned on a satisfactory showing that the $4.50 rate was in the public interest, and provided for a later formal hearing on that question.

The formal hearing was held October 29, 1974. Algonquin submitted the testimony of Teel, a consultant specializing in rate proceedings, and Jaques, vice president of Algonquin, and two exhibits. Counsel for the Commission cross-examined Teel and Jaques, but offered no evidence.

The initial decision of the Hearing Examiner issued February 28, 1975. The Commission order issued August 17, 1976, three months after termination of the storage service. Rehearing was denied on December 27, 1976.

ALGONQUIN’S ARGUMENTS

Algonquin contends: (1) the Commission lacks statutory authority to impose a confiscatory rate; (2) the Commission’s opinion lacks a finding of public convenience and necessity; (3) the Commission’s findings are contrary to the record; and (4) Algonquin was not accorded a fair hearing.

With respect to (1) Algonquin argues: (a) the $3.45 rate is below cost; (b) a below-cost rate is unjust, unreasonable and confiscatory; and (c) a confiscatory rate is contrary to the requirement of § 7(e) that all conditions be “reasonable.”

With respect to (2), Algonquin argues that there is no explanation of why the public convenience and necessity requires: *1046 (a) the $3.45 rate; (b) employment of the method by which that rate was derived; and (c) that Algonquin be denied recovery of its costs.

With respect to (3), the record, Algonquin argues: (a) the Commission’s evaluation of the $4.50 rate was contrary to the record in that the Commission used a “formula” it found in the application, when the evidence showed that $4.50 was a below-cost rate established solely on competitive considerations; and (b) the Commission calculated its $3.45 rate in a manner contrary to the record in that: (i) it employed a limited cost test it found in the application, but substituted different cost figures from Exhibit 1; (ii) it “justified” the calculation as derived from the “same method” as the application; (iii) its substitution of interest figures from Exhibit 1 was improper and contrary to the Uniform System of Accounts prescribed for natural gas companies; (iv) it erroneously assumed that Algonquin wished to recover “out-of-pocket” costs; (v) it ignored the record showing that even the $4.50 rate would not recover out-of-pocket costs; (vi) it excluded income taxes because they were not included in the application; (vii) it excluded income taxes because of an erroneous conclusion that there is no return in an out-of-pocket formula; (viii) it premised the $3.45 rate on sale of 600,000 barrels of storage space, when only 280,400 barrels were sold; and (ix) its own finding of out-of-pocket costs would not be met by a $3.45 rate, the unit cost per barrel being established in the record as $7.39.

With respect to (4), unfair hearing, Algonquin argues: (a) the application was not in evidence; (b) yet, without explanation or notice, it was bound by its application formula, in violation of Commission Rule 1.11(b), 18 C.F.R. § 1.11(b); and (c) the theory for reducing the $4.50 rate was first formally proposed in the Commission Staff’s post-hearing brief.

THE COMMISSION’S ARGUMENTS

The Commission contends: (1) the “just and reasonable” standard of §§ 4 and 5, 15 U.S.C. §§ 717c and d, does not apply to § 7; (2) the $4.50 rate was not in the public convenience and necessity; and (3) the refund order was proper.

With respect to (1), the Commission argues: (a) its duty is to hold initial rates to levels consistent with the public convenience and necessity pending determination in a future § 4 hearing that the rate is just and reasonable; (b) the Commission is not required by § 7 to find the initial rate just and reasonable; and (c) Algonquin’s rate was not shown to be required by public convenience and necessity.

With respect to (2), the Commission argues: (a) Algonquin’s “confiscatory” argument is an attempt to transfer the burden of proof; (b) Algonquin’s application involved a proposal to recover out-of-pocket expenses; (c) because Algonquin chose an out-of-pocket formula, it cannot include cost-of-service items, such as income taxes; (d) Algonquin departed at the hearing from the method of rate derivation in its application, without reasonable explanation or support; (e) the Commission used the sale of 600,000 barrels in calculating the rate because Algonquin used that figure in its application formula; and (f) the figures in Algonquin’s Exhibit 1 support the $3.45 rate.

With respect to (3), the Commission argues that Algonquin, having been on notice that a refund was possible and having accepted a refund-conditioned certificate, cannot argue that a refund is improper.

The Commission has not denied that its $3.45 rate is confiscatory; nor has it explained why the $3.45 rate is required by public convenience and necessity; nor has it responded to Algonquin’s contention that it was deprived of a fair hearing; nor has it argued that the $3.45 rate is adequate to meet Algonquin’s out-of-pocket costs.

ISSUE

The issue is whether the decision of the Commission is supported by substantial evidence.

OPINION

Section 7(c) of the Natural Gas Act requires that no transaction within the juris *1047 diction of the Commission be undertaken without a certificate of public convenience and necessity. Section 7(e) gives the Commission the power to attach “such reasonable

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
570 F.2d 1043, 187 U.S. App. D.C. 134, 1978 U.S. App. LEXIS 12901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/algonquin-lng-inc-and-algonquin-gas-transmission-company-v-federal-cadc-1978.