Alden v. Central Power Electric Cooperative, Inc.

168 F. Supp. 19, 1958 U.S. Dist. LEXIS 3306
CourtDistrict Court, D. North Dakota
DecidedSeptember 2, 1958
DocketCiv. No. 3500
StatusPublished
Cited by3 cases

This text of 168 F. Supp. 19 (Alden v. Central Power Electric Cooperative, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alden v. Central Power Electric Cooperative, Inc., 168 F. Supp. 19, 1958 U.S. Dist. LEXIS 3306 (D.N.D. 1958).

Opinion

DEVITT, District Judge.

This is an action by a Chicago engineering firm against a North Dakota cooperative power association to recover approximately $104,000 allegedly due for work in designing and supervising the construction of an 8-million-dollar power generating station at Voltaire, in northwestern North Dakota.

The plaintiffs and the Ulteig Engineering Corporation of Fargo, North Dakota, contracted to prepare plans and supervise the construction of the cooperative power plant for a fee based on an agreed formula with a top ceiling of $500,000. The plaintiffs claim that there were changes in the scope of the work, occasioned principally by changes in boiler [20]*20design not contemplated by the contract, and that they are entitled to additional compensation.

The defendant denies that any additional compensation is due. It states that the engineering service contract specifically provided that $500,000 was the maximum engineering fee to be paid unless the parties agreed in writing, and in advance, for increased compensation and that the parties did not do that. The defendant also contends that alterations were made in the plans by the engineer without consultation with the owner, contrary to the terms of the contract, and that the engineer was specifically required to make necessary changes requested by the owner.

The plaintiffs argue that although the contract placed a specific $500,000 ceiling on their compensation, extra work was performed and the conduct and actions of the defendant in connection with it constituted a waiver of that provision.

The defendant has filed a counterclaim based on the theory that the plaintiffs unreasonably delayed the preparation of proper plans and specifications, insisted on impractical plans over the protest of the defendant, and were dilatory in carrying out the terms of their contract as the result of which the plant was belatedly opened and defendant was deprived of the use of the plant for an 8-month period; it is alleged that defendant was compelled to pay heating costs for the unusable plant during one winter, was obligated to pay overtime wages for labor in order to reduce the period of belated opening, was obligated to pay some $10,000 for excessive amounts of electric cable which were unnecessarily ordered by the plaintiffs, and incurred other damages in that plaintiffs improperly excavated and filled the area around the substation. It seeks damages in the sum of about $400,000.

The plaintiffs are partners in the engineering business and specialize in the design and supervision of construction of power stations. The defendant is a corporation organized under the cooperative laws of the State of North Dakota and was formed by eight other North Dakota electrical cooperatives for the purpose of erecting a power station to furnish electrical energy to the members of the eight cooperatives situated principally in central and northwestern North Dakota in an area near the recently completed Garrison Dam.

In the first instance, defendant engaged the Ulteig Engineering Corporation of Fargo, to serve as the engineer for the construction of the planned power plant. Ulteig in turn solicited the professional assistance of plaintiffs. The agreement between the parties is contained in three contracts dated November 26, 1949 between plaintiffs, defendant and Ulteig Engineering Corporation. By its terms, the principal responsibility for the project rested with the plaintiffs. Defendant was to pay compensation directly to the plaintiffs. Application was made to the Rural Electrification Administration of the Department of Agriculture (REA) for a 100% loan to finance the project. Under the statutes and the established policy of the REA, it exercised a rather minute supervision over the project at every stage. The plant was constructed during the period 1950-1952.

In the summer of 1949 the plaintiffs, acting through their principal partner, Vern E. Alden, established first contact with the members of the Board of Directors of the defendant corporation. In August of that year Alden prepared a so-called power plant study, which was to accompany the defendant’s application to the REA for the required loan. This study contemplated the use of two boilers, each having a continuous generating capacity of 240,000 pounds per hour with a maximum capacity of 260,000 pounds per hour for two-hour periods. Later, after consultation with boiler manufacturers and a study of the peculiar physical space requirements for a plant burning North Dakota lignite coal, Alden apparently decided that smaller boilers would be more suitable. He therefore recommended and proposed the use of boilers each having a continuous capacity [21]*21of 195,000 pounds per hour with a maximum capacity of 225,000 pounds per hour for two-hour periods. This size boiler will subsequently be referred to as the smaller boiler, and the previously mentioned one of greater generating capacity will be referred to as the larger boiler. Alden submitted preliminary plans and specifications, providing for the use of the smaller boilers, to the Board of Directors of the defendant corporation. At a meeting in November of 1949, the Board approved such. The REA never did approve these preliminary plans and specifications. There is conflict in the evidence as to whether or not the Board actually understood, in approving such preliminary plans and specifications, that they provided for the use of smaller boilers.

In an appearance before defendant’s Board of Directors during the negotiation period in the summer of 1949, Alden represented that plaintiffs’ maximum compensation would be $500,000 but that if he could employ the plans and specifications used in the construction of a similar power plant at Cassville, Wisconsin, it would be possible to reduce the total compensation by some $50,000 to $75,000. The Cassville plant was constructed with the larger type boilers. Both parties apparently contemplated duplicating the Cassville plant, but there is conflict in the evidence as to whether this also included an exact duplication of the larger boilers there employed.

After the Board approved the proposed engineering service contract at its meeting in November, 1949, some of the Board members went to Wisconsin to study other power plants. During that trip, and on or about January 13, 1950, members of the Board claim that they first learned that the plans for the proposed plant in North Dakota contemplated the use of the so-called smaller boiler. They expressed doubt as to the wisdom of using the smaller boilers, claimed ignorance of the fact that they had approved the use of such, and contended that the understanding was that the larger boilers proposed in the so-called power study, and as used in the Cassville plant, were to be employed. As the result of this possible misunderstanding, a meeting was held in the REA offices in Washington on January 25-26, 1950. Shortly prior to this time, a contract had been let for the smaller boilers to the Combustion Engineering Corporation. Representatives of that company, of the plaintiffs, of the defendant, of Ulteig Engineering Corporation and of the REA were present at the Washington meetings.

Vern E. Alden testified that at the meeting he strongly urged the use of the smaller boilers and said that the larger ones would be uneconomical and that substituting the larger ones at that stage would unduly delay construction of the plant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
168 F. Supp. 19, 1958 U.S. Dist. LEXIS 3306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alden-v-central-power-electric-cooperative-inc-ndd-1958.