Alessi Equip., Inc. v. Am. Piledriving Equip., Inc.

CourtCourt of Appeals for the Second Circuit
DecidedNovember 21, 2025
Docket22-2317
StatusPublished

This text of Alessi Equip., Inc. v. Am. Piledriving Equip., Inc. (Alessi Equip., Inc. v. Am. Piledriving Equip., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alessi Equip., Inc. v. Am. Piledriving Equip., Inc., (2d Cir. 2025).

Opinion

22-2317 Alessi Equip., Inc. v. Am. Piledriving Equip., Inc.

United States Court of Appeals For the Second Circuit

August Term 2023

Argued: November 7, 2023 Decided: November 21, 2025

No. 22-2317

ALESSI EQUIPMENT, INC.,

Plaintiff-Counter-Defendant-Appellee,

v.

AMERICAN PILEDRIVING EQUIPMENT, INC.,

Defendant-Counter-Claimant-Appellant.

Appeal from the United States District Court for the Southern District of New York No. 18-cv-3976, Judith C. McCarthy, Magistrate Judge.

Before: WALKER, RAGGI, SULLIVAN, Circuit Judges.

American Piledriving Equipment, Inc. (“APE”), a manufacturer of construction equipment, appeals from the amended December 30, 2022 judgment of the United States District Court for the Southern District of New York (McCarthy, M.J.) awarding damages, including pre-judgment interest, to APE’s distributor, Alessi Equipment, Inc. (“Alessi”), for breach of a distribution agreement executed by the parties in 2012 (the “2012 Distributor Agreement”). On January 6, 2022, the district court granted summary judgment against APE as to liability on Alessi’s claim for breach of the 2012 Distributor Agreement, and in favor of APE as to liability and damages on its breach-of-contract counterclaim against Alessi. A jury thereafter awarded Alessi $920,846.70 in damages arising from APE’s breach. The district court later denied APE’s motion for judgment as a matter of law pursuant to Federal Rule of Civil Procedure 50(b), or in the alternative, for a new trial or remittitur pursuant to Rule 59(a). The district court also awarded Alessi pre-judgment interest over APE’s objection that Alessi’s request for such interest was untimely under Federal Rule of Civil Procedure 59(e).

In a summary order filed today, we reject APE’s challenges on appeal to the district court’s grant of summary judgment as to liability on Alessi’s breach-of- contract claim, as well as its denial of APE’s post-trial motion under Rule 50(b) and Rule 59(a). Here, we address APE’s argument that the district court erred in awarding Alessi prejudgment interest and conclude that Alessi’s motion for that interest pursuant to Rule 59(e) was timely filed. Specifically, we hold that the purported judgment entered by the district court on June 23, 2022 was not sufficiently “final,” and thus did not trigger the 28-day deadline for filing the Rule 59(e) motion, because it omitted any reference to APE’s successful counterclaim or to the award of prejudgment interest to which each party was entitled, and did not satisfy the requirements for the entry of a judgment under Rule 58. We therefore AFFIRM the judgment of the district court as to its award of prejudgment interest to Alessi.

AFFIRMED.

BRIAN D. WALLER, Peckar & Abramson, P.C., New York, NY, for Defendant-Appellant.

KRISTOPHER M. DENNIS, The Law Office of Kristopher M. Dennis, New York, NY (Keith A. Lavallee, Lavallee Law Offices PLLC, Farmingdale, NY, on the brief), for Plaintiff- Appellee.

RICHARD J. SULLIVAN, Circuit Judge:

American Piledriving Equipment, Inc. (“APE”), a manufacturer of

construction equipment, appeals from the amended December 30, 2022 judgment

2 of the United States District Court for the Southern District of New York

(McCarthy, M.J.) awarding damages, including pre-judgment interest, to APE’s

distributor, Alessi Equipment, Inc. (“Alessi”), for breach of a distribution

agreement executed by the parties in 2012 (the “2012 Distributor Agreement”). 1

On January 6, 2022, the district court granted summary judgment against APE as

to liability on Alessi’s claim for breach of the 2012 Distributor Agreement and in

favor of APE as to liability and damages on its breach-of-contract counterclaim

against Alessi. A jury thereafter awarded Alessi $920,846.70 in damages arising

from APE’s breach. The district court later denied APE’s motion for judgment as

a matter of law pursuant to Federal Rule of Civil Procedure 50(b), or in the

alternative, for a new trial or remittitur pursuant to Rule 59(a). The district court

also awarded Alessi pre-judgment interest over APE’s objection that Alessi’s

request for such interest was untimely under Federal Rule of Civil Procedure 59(e).

In a summary order filed today, we reject APE’s challenges on appeal to the

district court’s grant of summary judgment as to liability on Alessi’s breach-of-

contract claim, as well as its denial of APE’s post-trial motion under Rule 50(b) and

Rule 59(a). Here, we address APE’s argument that the district court erred in

1Magistrate Judge McCarthy handled the case for all purposes with the consent of the parties pursuant to 28 U.S.C. § 636(c). 3 awarding Alessi prejudgment interest and conclude that Alessi’s motion for that

interest pursuant to Rule 59(e) was timely filed. Specifically, we hold that the

purported judgment entered by the district court on June 23, 2022 was not

sufficiently “final,” and thus did not trigger the 28-day deadline for filing the Rule

59(e) motion, because it omitted any reference to APE’s successful counterclaim or

to the award of prejudgment interest to which each party was entitled, and did not

satisfy the requirements for the entry of a judgment under Rule 58. We therefore

AFFIRM the judgment of the district court as to its award of prejudgment interest

to Alessi.

I. BACKGROUND

Alessi commenced this action in May 2018, alleging, among other things,

that APE breached the 2012 Distributor Agreement by selling equipment covered

by that agreement directly to third parties. After Alessi filed an amended

complaint on July 24, 2018, APE filed an answer and asserted counterclaims

against Alessi on March 19, 2019, alleging breach of contract and unjust

enrichment arising from Alessi’s failure to remit payment to APE for amounts

owed under a rental agreement entered into by the parties in January 2016 (the

“Rental Agreement”), as well as for various purchases that Alessi made from APE

4 between November 2016 and December 2017 (the “Purchase Agreements”). As

relief, APE requested damages equaling the amounts owed under those

agreements – a total of $52,505.92 – as well as “[s]tatutory interest accruing on

Alessi’s indebtedness . . . from the date of its default through the present.” Dist.

Ct. Doc. No. 36 at 23.

After the completion of discovery, the parties consented to have the case

heard by a magistrate judge, and then each moved for summary judgment. On

January 6, 2022, the district court granted summary judgment as to liability on

Alessi’s contract claim for breach of the 2012 Distributor Agreement, but

concluded that the issue of damages would have to be decided at trial. At the same

time, the district court granted summary judgment to APE with respect to both

liability and damages on its breach-of-contract counterclaim regarding Alessi’s

failure to remit payment under the Rental Agreement and Purchase Agreements.

Finally, the court dismissed all remaining claims and counterclaims.

After a four-day trial held in June 2022, the jury returned a verdict awarding

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Indrelunas
411 U.S. 216 (Supreme Court, 1973)
Bankers Trust Co. v. Mallis
435 U.S. 381 (Supreme Court, 1978)
Osterneck v. Ernst & Whinney
489 U.S. 169 (Supreme Court, 1989)
Winslow v. Federal Energy Regulatory Commission
587 F.3d 1133 (D.C. Circuit, 2009)
Crowe v. Bolduc
365 F.3d 86 (First Circuit, 2004)
Kanematsu-Gosho, Ltd. v. M/T Messiniaki Aigli
805 F.2d 47 (Second Circuit, 1986)
Angelo Fiataruolo, Angelo Veno v. United States
8 F.3d 930 (Second Circuit, 1993)
Cooper v. Town of East Hampton
83 F.3d 31 (Second Circuit, 1996)
Selletti v. Carey
173 F.3d 104 (Second Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Alessi Equip., Inc. v. Am. Piledriving Equip., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/alessi-equip-inc-v-am-piledriving-equip-inc-ca2-2025.