ALEXANDER MIROPOLSKY & Another v. WILLIAM CAMPBELL & Another; LAWRENCE BUCCI & Another, Third-Party
Opinion
NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
23-P-401
ALEXANDER MIROPOLSKY & another1
vs.
WILLIAM CAMPBELL & another2; LAWRENCE BUCCI & another,3 third-
party defendants.4
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
The plaintiffs, Alexander and Larissa Miropolsky
(Miropolskys), appeal from so much of a Superior Court judgment
that denied their posttrial petition for attorney's fees. The
Miropolskys requested fees pursuant to a contractual
indemnification provision contained within a "Declaration of
Reservation of Easements and Roadways and Common Driveways"
(declaration). On appeal, the Miropolskys contend that they are entitled to attorney's fees in connection with their breach of easement claim against the defendants, William and Lindsey Campbell (Campbells). Because we conclude that the indemnification provision was not intended to apply to direct claims, we affirm.
Background. This appeal arises from a dispute regarding a declaration for the Hummingbird Lane Subdivision (subdivision). The Miropolskys are the owners and full-time residents of a house in the subdivision now known as 1 Hummingbird Lane (Miropolsky property). The subdivision includes two other homes, one on Lot 3 owned by the Campbells, and the other on Lot 2 owned by the Buccis (collectively, the "Remaining Land"). The Campbells are the developers of the subdivision and in January 2018, they submitted an application to the Westford planning board for approval of a definitive subdivision plan to construct the subdivision.
The Miropolsky property is a parcel subject to the declaration, created by the original owners of the property on which the subdivision was being built.5 The declaration created a fifty-foot-wide access and utility easement running across the
Miropolsky property, called the "Access Easement Area."6 Among other things, the declaration grants a right of way to access the subdivision.
Paragraph 2 of the declaration is entitled "Indemnification" and obligates the Campbells and the Buccis, as owners of the Remaining Land, to:
"[R]estore any land of the servient estate disturbed in the exercise of rights granted hereunder promptly and in a reasonable fashion consistent with the surrounding land and free of refuse. Improvements to the Access Easement Area shall be completed within twelve (12) months of the initial initiation of construction within the Access Easement Area and shall be performed in a good and workmanlike manner so as to minimize all disturbance to the use and enjoyment of the [Miropolsky property]; and if vehicle access or egress to and from the [Miropolsky property] has to be temporarily interrupted for construction purposes, the occupants of the [Miropolsky property] shall be provided with at least seven (7) days written notice and such temporary interruptions shall be limited to a combined period not to exceed 48 hours." Within that same paragraph, the declaration contains an indemnification provision, which provides that "The owner or owners of the Remaining Land hereby agrees to defend, indemnify and hold harmless the owner of the [Miropolsky property] for all costs, losses, expenses and attorney's fees associated with any claim of damage to personal property, injury or death to persons resulting from the exercise of the easements granted herein and for entry upon and activities performed within the Access Easement Area."
In early August 2018, the Campbells began construction on the subdivision. The work included improvements and alterations to the Access Easement Area, the roadway through the area, stormwater drainage, and other excavation site work. The work was not completed until July 2021, after the twelve-month requirement delineated in paragraph 2 of the declaration.
In September of 2019, the Miropolskys filed an action in the Superior Court to enforce their rights under the declaration. Following a three-week trial the jury found in favor of the Miropolskys on their breach of easement claim, and against the Campbells on their breach of easement counterclaim.7 On October 6, 2022, the Miropolskys filed a posttrial petition for attorney's fees and costs with the Superior Court. On October 19, 2022, the judge denied the Miropolskys' petition because "the indemnification clause does not apply to first party claims like this one." Judgment entered on October 21, 2022, and the Miropolskys timely appealed.
Discussion. The Miropolskys contend that the judge erred in denying their petition because the indemnification provision was intended to apply to direct claims. We disagree.
"Our traditional and usual approach to the award of attorney's fees for litigation has been to follow the 'American Rule': in the absence of statute, or court rule, we do not allow successful litigants to recover their attorney's fees and expenses." John T. Callahan & Sons, Inc. v. Worcester Ins. Co., 453 Mass. 447, 449 (2009). "The parties, however, may construct their agreement to provide for the payment of attorney's fees through clear and unambiguous language." K.G.M. Custom Homes, Inc. v. Prosky, 468 Mass. 247, 258 (2014).
The interpretation of an indemnity clause is a question of law for the court. See Post v. Belmont Country Club, Inc., 60 Mass. App. Ct. 645, 647 (2004). Under Massachusetts law, indemnity clauses "are not read with any bias in favor of the indemnitor and against the indemnitee; rather, such provisions are to be fairly and reasonably construed to ascertain the intention of the parties and to effectuate the purpose sought to be accomplished." Urban Inv. & Dev. Co. v. Turner Constr. Co., 35 Mass. App. Ct. 100, 107 (1993). Massachusetts indemnity clauses are not necessarily limited to third-party claims. See Caldwell Tanks, Inc. v. Haley & Ward, Inc., 471 F.3d 210, 216
(1st Cir. 2006). Rather, we interpret each indemnity contract on its own terms, "with the conclusion in a particular case turning on the particular language used against the background of other indicia of the parties' intention." Shea v. Bay State Gas Co., 383 Mass. 218, 222-223 (1981), quoting United States v. Seckinger, 397 U.S. 203, 213 n.17 (1970).
Here, the language of the indemnification provision cannot be "fairly and reasonably construed" to include indemnification for attorney's fees in an action between the parties. Whittle v. Pagani Bros. Constr. Co., 383 Mass. 796, 798 (1981). The Miropolskys rely on language in the indemnification provision stating that the owner agrees to "defend, indemnify and hold harmless the owner of the [Miropolsky property] for all costs, losses, expenses and attorney's fees." They place special emphasis on "all costs" as proof that the parties' intent was to apply the indemnification provision to a direct claim. However, viewing the declaration as a whole, we conclude that the indemnification provision was not intended to apply to a direct claim. This is so for various reasons.
Free access — add to your briefcase to read the full text and ask questions with AI
ALEXANDER MIROPOLSKY & Another v. WILLIAM CAMPBELL & Another; LAWRENCE BUCCI & Another, Third-Party (ALEXANDER MIROPOLSKY & Another v. WILLIAM CAMPBELL & Another; LAWRENCE BUCCI & Another, Third-Party) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.