Aldea Dos Vientos v. CalAtlantic Group, Inc.

CourtCalifornia Court of Appeal
DecidedFebruary 6, 2020
DocketB291731
StatusPublished

This text of Aldea Dos Vientos v. CalAtlantic Group, Inc. (Aldea Dos Vientos v. CalAtlantic Group, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aldea Dos Vientos v. CalAtlantic Group, Inc., (Cal. Ct. App. 2020).

Opinion

Filed 2/6/20 CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION SIX

ALDEA DOS VIENTOS, 2d Civil No. B291731 (Super. Ct. No. 56-2013- Plaintiff and Appellant, 00445377-CU-OR-VTA) (Ventura County) v.

CALATLANTIC GROUP, INC.,

Defendant and Respondent.

It is reputed that condominium projects have three phases—planning, building, and the lawsuit. Obviously, this case is an example of the third phase. We are optimistic there are numerous condominium projects that experience only the first two phases. A condominium association sued the developer alleging construction defects. The association’s governing documents require arbitration of such disputes and a vote of at least 51 percent of the association’s membership prior to beginning arbitration. The association began arbitration without obtaining a vote of its members. Later, the members overwhelmingly voted to pursue the arbitration. The arbitrator dismissed the arbitration for lack of a membership vote prior to its commencement. The trial court confirmed the award and entered judgment for the developer. We reverse. We disagree with Branches Neighborhood Corp. v. CalAtlantic Group, Inc. (2018) 26 Cal.App.5th 743 which holds otherwise. FACTS Aldea Dos Vientos is a condominium project in Thousand Oaks. The project is a common interest development subject to the Davis-Stirling Common Interest Development Act (Civ. Code, § 4000, et seq., hereafter Davis-Stirling Act). The project is governed by the Aldea Dos Vientos homeowners association (Association) and recorded covenants, conditions, and restrictions (CC&R’s). CalAtlantic Group, Inc. is the successor to the developer of the project (Developer). The Association claims it discovered $5.6 million in construction defects in the common areas and individual units. Beginning in November 2012, the Association engaged in discussions with the Developer about the defects. In November 2013, when the discussions were unproductive, the Association brought suit against the Developer. The trial court stayed the litigation on the parties’ stipulation to enter into mediation, and if that failed, arbitration administered by JAMS. Mediation failed to produce a settlement. Section 7.01A of the CC&R’s requires that all disputes between the Developer and the Association or its members, including construction defect claims, be resolved by arbitration. On June 24, 2016, the Association filed a demand for arbitration. The Developer filed an answer in arbitration for the first time raising section 7.01B of the CC&R’s (hereafter section 7.01B) as a defense. Section 7.01B provides: “Required Vote to Make Claim. Prior to filing a claim pursuant to the ADR Provisions, the Association must obtain the

2 vote or written consent of Owners other than Declarant who represent not less than fifty-one percent (51%) of the Association’s voting power (excluding the voting power of Declarant).” The Association admitted that it had not obtained a vote from its members prior to beginning arbitration. The arbitrator stayed the arbitration to allow the Association to petition the trial court to resolve the issue of arbitrability. In the meantime, the Association obtained the approval of over 99 percent of its members to continue the arbitration, with only one member voting against continuing out of 116 votes. The Association moved the trial court to rule that the retroactive vote allowed arbitration to proceed. The court denied the motion on the ground that arbitrability was a matter for the arbitrator to decide. The matter returned to the arbitrator. The arbitrator heard oral argument on motions for summary judgment by the Association and the Developer concerning interpretation of section 7.01B. The Developer filed a motion to dismiss based on the Association’s failure to comply with section 7.01B prior to beginning arbitration. The Association filed a cross-motion on the ground that the ratifying vote of the Association members satisfied section 7.01B. The Association also filed a second demand for arbitration. The arbitrator summarily dismissed the original demand for arbitration. The Developer moved the trial court to confirm the arbitrator’s award. The court concluded that the dismissal of the arbitration constituted a final determination of the rights of the parties notwithstanding the second demand for arbitration. The

3 court entered judgment in favor of the Developer and against the Association. DISCUSSION I. Arbitrator Exceeded His Power The trial court shall vacate an arbitration award if “[t]he arbitrators exceeded their powers and the award cannot be corrected without affecting the merits of the decision upon the controversy submitted.” (Code Civ. Proc., § 1286.2, subd. (a)(4).) Arbitrators exceed their power by issuing an award that violates a party’s unwaivable statutory rights or that contravenes an explicit legislative expression of public policy. (Richey v. AutoNation, Inc. (2015) 60 Cal.4th 909, 916.) That is particularly true of the rights and policies governing the conduct of the arbitration itself. (Sargon Enterprises, Inc. v. Browne George Ross LLP (2017) 15 Cal.App.5th 749, 765.) Section 7.01B contravenes explicit legislative expressions of public policy. (a) Housing Policy The Legislature stated that “housing is of vital statewide importance to the health, safety, and welfare of the residents of this state . . . .” (Health & Saf. Code, § 50001.) The Legislature intended housing to be free of substantial construction defects. (See Civ. Code, §§ 896 [listing construction defects for which the developer is liable]; 897 [developer liable for defects not expressly listed]; 941, subd (a) [10-year statute of limitations on actions for construction defects].) Provisions such as section 7.01B contravene statutory policy by giving the Developer the unilateral power to bar actions for construction defects.

4 (b) Policy Against Unreasonable Servitudes The Davis-Stirling Act prohibits the enforcement of unreasonable provisions in the CC&R’s. (Civ. Code, § 5975, subd. (a) [“The covenants and restrictions in the declaration shall be enforceable equitable servitudes, unless unreasonable”].) Here, section 7.01B as interpreted by the arbitrator is not just unreasonable, it is unconscionable. It gives the Developer veto power over the Association’s claims in spite of the members’ vote to proceed with the arbitration. The Developer relies on Branches Neighborhood Corp. v. CalAtlantic Group, Inc., supra, 26 Cal.App.5th 743 (Branches). After the trial court affirmed the arbitrator’s award, the Fourth District of the Court of Appeal, Division Three decided Branches. The facts in Branches are similar to the facts here and involved the same developer and arbitrator. In Branches, a condominium development’s CC&R’s contained a provision similar to section 7.01B, requiring the condominium association to obtain a vote of at least 51 percent of its members before beginning arbitration against the project’s developer. The association began arbitration without seeking a vote. When the developer sought to dismiss the arbitration, the association obtained a ratifying vote from over 51 percent of its members. Nevertheless, the arbitrator dismissed the arbitration and the trial court entered judgment against the association. The Court of Appeal affirmed. The court rejected the association’s argument that the ratification vote was sufficient, pointing out that the CC&R’s require the vote before arbitration. (Branches, supra, 26 Cal.App.5th at p. 758.) The court also rejected the association’s argument that the arbitrator exceeded his powers by issuing an award that violates a party’s unwaivable statutory

5 rights or that contravenes an explicit legislative expression of public policy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richey v. Autonation, Inc.
341 P.3d 438 (California Supreme Court, 2015)
Sargon Enters., Inc. v. Browne George Ross LLP
223 Cal. Rptr. 3d 588 (California Court of Appeals, 5th District, 2017)
Branches Neighborhood Corp. v. Calatlantic Grp., Inc.
237 Cal. Rptr. 3d 411 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Aldea Dos Vientos v. CalAtlantic Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/aldea-dos-vientos-v-calatlantic-group-inc-calctapp-2020.