Algonquin Gas Transmission Co. v. New York State Thruway Authority

8 Misc. 2d 438, 168 N.Y.S.2d 117, 1957 N.Y. Misc. LEXIS 2172
CourtNew York Court of Claims
DecidedNovember 15, 1957
DocketClaim No. 32721
StatusPublished

This text of 8 Misc. 2d 438 (Algonquin Gas Transmission Co. v. New York State Thruway Authority) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Algonquin Gas Transmission Co. v. New York State Thruway Authority, 8 Misc. 2d 438, 168 N.Y.S.2d 117, 1957 N.Y. Misc. LEXIS 2172 (N.Y. Super. Ct. 1957).

Opinion

Richard S. Heller, J.

The claim as filed on July 30, 1954 sought recovery of damages on a number of grounds. By amendment and stipulation of the parties, the claim was limited to recovery of the expense of relocating a gas transmission pipe line under the provisions of section 346 of the Highway Law.

The pertinent provision of section 346 reads as follows: Telephone and telegraph wires, power transmission and gas, oil and water lines, conduits, cables of every kind and nature, that cross any thruway may, in the discretion of the superintendent of public works, be relocated in suitable facilities to be installed under or over and across any such thruway. The expense of such relocation and of installing such facilities shall be deemed to be part of the cost of the thruway. The work of such relocation may be done by the owner of such wires, lines, conduits and cables, and the superintendent of public works is hereby empowered to enter into an agreement with such owner for the performance of all or any part of the work of such relocation at the expense of the state. ’ ’

The State does not dispute the effect of this statutory provision as a modification of the common-law rule that utility companies maintain their services subject to the duty to relocate at their own expense. The State however, urges that under the statutory provision, the State can only be held liable for the cost of relocation where such relocation is made necessary by the public improvement. Here the State asserts that the relocation was made necessary by claimant’s negligence rather than by the public improvement.

Claimant obtained from the Federal Power Commission a certificate of convenience and necessity for the construction of a high-pressure gas transmission line from Lambertville, New Jersey to Boston, Massachusetts. The line was to furnish to New Jersey, New York and the New England area natural gas from the southwestern part of the United States for domestic and industrial consumption.

On or about January 22,1951 claimant entered into an agreement with Ford, Bacon & Davis, Inc., an internationally known firm of consulting engineers, for the design and supervision of construction of this high-pressure gas transmission pipe line. [440]*440Ford, Bacon & Davis, Inc. proceeded to carry out this contract and between December 26,1951 and June 11, 1952 rights of way either in the form of temporary and permanent easements or licenses with a yearly fee involved, were obtained over property in Rockland County in the village of Suffern and the village of Hillburn. These rights of way were obtained for the purpose of installing the pipe line which in this particular area was to run in a northeasterly direction from a State highway known as Route 17 to a State highway known as Route 59 crossing both highways and the Ramapo River. On April 17,1952 the Department of Public Works of the State of New York granted a permit for the installation of this pipe line under Routes 17 and 59 at locations designated by Ford, Bacon & Davis, Inc., acting as agents for the claimant.

About June, 1952 work was actually being carried on in this area consisting first of clearing and grading, trenching and finally laying the pipe line. At about the time this work commenced in June, 1952 a consulting engineer firm known as Clarke & Rapuano which had been employed by the Department of Public Works or the New York State Thruway Authority to design the New York State Thruway from the New Jersey line at Suffern north to the village of Harriman, became aware of the activities of the claimant in this case. Claimant’s agent was advised that it was contemplated that the New York Thruway would be constructed through this area and between. June and October 2, 1952 a number of conferences were had between employees of Ford, Bacon & Davis, Inc. and Clarke & Rapuano, all of which dealt with a number of problems involved in the relationship of the construction of the Thruway and the pipe line.

Up until October 1, 1952 Clarke & Rapuano were unable to furnish to claimant’s agent any definite information as to the precise location of the Thruway in this area although general information as to the proposed route and as to a proposed relocation of the Ramapo River was given to claimant’s agent.

On October 1, 1952 at a time when claimant’s agent was preparing for the last stages of the installation of the pipe line through this area, Clarke & Rapuano furnished a map dated September 17,1952 labelled an alignment plan of the interchange area and showing in general a proposed location for the Thruway. An engineer employed by Clarke & Rapuano drew in pencil on the map the proposed relocated channel for the Ramapo River.

At this point there is a direct conflict in the testimony of the engineer employed by Clarke & Rapuano and the engineer [441]*441employed by claimant’s agent. The representative of Clarke & Rapuano asserts that he did not indicate to the representative of claimant’s agent the elevation of the new proposed Ramapo channel but asserts that he told the representative of claimant’s agent generally where the new channel would run and how the elevation of the bed of that channel could be determined, namely by running a straight grade between two bridges some 4,000 feet apart. The representative of claimant’s agent asserts that he was given at that time a precise elevation for the new channel and that the pipe line was thereafter installed at an elevation placing the top of the pipe approximately four feet below the proposed elevation of the relocated river bed.

Thereafter claimant’s agent completed the installation of the pipe line in this area generally at a greater depth below ground level than normal in order to protect the pipe line from any possibility of exposure and from any possible damage which might result from the heavy construction equipment which would be used in the construction of the Thruway.

About February, 1953, after a number of requests, claimant furnished to Clarke & Rapuano a so-called “ as built ” plan of the pipe line in this area so that in the design of the Thruway Clarke & Rapuano would have detailed information concerning the pipe line. The furnishing of this as built” plan was delayed due to certain difficulties which claimant encountered, having no relevancy to this claim but which had resulted in a discontinuance of work with consequent limitation of personnel available to complete the ‘‘ as built ’ ’ plan. Thereafter Clarke & Rapuano requested information as to the easements and rights of way owned or possessed by claimant and this information was furnished.

The final plans made by Clarke & Rapuano were completed on July 30,1953 and finally approved by the Thruway Authority on August 24, 1953. In September, 1953 claimant’s pipe line including the area in question here was placed in service and utilized to supply gas for domestic and industrial purposes.

Between October 2, 1953 and March 5, 1954 the Department of Public Works appropriated property for Thruway purposes in this area by filing notices in the Department of State and between September 21,1954 and October 21,1954 title vested by filing in the appropriate County Clerk’s office.

In March, 1954 a new channel had been dredged for the relocation of the Ramapo River and it was discovered that the pipe line as installed projected about a foot and a half above the bed of the relocated river.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glanzer v. . Shepard
135 N.E. 275 (New York Court of Appeals, 1922)
H. R. Moch Co. v. Rensselaer Water Co.
159 N.E. 896 (New York Court of Appeals, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
8 Misc. 2d 438, 168 N.Y.S.2d 117, 1957 N.Y. Misc. LEXIS 2172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/algonquin-gas-transmission-co-v-new-york-state-thruway-authority-nyclaimsct-1957.