Aleksey Kizlov v. Brookhill Landscape And Construction, Llc

CourtCourt of Appeals of Washington
DecidedOctober 28, 2019
Docket78847-7
StatusUnpublished

This text of Aleksey Kizlov v. Brookhill Landscape And Construction, Llc (Aleksey Kizlov v. Brookhill Landscape And Construction, Llc) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aleksey Kizlov v. Brookhill Landscape And Construction, Llc, (Wash. Ct. App. 2019).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

ALEKSEY KOZLOV and IRINA KOZLOV, husband and wife, No. 78847-7-I

Appellants, DIVISION ONE

v. UNPUBLISHED OPINION

BROOKHILL LANDSCAPE AND CONSTRUCTION, LLC, a Washington limited liability company,

Respondent

IRONSHORE INDEMNITY INC., a corporation domiciled in the State of Minnesota, bond account number 100178180,

Defendant. FILED: October 28, 2019

APPELWICK, C.J. — Kozlov appeals from summary judgment dismissing his

breach of contract claims on the basis of accord and satisfaction. Brookhill

tendered a check in complete satisfaction of all amounts due and owing, and

Kozlov negotiated the check. Kozlov argues the check could not be consideration

for an accord and satisfaction, because it was merely a refund of Kozlov’s own

funds. We affirm. No. 78847-7-1/2

FACTS

On December 6, 2015, Alexey and Irma Kozlov entered into a contract with

Brookhill Landscape and Construction LLC (Brookhill) for landscaping work on

their home. The contract included various projects to be completed at a cost of

$65 per hour and a 20 percent markup on materials. The estimated cost was

$343,000 plus tax. The Kozlovs paid an initial deposit of $137,200, and agreed to

periodic payments while Brookhill completed work.

On April 16, 2016, the parties revised the contract to include additional

projects, raising the estimated cost to $420,000. They also agreed the work would

be completed before July 16, 2016. The Kozlovs paid Brookhill $137,200 in

December, 2015, $100,000 in April 2016, and $100,000 in July 2016. The Kozlovs

continued to request additional work until July 2016.

In July2016, the relationship between the parties began to deteriorate. The

work was not completed by July 16. The Kozlovs claimed that Brookhill’s crew

was not showing up regularly or with sufficient staff to make progress on the job.

They further contended that Spencer Bowhay, the manager at Brookhill, was

unresponsive and combative in response to inquiries about the project. On July

27, 2016, the Kozlovs’ attorney sent Brookhill a letter indicating their desire to

terminate the contract. The attorney demanded that Brookhill return the most

recent $100,000 payment. The letter indicated that a third party would assess

additional damages owed to the Kozlovs.

In response, Brookhill sent the Kozlovs’ attorney a letter, enclosing a check

and a copy of the accounting ledger of the contract. The check was for $23,611,

2 No. 78847-7-1/3

which, according to Brookhill and the accounting ledger, was the difference

between the total payments received and the total invoices. The letter said, that

the check was given “in full settlement of all amounts owing under the contract.”

And, the back of the check said, “Full and final payment in complete satisfaction àf

all amounts due and owing.” The Kozlovs deposited the check on August 24, 2016.

The Kozlovs filed this lawsuit 19 months later, on March 18, 2019. They

now seek almost $400,000 in damages they claim to have paid to another

contractor to complete the projects and $217,000 in restitution to recover amounts

paid to Brookhill. Brookhill asserted an accord and satisfaction as an affirmative

defense, and moved for summary judgment on that basis. The trial court granted

summary judgment to Brookhill. The Kozlovs appeal.

DISCUSSION

The Kozlovs contend that accord and satisfaction fails for want of

consideration. Specifically, they claim that Brookhill’s payment of $23,611 cannot

serve as consideration because it was a refund of the Kozlovs’ money.

Summary judgment is appropriate when no genuine issues exist as to any

material fact and the moving party is entitled to judgment as a matter of law. Keck

v. Collins, 184 Wn.2d 358, 370, 357 P.3d 1080 (2015). We review summary

judgment decisions de novo. ki

The doctrine of accord and satisfaction allows parties to agree to discharge

duties owed under a contract through a performance different than the one owed.

See Nw. Motors, Ltd. v. James, 118 Wn.2d 294, 303, 822 P.2d 280 (1992). Accord

and satisfaction requires that the parties have (1) a bona tide dispute; (2) an

3 No. 78847-7-1/4

agreement to settle that dispute; and (3) perIormance of that agreement. Paopao

v. Dep’t. of Soc. & Health Servs., 145 Wn. App. 40, 46, 185 P.3d 640 (2008).

In their termination letter, the Kozlovs requested a refund of their previous

$100,000 deposit and indicated that they would have additional demands for

damages. Brookhill responded with a different amount. It invoiced unbilled labor

and material costs and deducted them from the $100,000 advance, and then

offered the remaining $23,611 in full payment of all amounts due. There was,

therefore, a bona fide dispute between the parties over what was owed to the

Kozlovs.

The Kozlovs contend that this payment was in fact an independent

obligation, separate of other potential debts under the contract. They claim this is

so because Brookhill did not dispute that this money was owed to the Kozlovs.

Therefore, they argue that to keep this amount would have constituted conversion

or larceny. In their estimation, because Brookh ill conceded that it owed the amount

offered, it cannot serve as an accord and satisfaction but rather was the fulfilment

of an independently owed obligation.

The Kozlovs point to Field Lumber v. Petty, 9 Wn. App. 378, 512 P.2d 764

(1973), to support this proposition. In that case Petty attempted an accord and

satisfaction by tendering payment of $500 despite acknowledging that he owed

$1,092 j~ at 379. Field Lumber asserted that Petty owed $1,752. IcL at 379-80.

The court ruled that the $500 payment could not constitute an accord and

satisfaction in spite of the bona fide dispute of the total amount due, because it

was less than Petty himself acknowledged that he owed. See Id. at 380-81. It

4 No. 78847-7-1/5

stated that accord and satisfaction is not applicable “where a portion of the alleged

debt in excess of the amount paid is acknowledged and not in dispute.” Id. at 379

(emphasis added).

Field Lumber answers the question of when new consideration is required

for an accord and satisfaction. Id. at 380. Under Field Lumber, new consideration

is required when the debtor tenders any amount less than they acknowledge to the

creditor that they owe. k~. Where, as here, the debtor and creditor disagree on

the amount owed, new consideration is required only when the debtor attempts to

settle by tendering an amount less than the debtor acknowledges is owed. See

id. Where the debtor tenders what they acknowledge they owe in settlement of

the dispute, no new consideration is required. ki at 379.

Unlike Field Lumber, here Brookhill had not acknowledged a debt in excess

of the amount it tendered. The Kozlovs contended they were owed $100,000 plus

yet-to-be-determined damages. Brookhill contended the Kozlovs were owed

$23,611, and tendered that amount. Therefore, Field Lumber does not apply and

no new consideration is required.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northwest Motors, Ltd. v. James
822 P.2d 280 (Washington Supreme Court, 1992)
Field Lumber Co. v. Petty
512 P.2d 764 (Court of Appeals of Washington, 1973)
Evans v. Columbia International Corp.
478 P.2d 785 (Court of Appeals of Washington, 1970)
Paopao v. STATE, DSHS
185 P.3d 640 (Court of Appeals of Washington, 2008)
Keck v. Collins
357 P.3d 1080 (Washington Supreme Court, 2015)
Paopao v. Department of Social & Health Services
145 Wash. App. 40 (Court of Appeals of Washington, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Aleksey Kizlov v. Brookhill Landscape And Construction, Llc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aleksey-kizlov-v-brookhill-landscape-and-construction-llc-washctapp-2019.