Algernon Blair Group, Inc. v. United States Fidelity & Guaranty Co.

821 F.2d 597
CourtCourt of Appeals for the Eleventh Circuit
DecidedJuly 15, 1987
DocketNo. 86-7611
StatusPublished
Cited by1 cases

This text of 821 F.2d 597 (Algernon Blair Group, Inc. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Algernon Blair Group, Inc. v. United States Fidelity & Guaranty Co., 821 F.2d 597 (11th Cir. 1987).

Opinion

HILL, Circuit Judge:

USF & G insured a block of three buildings owned by appellee, Algernon Blair Corp, Inc. (“Algernon”) for $5,000,000. The buildings were located next to each other on a single block in Nashville, Tennessee. On October 12, 1985, the property was substantially damaged by a fire. Algernon Blair notified its insurance carrier, U.S. Fidelity and Guaranty (“USF & G”), of the loss. Two days later, on October 14, an on-site meeting took place between Alger-non officials, Mr. James M. Anglea, supervisor of building inspections for the Metropolitan Government of Nashville and Davidson County, (“Metro Government”) representatives of the Nashville Fire Department, and a claims adjuster representing USF & G. At the meeting Mr. Angela [599]*599advised the parties that the subject property was so substantially damaged as to constitute a health hazard to the public. Accordingly, he ordered Algernon to barricade the area and to demolish the remaining structures. He followed up this verbal order with a letter dated October 14, 1985. The pertinent parts stated as followed:

As the result of a recent fire at the above referenced location, it has been determined by a visual inspection made by this department on October 14, 1985 that the buildings are substantially damaged and a hazard to the public.
You are therefore notified to demolish the remaining structures, and further to make safe the area by barricades or other methods approved by this department before any work begins.
This demolition should begin not later than October 28, 1985, and be completed within ninety (90) days. Furthermore, there exists dangerous conditions caused by partial collapse of some walls leaving other high standing walls that need to be leveled to the ground immediately. You are directed to correct these conditions as soon as possible but not later than October 28, 1985.

Algernon promptly employed a wrecking company to barricade the area and begin demolition of the remaining structures.

On October 18, 1985, prior to the commencement of any demolition work, USF & G obtained a temporary restraining order from the Chancery Court for Davidson County, Tennessee. The order temporarily forbade Algernon, the wrecking company, or the local government authorities from “destroying, tearing down, moving, or tampering with the structures remaining or rubble remaining as a result of the fire,” so as to enable USF & G to complete its investigation. By its terms, the restraining order remained in effect from October 18 to October 25.

In obtaining this ex parte TRO, USF & G contended that the buildings were not in danger of collapse and that they did not constitute a hazard to the safety of the public. However, USF & G did not challenge the validity of the Metro Government demolition order, nor did it seek to stay the demolition beyond the expiration of the TRO on October 25. Moreover, USF & G never requested Algernon Blair to resist or challenge the Metro demolition order, to appeal it, or to take any action to have the Metro Government’s demolition order rescinded.

On October 24, Algernon Blair submitted a letter to USF & G which stated in relevant part:

Please regard this letter as the proof of loss by Algernon Blair Group, Inc. and a formal demand for payment by U.S.F. & G in the amount of $5,000,000 for the total loss of the property which U.S.F. & G insured in Nashville, Tennessee. If you wish us to supplement this proof of loss on some form from your company, please promptly furnish us with your form.
The Nashville Supervisor of Building Inspections has determined that the remaining structures “are a hazard to the public” and ordered that we “demolish the remaining structures, and further to make safe the area by barricades____” Your company has secured an order from the Nashville court restraining us and the City and our demolition contractor from doing this work. Of course, if any person is injured or property is damaged as a result thereof, we regrettably have to expect your company ... to indemnify us completely____

On October 25, the date on which the restraining order would expire, USF & G informed the other parties that it would not seek an extended injunction.

At this point a new group entered the controversy. Representatives of Historic Nashville, Inc. told the court handling USF & G’s TRO that they were prepared to file a lawsuit of their own, or to intervene in USF & G’s lawsuit, to prevent demolition of the facades of the burned structures. The preservation group felt that the facades facing on Second Avenue were of historical significance.

In order to avoid this additional complication, the Metro Government agreed to take out a temporary $1,000,000 liability policy [600]*600to protect Algernon Blair from any harm caused to the public by the hazard its buildings created. The Metro Government then gave the preservation group until November 6 to raise enough money to make the facade structurally sound. However, during this time the Metro Government’s demolition order remained in effect, so Alger-non began to clear the remains of the burned structures, other than the facades. When Historic Nashville failed to raise the necessary funds by November 6, Algernon Blair completed the demolition of all remaining structures, including the Second Avenue facades.

By letter dated November 7, USF & G informed Algernon Blair that its letter of October 24 was insufficient as a proof of loss, and asked Algernon to submit a USF & G form for proof of loss. Appellant complied with this request on or about November 19, again making a claim for the $5,000,000 face amount of the policy. In response to this demand, USF & G offered Algernon Blair $3,205,000, which it contended was the full amount of the loss sustained. This offer was rejected, and Algernon Blair filed suit in state court to recover the full amount of the policy. The case was then removed to federal district court for the middle district of Alabama. The district court granted summary judgment in favor of Algernon Blair. In a separate order dated August 18, 1986, the court awarded Algernon prejudgment interest pursuant to Tennessee laws. USF & G now appeals.

DISCUSSION

Neither party contests the fact that if the subject property was a total loss then USF & G owes Algernon the full value of the $5,000,000 policy. The question raised on this appeal is whether the Metro Government’s demolition order rendered the subject property a constructive total loss at law.

According to the documents filed in district court, at that level USF & G argued that the Metro Government erred in determining that the buildings were a total loss. Second, USF & G argued that the Metro Government did not have the legal authority to order Algernon to demolish the remaining structures on the subject property. USF & G contended that the local government was only empowered to give the property owner a choice of repairing the building commensurate with safety requirements or demolishing them. This argument was based wholly on USF & G’s construction of the municipal regulations authorizing the Metro Government to order demolitions of partially destroyed structures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
821 F.2d 597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/algernon-blair-group-inc-v-united-states-fidelity-guaranty-co-ca11-1987.